This is Addendum #1 to a Request for Proposals issued by the City of Philadelphia's Capital Program Office for professional services related to the design, bidding, and construction administration of a new Class A Burn Building at the Philadelphia Fire Academy (Opportunity No. 21260522132250). The addendum, dated June 23, 2026, addresses questions submitted by prospective applicants prior to the proposal deadline of July 20, 2026 and incorporates attendance sign-in sheets from three pre-proposal meetings held on May 18, June 8, and June 9, 2026. The addendum clarifies that all work covered in the supplement shall be included in the original proposal and constitutes one of the contract documents.

The addendum provides critical clarifications on project requirements and site conditions. The Office of Sustainability has confirmed that LEED certification is not required since the burn building will contain no conditioned building space; however, the City intends to pursue sustainability initiatives in alternative forms. The new burn building will be located in the SP-POA-A zoning district, with an anticipated limit of disturbance under one acre. No hazardous materials will be stored in the facility, and no existing environmental reports are available for the site. Utility connections will be minimal, limited to electric service for stairwells, hallways, and select rooms, with water drainage only for sanitary purposes and no natural gas connections anticipated (though propane may be used for minimal Class B training props if included). No Class B prop manufacturer has been pre-selected, and any proposed props must be documented as part of the bid package. The addendum confirms that the City has not pre-registered the project with USGBC and will not pursue LEED v4, v4.1, or v5 certification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

New Burn Building 13-25-4520-01 RFP 1.03 file 1 Addendum #1

23 June 2026

ADDENDUM NO. 1

CAPITAL PROGRAM OFFICE

For the Project: New Burn Building – Philadelphia Fire Academy Opportunity No.: 21260522132250

I. INSTRUCTIONS

This supplement to the RPF is issued prior to the receipt of proposals in response to Applicant questions. All work covered in this supplement shall be included in the original proposal, and the supplement will be considered one of the contract documents.

II. SIGN IN – Attendance

1. Please find attached the attendance sign in sheets from 06.09.2026,06.08.2026, and 05.18.2026 FYI.

III. RESPONSES TO QUESTIONS SUBMITTED BY PROSPECTIVE APPLICANTS

1. Q: With all LEED v4 and LEED v4.1 project registrations closing at the end of June 2026, has the City registered this project with USGBC or will the project be seeking certification under the new LEED v5 Rating System?

A: No – The Office of Sustainability has confirmed; since this project will not have ANY conditioned building space, it is not required to be LEED certified.

2. Q: Is it in fact the intent of the City to seek formal LEED Gold certification for this project or pursue sustainability initiatives in another form?

A: See answer above to #.1, Yes the City intends to pursue sustainability initiatives in another form.

3. Q: Does the successful team have permission from the Capital Program Office (CPO) to submit to the Office of Sustainability

(OOS) a request on CPO’s behalf for an alternative standard or exception?

A: See answers above #.1 and #.2

4. Q: Will any hazardous materials be stored in the new burn building? If yes, are variances anticipated for storage in the floodplain?

A: No hazardous materials are to be stored in the new burn building.

5. Q: The property falls under two zoning districts ( I-3 and SP-POA-A). Please confirm which zoning district the new burn building will be located on?

A: The new burn building will be located on the zoning district SP-POA-A.

6. Q: Is the anticipated limit of disturbance under or over 1 acre?

A: The anticipated limit of disturbance is under 1 acre.

7. Q: Please confirm which utility connections will be required for the new burn building:

a. Gas

b. Electric d.Domestic Fire

e. Sanitary

A: a. Gas- No Natural Gas connections are likely- If there are any Class B props, it is more likely fuel to be propane.

b. Electric- minimal electric including stairwells, hallways and some rooms

d. Domestic Fire- no connections

e. Sanitary -water drainage only

8. Q: Are there any existing environmental reports for the site that would be available to distribute?

A: There are no existing environmental reports for the site.

New Burn Building 13-25-4520-01 RFP 1.03 file 2 Addendum #1

9. Q: Does the City have a class B prop manufacturer that is preselected to work with? If not, is there a process to select the manufacturer?

A: No Class B prop manufacturer has been pre-selected. It is anticipated that there will be a very minimal scope of Class B props.

If any props are proposed, they shall be documented as part of the Bid package.

-END OF ADDENDUM NO. 1-