Addendum #2 - 751-22464 Piers Gorge Access.pdf

PDF 2 MB Posted

Attached to
751/22464. JBB; Menominee River RA - Piers Gorge Access
Solicitation number
RFQ 171 250000000420 3
Issued by
Delta County, Michigan

About this file

This is Addendum #2 issued on June 5, 2025, by Sanders & Czapski Associates, PLLC on behalf of the Michigan Department of Natural Resources for the Menominee River Recreation Area - Piers Gorge Access project located in Norway, Michigan (File No. 751/22464.JBB). The addendum clarifies and revises information contained in the Project Manual and Drawings, and bidders must acknowledge receipt of this addendum on their Bid Forms. The date, time, and location for bid receipt remain unchanged. Key revisions include clarification that the EGLE permit will be issued by bulletin, revised site plan sheets (Sheet 4 and Sheet 5) showing wetland boundaries and details, and assignment of contractor responsibilities for obtaining and paying for a Work in Right-of-way Permit from the Dickinson County Road Commission.

The contractor is responsible for securing all permits and bearing associated costs, including maintaining required barricades. Regarding site conditions, the contractor must limit equipment traffic across the site from the east end of the bridge to the west end of the boardwalk to existing trail surfaces or track bog mats placed and maintained by the contractor to minimize ground disturbance. All excess soils from construction activities must be disposed of in upland areas not on State-owned land, and this disposal obligation remains the contractor's responsibility. The Wetland and Inland Lakes and Streams Floodplain permit is currently under EGLE review; pending its issuance, the stated conditions apply as binding requirements equivalent to permit conditions. Detail 1 of the Longitudinal Section FRP Bridge has been revised to show the entire bridge length and its relationship to surface water of the intermittent stream and wetlands.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Menominee River Recreation Area – Piers Gorge Access

ADDENDUM #2

June 5, 2025

Project: Menominee River Recreation Area – Piers Gorge Access

Department of Natural Resources Norway, Michigan 49855

File No: 751/22464.JBB Agency: Department of Natural Resources

Issued by: Sanders & Czapski Associates, PLLC 105 Country Lane Marquette, Michigan 49855

Date: June 5, 2025

Notice to Bidders:

This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement.

The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form(s)

The date, time and location for receipt of bids is unchanged by this Addendum.

Attachments to this Addendum:

o Sheet 4 – Enlarged Site Plan: revised as part of Addendum #2 dated

June 5, 2025 o Sheet 5 - Details / Schedules / Notes: revised as part of Addendum #2 dated June 5, 2025

The Drawings:

A. Cover Sheet – Permit Requirements

a. Clarify: The EGLE permit will be issued by Bulletin.

b. Change: It is the Contractors responsibility to secure and pay all costs for a

“Work in Right-of-way Permit” from the Dickinson County Road Commission, and to place and maintain barricade as noted on Sheet 3 of The Drawings.

B. Sheet 4 – Enlarged Site Plan (attached)

a. Sheet 4 issued as a part of Addendum #2 shows the location of wetland boundary.

b. Wetland and inland lakes and streams floodplain permit has been applied for with EGLE. It is currently in review. In the absence of the permit the following conditions will apply and the Contractor is bound to meet them as though they are a condition of the EGLE permit. Any and all equipment traffic across the site from the east end of the bridge to the west end of the boardwalk that does not occur on the existing trail surface shall be limited to track (bog) mats placed and maintained by the contractor to minimize disturbance of existing grade. Also, disposal of excess soils resulting from the construction and not salvaged for re-use is the responsibility of the contractor and shall be in an upland area and not on State Owned land. The EGLE permit will be issued by bulletin.

C. Sheet 5 – Details / Schedules / Notes (attached)

a. Revise: ‘Detail 1, Longitudinal Section FRP Bridge’, to show entire length of

FRP Bridge, also showing relationship to surface water of intermittent stream and wetlands.

END OF ADDENDUM #2