About this file

This Addendum 1 document contains questions and responses related to IFB 2027*002, an EPA Five-Year Reviews solicitation issued by the Colorado Department of Public Health and Environment (CDPHE). The solicitation seeks contractor services to complete Five-Year Reviews (FYRs) for five specified Superfund sites in Colorado. The project requires site inspections and deliverables including a contract-specific Quality Assurance Project Plan (QAPP) and Health and Safety Plan. Bidders must demonstrate minimum qualifications by having completed Five-Year Reviews at a minimum of two of the five listed sites to establish familiarity with these sites and prior work experience in Colorado. CDPHE clarified that while FYRs for these sites were previously prepared by EPA or CDPHE staff members, consultants with relevant CERCLA facility experience are encouraged to apply if they meet the two-site experience requirement.

The total contract budget is not to exceed $370,000, with CDPHE requesting line item costs for each of the five sites. All supplemental costs, including the QAPP, Health and Safety Plan, and other project-related expenses, must be incorporated into the individual site cost breakdowns rather than listed as separate line items. Each site requires a minimum of one site visit for vendor observations to ensure accurate assessment of current site conditions. The budget template must reflect costs allocated across all five sites with detailed deliverable-level pricing to support anticipated invoicing amounts throughout the contract term.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1

COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT

SOLICITATION QUESTIONS AND ANSWERS

Solicitation #: IFB 2027*002 Solicitation Name: EPA Five-Year Reviews

Vendor Question #1: Would the CDPHE consider bids from firms that have not performed reviews for the sites listed in the solicitation?

CDPHE Answer #1: Previous work with a minimum number of 2 of the sites listed is required.

Vendor Question #2: Section B, Minimum Qualifications includes the requirement to have completed a Five-Year Review at two of the five sites that will be completed under this project. Five-Year Reviews are straightforward documents that follow specific Superfund guidance. It’s unclear what is critical about these sites that previous experience at two of the sites is a requirement. Can CDPHE remove this qualification or clarify the need to limit the competition on this opportunity to only previous contractors?

CDPHE Answer #2: Not all sites are equal, having performed reviews at any 2 of the listed sites shows familiarity of these sites and exhibits previous work in Colorado. CDPHE has not conducted FYRs at these sites, only at the Denver Radium Site and Chem Sales Site by CDPHE staff members.

Vendor Question #3: Section III.B.3 states that the bidder shall have performed Five-Year Reviews (FYRs) for a minimum of two sites specified in the IFB. Based on our cursory review of the last two FYRs for each site, they were primarily prepared by either EPA or CDPHE. Please clarify whether consultants with prior FYR experience at other CERCLA facilities can qualify for this bid opportunity.

CDPHE Answer #3: Having performed reviews at any 2 of the listed sites shows familiarity of these sites and exhibits previous work in Colorado. CDPHE has not conducted FYRs at these sites, only at the Denver Radium Site and Chem Sales Site by CDPHE staff members.

Vendor Question #4: IFB1- 2027000002, TITLE: EPA Five-Year Reviews, section VI. Attachments and Exhibits – Attachment 2 Budget Template includes total site cost, but does not include line item costs associated with the deliverables outlined in Attachment Exhibit C – Draft Statement of Work, Section III Work Plan, Deliverables.” In addition to the total cost per site, would CDPHE allow for the costs for each site’s deliverable to be included in the Budget Template to indicate the anticipated invoicing amounts?

CDPHE Answer #4: CDPHE is requesting a line item cost for each of the five (5) sites resulting in a total not to exceed $370,000. Supplemental costs (including QAPP, Health and Safety plan, etc…) should be incorporated into and divided out for each of the five (5) sites.

Vendor Question #5: IFB1- 2027000002, TITLE: EPA Five-Year Reviews, section VI. Attachments and Exhibits – Attachment 2 Budget Template includes site costs, but does not include a line for the Quality Assurance Project Plan. Attachment Exhibit C – Draft Statement of Work, Section III Work Plan, Sub-activities #2 states “The Contractor shall submit a contract- specific Quality Assurance Project Plan (QAPP).” As the QAPP is a “contract-specific” document, would it be appropriate to include the QAPP as a deliverable and add it to the Budget Template? Or shall we factor in the QAPP costs across the five sites?

CDPHE Answer #5:CDPHE is requesting a line item cost for each of the five (5) sites resulting in a total not to exceed $370,000. Supplemental costs (including QAPP, Health and Safety plan, etc…) should be incorporated into and divided out for each of the five (5) sites

Addendum 1

Vendor Question #6: IFB1- 2027000002, TITLE: EPA Five-Year Reviews, section VI. Attachments and Exhibits, Exhibit C – Draft Statement of Work, Section III Work Plan, Sub-activities #3 states “The Contractor shall conduct Site Inspections.” Can CDPHE confirm that a single site inspection is anticipated for each FYR site?

CDPHE Answer #6: Each site shall require a site visit for observations made by the Vendor for accurate site conditions for each respective site.

File details come from the government source that posted it. Updated .