Addendum 1 RFP ED-25-613.pdf

PDF 1 MB Posted

Attached to
RFP for Connect Shelters for Purchase And Use
Solicitation number
ED-25-613
Issued by
California

About this file

Summary

This is an Addendum No. 1 to Request for Proposal (RFP) No. ED-25-613 issued by the City of Long Beach, Department of Financial Management, for the purchase and use of Connect Shelter modular units. The City is seeking proposals from qualified organizations to purchase and use twelve (12) modular Connect Shelters units, which provide a total of thirty-three (33) single-occupancy units. The units consist of nine standard modulars (approximately 9 ft by 40 ft, each containing 3 single-occupancy units) and three ADA-accessible modulars (approximately 10 ft by 40 ft, each containing 2 ADA-accessible single-occupancy units). Each single-occupancy unit is approximately 10 ft by 10 ft with a private ensuite bathroom and shower. The units are designed to be connected to utilities including power, water, and sewage and contain a dedicated fire sprinkler system but do not include a kitchen, as they were designed as temporary housing. The units are currently wrapped and in storage. Asset tours are available upon request with nine business days' notice. The original RFP deadline was September 4, 2025 at 11:00 AM PST; however, Addendum No. 1 extends this deadline to October 7, 2025 at 11:00 AM PST. The optional pre-proposal meeting was held on August 13, 2025. Proposers must acknowledge receipt of this addendum by signing and submitting it with their proposal, or they may be disqualified. After evaluation is complete, the City will post a Notice of Intent to Award, and assuming no protests are received, will enter into contract negotiations before final contract execution.

The City's original cost estimate for the project, prepared in 2022 for a specific site, is attached and totals approximately $4.566 million, comprising $2.372 million for site work and $2.194 million for modular unit installation. This estimate includes public agency requirements such as prevailing wage and government code compliance, and the unit costs reflect the actual cost for setting the modulars onsite rather than the purchase price of the units themselves. The estimate may vary by plus or minus 25 percent or more and does not include unforeseen conditions or economic fluctuations. The City notes that non-profits and other entities not bound by the same municipal standards may incur lower costs. While the City's preference is for these units to address homelessness, the City will evaluate all proposals based on the established evaluation criteria, and interested parties whose intended purpose would not address homelessness may still submit proposals. Proposers are responsible for all costs associated with unit delivery, installation using cranes, and site preparation including excavation of stem wall foundations and trenching for utility connections. Additional infrastructure not included in the purchase, such as decking, site amenities (parking, fencing, lighting, landscaping, wayfinding), supportive services facilities, and communal open space, would be the proposer's responsibility. All inquiries should be submitted via email to rfppurchasing@longbeach.gov, and proposals must be submitted electronically through www.LongBeachBuys.com.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Financial Management 411 West Ocean Boulevard, 6th Floor

Long Beach, CA 90802

(562) 570-6425

September 26, 2025

NOTICE TO PROPOSERS

ADDENDUM NO. 1: Q&A

RFP No. ED-25-613 Connect Shelters for Purchase and Use

This addendum changes and supersedes the language in the original RFP. Please acknowledge receipt of this addendum by signing and submitting with your proposal. Any proposer who fails to submit this addendum may be disqualified.

The City would like to remind Proposers that pursuant to Section 5.2.25 of the RFP, the City will not be responsible for or bound by any oral communication or any other information or contact that occurs outside the official communication process specified herein, unless confirmed in writing by the City Contact.

The City would like to provide the following updates:

• RFP deadline extended to 11:00 AM 10/07/25.

• Optional pre-proposal meeting slide deck attached.

• Original rough order magnitude (ROM) cost estimate attached.

The questions and answers are as follows:

1. Q: When you developed the project did you figure out how much it would cost?

A: Yes, but note that the City’s cost includes public agency requirements like prevailing wage, government code requirements, etc. The estimated cost the City was expecting to incur may be lower for other entities such as non-profits who may not be held to the same standards as a municipal entity.

2. Q: Are you able to provide as estimate on what it would cost?

A: Original ROM cost estimate attached. Note that this estimate is from 2022 and was prepared for a specific site. Also note that the unit cost is not the cost to purchase the units, it is the actual cost for setting the modulars onsite.

3. Q: We are interested but our intended purpose would not address homelessness.

Should we still submit a proposal?

Addendum No. 1 RFP PW-25-536

A: Yes. It is the City’s preference that these units be repurposed to tackle homelessness, but the City will evaluate all proposals based on the evaluation criteria.

4. Q: Is it possible to tour the assets?

A: Yes. However, because the units are stored offsite by a third party, the City needs nine business days’ notice in order to have the units available for inspection.

5. Q: If we submit a bid in response to the above-mentioned Request for Proposal (RFP) and our bid is selected, are we legally obligated to purchase the "tiny homes"?

A: Generally speaking, after the evaluation is complete, the City will post a Notice of Intent to Award, publicly stating who the City intends to award the contract to.

Assuming no protests are received, the City will then enter into any contract negotiations, if applicable, before a contract is executed by all parties.

PREPARED BY: Tommy Ryan, Administrative Analyst III

ACKNOWLEDGED BY: ________________________________________________

Company Name

Print Name Title

Signature Date

11/15/2022

City of Long Beach

DESCRIPTION OF WORK

OTY UOM Unit Cost Total Cost

Site Work

Surveying 1 LS 25,000.00$ 25,000.00$

Monument Sign 1 LS 15,000.00$ 15,000.00$

SWPPP 1 LS 36,000.00$ 36,000.00$

Pavement Removal 146 CY 160.00$ 23,680.00$

Tree Removal up to 24" 6 EA 2,000.00$ 12,000.00$

Mobilization on Non Budget Items 1 LS 25,000.00$ 25,000.00$

Water 1 LS 95,000.00$ 95,000.00$

Sewer 1 LS 180,000.00$ 180,000.00$

Fire Water and Fire Hydrants 1 LS 200,000.00$ 200,000.00$

Storm Drain 1 LS 131,000.00$ 131,000.00$

Modular Wetland System 2 EA 45,000.00$ 90,000.00$

Asphalt Paving 11,000 SF 20.00$ 220,000.00$

Asphalt Trench Patching 1200 SF 20.00$ 24,000.00$

Edison Transformer and Fee 1 EA 100,000.00$ 100,000.00$

Switchgear and Distribution 1 LS 150,000.00$ 150,000.00$

Grading 1 LS 50,000.00$ 50,000.00$

Traffic Cotroll 20 Days 50,000.00$

Wrought Iron Fence 10 ' High 170 LF 700.00$ 119,000.00$

16' Gate 12,000.00$

Solar Lights 6 EA 16,000.00$ 96,000.00$

Bollards at Fire Hydrant's 6 EA 2,000.00$ 12,000.00$

ADA Signage 5,000.00$

Direct Cost 1,670,680.00$

Construction Contingency 10% 167,068.00$

General Conditions 8% 133,654.00$

Insurance 2% 33,413.00$

Profit and Overhead 10% 167,068.00$

Bond 1% 16,706.00$

Testing and Inspection 2% 33,413.00$

Permit and Plan Check 5% 83,534.00$

Utility Fees 4% 66,827.00$

2,372,363.00$

Modular Units

Pier Footings 150 EA 1,000.00$ 150,000.00$

Modular Units 12 EA 100,000.00$ 1,200,000.00$

Fire Alarm System 1 LS 70,000.00$ 70,000.00$

Switchgear and Distribution 1 LS 150,000.00$ 150,000.00$

Security Check Point 1 EA 20,000.00$ 20,000.00$

1,590,000.00$

Construction Contingency 10% 159,000.00$

General Conditions 8% 127,200.00$

Insurance 2% 31,800.00$

Profit and Overhead 10% 159,000.00$

Bond 1% 15,900.00$

Testing/Inspection/Staking 2% 31,800.00$

Permit/Plan Check 5% 79,500.00$ 2,194,200.00$

Tiny Homes

ITEM

NO

Site Work Total

Labor and Material

Direct Cost

Modular Total

Disclaimer: It is the requestor's obligation to carefully review and confirm the information provided is valid and reflects the scope of work requested by the project customer. The attached budgetary estimate is an initial projection of cost based on preliminary, quantities, general construction methods, and the scope of work as provided in the preliminary design documents. The construction budget estimate is based on known conditions as described in the general scope of work but may does not include "Unforeseen Conditions" and fluctuating cost impacts of the economy. The estimate was developed by drawing on historical construction methods and current published construction cost standards.

The actual cost may vary (+/- 25% or more) of the estimated amount.

DATE PREPARED:

Connect Shelter Units (ED-25-613) Optional Pre-Proposal Meeting

August 13, 2025

The City of Long Beach is seeking proposals from qualified organizations to purchase and use twelve (12) modular Connect

Shelters units, providing a total of thirty-three (33) single-occupancy units, preferably for use consistent with the City’s intended use as interim housing for people experiencing homelessness.

The Opportunity

• The City of Long Beach contracted with Connect Homes to design and manufacture modular shelter units to be used for temporary housing for people experiencing homelessness.

• These units were successfully designed and manufactured, and are currently wrapped and in storage

• Due to extenuating circumstances, the project was discontinued, and the City is seeking to sell the completed units

• The 12 modular units provide a total of 33 single occupancy units

Background

• Nine (9) Standard Modulars (approx. 9 ft by 40 ft), each containing 3 single occupancy units

• Three (3) ADA-accessible Modulars (approx.

10 ft by 40 ft), each containing 2 ADA-accessible single occupancy units

• Each single occupancy unit is roughly 10 ft by 10 ft, with a private ensuite bathroom and shower.

• Units are designed to be connected to utilities, including power, water, and sewage, and contain a dedicated fire sprinkler system

• The units do not contain a kitchen, as they were designed as temporary housing

Connect Shelter Units

Rendering and promotional images

• Ensuite bathroom including sink, toilet, and shower attached to on-site plumbing lines

• ADA-accessible units include barrier free design, accessible grab bars, and roll-in shower

• Floor drains in bathroom and shower

• Ceiling-mounted combination exhaust fans

• Operable windows that are lockable from the inside and are commercial-grade thermally-broken aluminum, dual pane, OWE systems.

• Glass entry doors

• Design, materials, and assemblies built with durability and ease of maintenance in mind

• All-steel moment frame for durability and reusability

• Fully insulated walls, floors, and roof per CalGreen Title 24 Energy Code requirements

Connect Shelter Units

• Durable floor materials designed for easy cleaning

• In-unit controlled heating and cooling via ceiling-recessed fan coil and exterior heat pump

• Fire-resistant materials and in-unit detection and suppression systems, including smoke detector and Ceiling Mounted Flat Concealed Residential Fire Suppression Sprinkler Heads

• At least two recessed, dimmable LED lights

• Code-required electrical receptacles in sleeping room and bathroom

• Easily wipeable Fiber Reinforced Plastic board on the walls of sleeping units

• Fire Sprinkler Manifold, Electrical Subpanel, Condenser, and Water Heater all within a single exterior‐access utility room for convenient maintenance with no disturbance to occupants

• For installation, each unit requires a stem wall foundation to be excavated, as well as trenching for utility connections (water, sewer, and power).

• Units must be delivered and installed using cranes, at the proposer’s expense.

• The City’s project proposed additional infrastructure (not included), such as:

• Decking to connect each unit

• Site amenities such as parking lot, fencing, lighting, landscaping, and wayfinding

• A separate space for supportive services, administrative needs, meal preparation, and laundry

• Other communal open space and pet run

Considerations for Deployment

Conceptual Site Plan for Previous Proposed City of Long Beach “Tiny Homes” Project

Submit all inquiries via email to rfppurchasing@longbeach.gov

Proposals should be submitted electronically via www.LongBeachBuys.com

Conclusion

RFP Timeline

Release Date August 4, 2025

Optional Pre-Proposal Meeting August 13, 2025 (11:00 AM PST)

Questions Due to the City August 19, 2025 (11:00 AM PST)

Posting of the Q&A August 26, 2025

Proposals Due September 4, 2025 (11:00 AM PST) mailto:rfppurchasing@longbeach.gov http://www.longbeachbuys.com/