This is Addendum #2 to a general construction contract issued by the New York State Office of Parks, Recreation and Historic Preservation for campground restroom construction at Letchworth State Park, Project Number D006472-75, dated March 25, 2026. The addendum modifies specifications for door hardware finishes and requires all bidders to acknowledge receipt of this addendum in their bid submissions under penalty of disqualification.
The primary change specified in Addendum #2 requires that door hardware finish be changed to Matte Black, with deletion of code "US 4" from specification section 087100. This modification must be incorporated into all bid amounts, and bidders must document their acknowledgment of the addendum in the designated space on the bid form. The related contract opportunity involves multiple construction trades at Letchworth State Park, including general construction (D006472) with an estimated range of $3,097,727 to $4,191,043, electrical work (D006473) estimated at $185,886 to $251,493, mechanical work (D006474) estimated at $77,246 to $104,510, and plumbing work (D006475) for water supply, heating, fixtures, and drainage systems. MWBE participation goals are established for each trade, ranging from 12 to 25 percent for MBE and 5 to 18 percent for WBE participation. Designated agency contacts include Greg Robinson, Mike Petti, Val Symonds, Carissa Hartson, and John Honan.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum #3_032626.pdf | ||
| Addendum #1_032526.pdf | ||
| 2.0.a_NTB and ITB 02.2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KATHY HOCHUL
Governor
KATHY MOSER
Acting Commissioner
New York State Office of Parks, Recreation and Historic Preservation
ADDENDUM 2
JOB NAME AND PROJECT NUMBER
Campground Restrooms Letchworth State Park General D006472-75
DATE - March 25, 2026
ALL BIDDERS SUBMITTING A BID FOR THE ABOVE NAMED PROJECT SHALL TAKE NOTE OF THE
FOLLOWING CHANGES, ADDITIONS, INTERPRETATIONS, CLARIFICATIONS, ETC. IN CONNECTION
WITH THE DRAWINGS AND SPECIFICATIONS AND OTHER BID DOCUMENTS. THE FOLLOWING
INSTRUCTIONS HAVE PRECEDENCE OVER ANYTHING CONTRARILY SHOWN ON THE DRAWINGS
OR DESCRIBED IN THE SPECIFICATION DOCUMENTS, AND ALL SUCH INFORMATION SHALL BE
TAKEN INTO CONSIDERATION AND BE INCLUDED IN THE BIDDERS BID AMOUNT.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM BY INSERTING ITS NUMBER AND DATE IN THE
SPACE PROVIDED IN THE BID FORM. FAILURE TO DO SO MAY SUBJECT BIDDER TO
DISQUALIFICATION.
Summary of Addendum Items:
ITEM #1 – The door hardware finish is to be Matte Black, delete code “US 4” from specification section 087100.
END OF ADDENDUM 2