Addendum 2 12.16.24.pdf
PDF 303 KB Posted
- Attached to
- Bid # 1055 - Walley School Rehabilitation /Reuse
- Solicitation number
- 1055
- Issued by
- Bristol County, Rhode Island
About this file
Addendum 2, dated 12/16/2024, is issued by Brewster Thornton Group Architects, LLP for the Walley School Interior Package project located at 260 High Street in Bristol, Rhode Island. The addendum modifies the original bidding documents from 10/22/2024 and addresses several key changes to the project manual and drawings, including modifications to Section 01 5000, deletion of specific details, and revisions to stair finishing requirements. The document includes responses to contractor questions about existing on-site contractors, electrical coordination, temporary facilities, project signage, and bid date extensions.
The addendum indicates that multiple contractors are currently working on the building, including Westway Construction, F & S Electric, and Temptec Mechanical. The project involves interior package work for the Walley School rehabilitation, which is part of a larger community resources and senior center conversion. Notably, the bid date has been extended, and contractors are advised to coordinate with existing awarded contractors. The scope includes refinishing stairs, coordinating electrical services, and working within a historically significant building district that will require periodic reviews by historic preservation authorities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Walley School Interior Package 260 High Street, Bristol, RI 02809
Addendum 2: 12/16/2024
BTGA Project #2211 ADDENDUM 2 Brewster Thornton Group Architects, LLP SECTION 00 9000 - 2
SECTION 00 9000
ADDENDUM 2
1.01 GENERAL
This Addendum forms a part of the Contract Documents and modifies the Bidding Documents dated 10/22/2024. Acknowledge receipt of this Addendum in the space provided in the Bid Form. Failure to do so may disqualify the Bidder.
This Addendum consists of 2 pages plus the following:
1. Revised Invitation for Bid
2. SKA – INT1 dated 12/16/2024
1.02 CHANGES TO THE PROJECT MANUAL
1. Section 01 5000, Sub-Paragraph 3.3C, add, “Coordinate electrical power services with existing awarded electrical contractor”.
2. Delete Section 01 5000, Sub-Paragraph 2.4.
3. Delete Section 01 5000, Sub-Paragraph 3.4B.
1.03 CHANGES TO THE DRAWINGS
1. Delete Detail 3/A6.3.
2. Revise drawings per SKA-INT1, dated 12/13/24.
3. 2/A1.4: Add “SAND, STAIN, & SEAL WOOD STAIR TREADS. PAINT STAIR RISERS” hatch from
FINISH Schedule to the North Stairs. Scope associated with both North and South Stair.
1.04 QUESTIONS AND ANSWER
1. Question: Could a list of contractors currently working on the building be posted?
Answer: Contractors currently working on the building are Westway Construction, F & S Electric, and Temptec Mechanical. These contractors have subcontractors working for them in field as well.
2. Question: The “Removeable Walk-Off Mat” at the entrances, does not specify exactly where, please clarify.
Answer: Per A1.4 walk-off mat is not in this scope. North and South Stairs (riser and treads) are to be refinished per A1.4 finish schedule “SAND, STAIN, & SEAL WOOD STAIR TREADS. PAINT
STAIR RISERS.”
3. Question: Will there be an Addendum coming out?
Answer: Yes, Addendum 1 was posted on 12/12/2024.
4. Question: Spec. Section 015000; As the GC is not doing any electrical work under our contract; is the GC required to employ an electrician to set up the temporary electricity for the project as outlined in the specification section?
Answer: No, the awarded GC will coordinate with the existing awarded electrical contractor.
5. Question: Spec. Section 015000, Sub-Paragraph 2.4; Is a temporary ramp required to be installed at the adjacent Church? If so, what are the requirements of the ramp?
Answer: No.
6. Question: Spec. Section 015000, Sub-Paragraph 3.4; Is a project sign required for the project?
Answer: No.
Walley School Interior Package 260 High Street, Bristol, RI 02809
Addendum 2: 12/16/2024
BTGA Project #2211 ADDENDUM 2 Brewster Thornton Group Architects, LLP SECTION 00 9000 - 2
7. Question: Refer to metal ceiling and walls that are adjacent to the elevator. Please confirm if the elevator supplier is furnishing and installing this. If not, please provide finish that we are trying to match.
Answer: See SKA – INT1, dated 12/13/2024.
8. Question: Can the bid date be extended to allow more time due to holidays/vacations/etc.?
Answer: Yes, see the revised Invitation to Bid, included with this addendum.
END DOCUMENT
OPEN TO ABOVE
ELEV.
N. STAIR
L3a
9' - 0"
SD
ENTRY
7' - 6" 11' - 0"
BEAD BOARD CEILINGS
IN ENTRY 113, OWNED
BY OTHERS
ELEV.
PAINTED
CROWN
MOLDING TO
MATCH
EXISTING
PT-2
PAINTED
WALL
BASE
PT-2
PT-2
PAINTED CROWN
MOLDING TO
MATCH EXISTING
PT-2
STOREFRONT BY
OTHERS
PAINTED WALL BASE
PT-2
PAINTED CROWN
MOLDING TO
MATCH EXISTING
PT-2
PAINTED WALL BASE
EXISTING BRICK
WALL TO REMAIN
317 Iron Horse Way Suite 202 Providence, RI 02908 Tel: 401.861.1600 Fax: 401.861.5588
SCALE: As indicated SKA-INT1DATE:12/16/2024
260 HIGH STREET, BRISTOL, RI 02809
WALLEY SCHOOL
#2211
ELEVATOR ENTRY
VESTIBULE
SKA-INT1 Scale: 1/8" = 1'-0"
(PARTIAL) FIRST FLOOR
REFLECTED CEILING PLAN (1/A1.3)
SKA-INT1 Scale: 1/4" = 1'-0"
2 ENTRY - 113 - SOUTH ELEVATION (2/A7.1)
SKA-INT1 Scale: 1/4" = 1'-0"
3 ENTRY - 113 EAST ELEVATION (1/A7.1)
SKA-INT1 Scale: 1/4" = 1'-0"
4 ENTRY - 113 - WEST ELEVATION (4/A7.1)
File details come from the government source that posted it. Updated .