Addendum #2 is a contract document for the Menominee River Recreation Area – Piers Gorge Access project, issued by Sanders & Czapski Associates, PLLC on behalf of the Michigan Department of Natural Resources located in Norway, Michigan. The addendum revises and clarifies information in the original project manual and drawings, specifically addressing permit requirements, site access, and construction details for a boardwalk and FRP (Fiber Reinforced Polymer) bridge in a sensitive environmental area. The document indicates that an EGLE (Environment, Great Lakes, and Energy) permit is pending and provides interim guidelines for contractors regarding equipment movement, soil disposal, and wetland preservation.
The addendum requires the contractor to secure a "Work in Right-of-way Permit" from the Dickinson County Road Commission and details specific environmental protections, such as using track (bog) mats to minimize ground disturbance and ensuring excess soils are disposed of in upland areas. The project involves constructing a boardwalk and bridge across an area with wetlands and an intermittent stream, with careful consideration for minimizing environmental impact. The contractor will be responsible for maintaining existing trails, managing equipment traffic, and following strict guidelines to protect the natural landscape during construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Menominee River Recreation Area – Piers Gorge Access
ADDENDUM #2
June 5, 2025
Project: Menominee River Recreation Area – Piers Gorge Access
Department of Natural Resources Norway, Michigan 49855
File No: 751/22464.JBB Agency: Department of Natural Resources
Issued by: Sanders & Czapski Associates, PLLC 105 Country Lane Marquette, Michigan 49855
Date: June 5, 2025
Notice to Bidders:
This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement.
The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form(s)
The date, time and location for receipt of bids is unchanged by this Addendum.
Attachments to this Addendum:
o Sheet 4 – Enlarged Site Plan: revised as part of Addendum #2 dated
June 5, 2025 o Sheet 5 - Details / Schedules / Notes: revised as part of Addendum #2 dated June 5, 2025
The Drawings:
A. Cover Sheet – Permit Requirements
a. Clarify: The EGLE permit will be issued by Bulletin.
b. Change: It is the Contractors responsibility to secure and pay all costs for a
“Work in Right-of-way Permit” from the Dickinson County Road Commission, and to place and maintain barricade as noted on Sheet 3 of The Drawings.
B. Sheet 4 – Enlarged Site Plan (attached)
a. Sheet 4 issued as a part of Addendum #2 shows the location of wetland boundary.
b. Wetland and inland lakes and streams floodplain permit has been applied for with EGLE. It is currently in review. In the absence of the permit the following conditions will apply and the Contractor is bound to meet them as though they are a condition of the EGLE permit. Any and all equipment traffic across the site from the east end of the bridge to the west end of the boardwalk that does not occur on the existing trail surface shall be limited to track (bog) mats placed and maintained by the contractor to minimize disturbance of existing grade. Also, disposal of excess soils resulting from the construction and not salvaged for re-use is the responsibility of the contractor and shall be in an upland area and not on State Owned land. The EGLE permit will be issued by bulletin.
C. Sheet 5 – Details / Schedules / Notes (attached)
a. Revise: ‘Detail 1, Longitudinal Section FRP Bridge’, to show entire length of
FRP Bridge, also showing relationship to surface water of intermittent stream and wetlands.
END OF ADDENDUM #2