This document is an Addendum to an Invitation to Bid (ITB) issued by Portland Community College (PCC) for the SE Campus MDF HVAC Replacement Project. The purpose of the ITB is to remove and replace the HVAC systems serving the SE Campus MDF Room. The addendum provides key information, including the attendance record of the mandatory pre-bid conference, two substitution requests and PCC's decisions, questions and answers, and details for the public bid opening. The bid closing date remains unchanged at February 3, 2022 at 2:00 PM Pacific Time.

The substitution requests were for the outdoor and indoor HVAC units, which PCC approved with some noted conditions. PCC also provided photographs of the existing roof area and access, and answered questions related to the controls scope, existing equipment disposal, temporary HVAC, and potential COVID-19 impacts. The public bid opening will be held on February 3, 2022 at 2:05 PM Pacific Time via Zoom teleconference.

View the file

Other files

File Type Posted
IT1056-22 - Cerium SSJ.docx DOCX document
Posting 1.6.2022 - ITB SE Campus MDF HVAC Replacement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Planning and Capital Construction 9700 SW Capitol Hwy – Suite 260

Portland OR 97219

Date: 1/26/2022

SOLICITATION ADDENDUM NO. 1

P&CC21-014-ITB

ITB – SE CAMPUS MDF HVAC REPLACEMENT PROJECT

THE FOLLOWING CHANGES/ADDITIONS TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED:

This Addendum modifies the Invitation to Bid (ITB) document only to the extent indicated herein. All other areas not changed or otherwise modified by this Addendum shall remain in full force and effect. This Addendum is hereby made an integral part of the ITB document. Bidders must be responsive to any requirements of this Addendum as if the requirements were set forth in the ITB. Failure to do so may result in Bid rejection. See the ITB regarding requests for clarification or change and protests of this Addendum, and the deadlines for the foregoing.

This addendum is to be acknowledged in the space provided on the Bidder Certification Form supplied in the solicitation document. Failure to acknowledge receipt of this addendum may be cause to reject your bid.

The closing date REMAINS UNCHANGED: February 3, 2022 at 2:00 PM Pacific Time

The purpose of this Addendum is to provide four items of information. These four items follow this Addendum Number 1 Cover Page.

1) Attendance Record at the Mandatory Pre-Bid Conference and Site Inspection

2) Two Substitution Request Forms Submitted and PCC’s Decisions on those requests

3) Questions and Answers, including the requested photographs of the roof project area

4) Public Bid Opening information and teleconference logon details

END of Addendum # 1 Cover Page James Lasseter – PCC Buyer and Contract Specialist

Solicitation No. P&CC21-014-ITB

ITB – SE CAMPUS MDF HVAC REPLACEMENT PROJECT

Attendance Record – Mandatory Pre-Bid Conference and Site Inspection Held January 18, 2022 – 10:00AM

The following 8 firms are on record of having attended the Mandatory Pre-Bid Conference and Site Inspection:

GENERAL SHEET METAL

APEX MECHANICAL

YADON MECHANICAL

TOTAL MECHANICAL

CHERRY CITY ELECTRIC

HARDER MECHANICAL

NEXUS ELECTRICAL GROUP

BUILDSKAPE

--End of Attendance Record--

DocuSign Envelope ID: 956483DE-0A53-41E0-8EF1-2CDDBE8DD167

X

Buyer/Contract Specialist 1/25/2022

SECTION V – ATTACHMENTS

SE Campus MDF HVAC Replacement

Substitution Request Form Page 1 of 2 17JUN21_ITB_PI

ATTACHMENT I - SUBSTITUTION REQUEST FORM

USE AND SUBMIT A COPY OF THIS FORM FOR EVERY SUBSTITION REQUEST

Project:SE Campus MDF HVAC REPLACEMENT Deadline to Submit this Form: Jan 24, 2022 Noon Submit this Form to: james.lasseter@pcc.edu

RFP/ITB NUMER: P&CC21-014-ITB

Substitution Request Number:_________ From:___________________________________________ Date:____________________________________________

Specification/Section Title:

Article/Paragraph: Section No.: Page:

Description:

Original Specification: QTY:

Proposed substitution: QTY:

Manufacturer:

Address: Phone:

Trade Name: Model No./Color:

Installer: Address: Phone:

History: ☐ New Product ☐ 1 — 4 years old ☐ 5 — 10 years old ☐ More than 10 years old

Differences between proposed substitution and specified product:

☐ Point-by-point comparative data attached - REQUIRED FROM BIDDER/PROPOSER SUBMITTING THIS REQUEST

Reason for not providing specified item:

Similar Installation:

Project: Owner:

Address: Date Installed:

Proposed substitution affects other parts of Work: ☐ No ☐ Yes; explain

Dave Havelick - Sustainable Mechanical Systems

01/07/2022

V. 1, June 2020, Design & Construction Standards, Division 23: Heating Ventilating and Air Conditioning

Split System Air Conditioning Unit

7.Z. Decentralized HVAC Equipment

2 each Indoor/Outdoor Units

Daikin DX11TA CU-1,2 and DAT12043 AC-1,2, M Drawing 2.01

CU-1,2 and AC-1,2 2 ea. Indoor/ Outdoor Units

Johnson Controls (Z. 7. C. 3., pg. 27)/Fraser-Johnston manufactured by Johnson Controls in Norman, OK.

Norman, OK 877-874-7378

Fraser-Johnston

TBD TBD TBD

PH-10C00ATEAA5/CU-1,2 and NS-10C00CTCAA4/

AC-1,2; MINERAL BROWN

X

Negligible

Fraser Johnston has slightly different dims, performance, electrical than Daikn basis of design same as York,Tran, Carrier, etc.

X

Oregon State University

Withycombe Hall Theater

2921 SW Campus Way, Corvallis, OR

97331

NA

SECTION V – ATTACHMENTS

SE Campus MDF HVAC Replacement

Substitution Request Form Page 2 of 2 17JUN21_ITB_PI

Supporting Data Attached: ☐ Drawings ☐ Product Data ☐ Samples ☐ Tests

☐ Reports ☐ Sustainability Criteria (MA-CHPS) (LEED)

The Undersigned certifies:

• Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

• Same warranty will be furnished for proposed substitution as for specified product.

• Same maintenance service and source of replacement parts, as applicable, is available.

• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

• Proposed substitution does not affect dimensions and functional clearances.

• Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.

Submitted by:

Signed by:

Firm:

Address:

Telephone:

Email:

Attachments:

PCC INTERNAL USE (REVIEW AND ACTION)

☐ Substitution approved

☐ Substitution approved as noted

☐ Substitution rejected - Use specified materials.

☐ Substitution Request received loo late - Use specified materials.

Signed by: Date:

Additional Comments by PCC (if any):

x x

Dave Havelick

Sustainable Mechanical Systems

7412 SW Beaverton Hillsdale Hwy., Ste. 203, Portland, OR 97225

503-703-2042

Dave Havelick

Preliminary Submittal

DocuSign Envelope ID: 956483DE-0A53-41E0-8EF1-2CDDBE8DD167

Buyer/Contract Specialist

X

1/25/2022

SUBMITTAL DATA

Order #: Date: 01/06/2022 Project: PCC SE Center MDF Project #:

Submitter: David Havelick Sustainable Mechanical Systems Inc.

7412 SW Beaverton Hillsdale Hwy, Suite 203, Portland, Oregon 97225 503-703-2042 dhavelick@sustainmech.com

Information is subject to change without notice. Check local codes. Printed 01/06/2022

Notes:

1. Fraser Johnston manufactured by JCI in same Norman, OK factory and using same configuration, components, performance, etc. as already listed York.

2. Fraser Johnston split system per Specification Section 23, Z and drawings M2.01 through M2.06.

Date 01/06/2022 Project Name PCC SE Center MDF Project Number Client / Purchaser

Submittal Summary Page

Qty Tag # Model # / Material # Description 2 CU-1,2 PH-10C00ATEAA5 10 Ton, Split System R-410A Heat Pump, 2-Pipe R-410A, 2-Stage, Standard Motor, 208/230-3-60, Copper Tube/Al Fin Condenser Coil

• Smart Equipment Controller with Gateway to BACnet MS/TP (Programmable to Modbus or N2)

2 CU-1,2 2LA04702012 Low Ambient To 0° F

2 CU-1,2 1HG0429 Hail Guard

2 CU-1,2 2HG04700524 Hot Gas Bypass Kit; Includes discharge bypass valve and Copper pipe fittings for field installation. Used to modulate capacity at low load conditions.

2 CU-1,2 S1-TEC3630-14-000 7 DAY PROGRAMMABLE THERMOSTAT, OPTIONAL MSTP OR

N2 COMMUNICATION, RTU/HEAT PUMP WITH ECON,FULL

COLOR, WHITE, JCI LOGO

2 AC-1,2 NS-10C00CTCAA4 10 Ton, Split System R-410A Air Handler, 2-pipe w/Intellispeed, 2.0 HP Motor, 208/230-3-60

• Intellispeed VFD w/Bypass

• Composite Drain Pan

• Mod Option - Stainless Steel Drain Pan

2 AC-1,2 1RG0416 Return Air Grille

NOTES:

Less Or Provide By Others:

Disconnects, wire/wiring, kW heat, condensate overflow switch (Provided by control contractor), condensate pump (Provided by contractor), economizer/mixing box, refrigerant piping or accessories, external seismic restraints or calculations, external vibration isolation, field installation of accessories (Fld), start up, Owner training and labor warranty.

Equipment start-up and commissioning by a factory trained technician is recommended.

Contact your supplying distributor or sales representative for additional information & guidance.

WARNING: Cancer and Reproductive Harm - www.P65Warnings.ca.gov

Information is subject to change without notice. Check local codes. Printed 01/06/2022

Cooling Performance Total gross capacity 121.9 MBH Sensible gross capacity 99.0 MBH Total net capacity 115.8 MBH Sensible net capacity 92.9 MBH Efficiency (at ARI) 11.10 EER Integrated eff. (at ARI) 14.20 IEER Ambient DB temp. 95.0 °F Unit Leaving DB temp. 59.8 °F Unit Leaving WB temp. 57.3 °F Leaving air temp dew point 55.70 °F Power input (w/o blower) 9.08 kW Sound power 89 dB(A)

Refrigerant Refrigerant type R-410A

Heat Pump Performance Ambient DB temp. 47 °F Design Gross Capacity 107.4 MBH Power Input 7.29 kW Capacity @ 47 °F 104.00 MBH

COP @ 47 °F 3.30

Capacity @ 17 °F 63.00 MBH

COP @ 17 °F 2.30

Heating Performance Entering DB temp. 60 °F Supply air 4265 CFM

Electrical Data Power supply 208-3-60 Unit min circuit ampacity 41.6 Amps Unit max over-current protection 50 Amps

Dimensions & Weight Hgt 50 in. Len 59 in. Wth 32 in.

Weight with factory installed options 543 lbs.

Clearances Right 30 in. Front 36 in. Rear 24 in.

Top 120 in. Bottom 0 in. Left 30 in.

Note: Please refer to the tech guide for listed maximum static pressures

10 Ton

• Fraser-Johnston Split System Units are Manufactured at an ISO 9001 Registered Facility.

Unit Features

• Unit Cabinet Constructed of Powder Painted Steel, Certified At 750 Hours Salt Spray Test (ASTM B-117 Standards)

• Full Perimeter Base Rails with Built in Rigging Capabilities

• Scroll Compressors with Crankcase Heater

• Single Refrigeration Circuit (2 Pipe)

• Liquid Line Driers (Supplied for Field Installation)

• Suction Line Accumulator

• Copper Tube/Aluminum Fin Condenser Coil

• Back Seating Suction and Liquid Line Service Valves

• Inherently Protected Fan Motors

• Side or Bottom Single Point Power Connections

• Short Circuit Current: 5kA RMS Symmetrical Standard Unit Controller: Smart Equipment Control Board

• Anti-Short Cycle Protection, Lead-Lag, Low Voltage Protection, On-Board Diagnostic and Fault Code Display

• Safety Monitoring - Monitors the High and Low-Pressure Switches. The Unit Control Board will Alarm on Compressor Lockouts and Repeated Limit Switch Trips.

BAS Controller

• Smart Equipment Controller with Gateway to BACnet MS/TP (Programmable to Modbus or N2)

Warranty

• One (1) Year Limited Warranty on All Other Parts

• Five (5) Year Limited Warranty on Compressors

Information is subject to change without notice. Check local codes. Printed 01/06/2022

Outdoor Split System Fraser-Johnston Split-System R-410A Outdoor

Page: 3

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5 Quantity: 2 Tag #: CU-1,2 System: PH-10C00ATEAA5,NS-10C00CTCAA4

Additional Electrical Data Power supply 208-3-60 Unit min circuit ampacity 41.6 Amps Unit max over-current protection 50 Amps Min Voltage 187 V Max Voltage 252 V Comp #1 RLA 16 Comp #1 LRA 110 Outdoor Mtr Qty 2 Outdoor Fan Voltage 208-1-60 OD Fan Mtr FLA (ea.) 2.8

Outdoor Split System Fraser-Johnston Split-System R-410A Outdoor

Page: 4

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5

Factory Installed Options

PH-10C00ATEAA5

Equipment Options Option(s) Selected

Product Category: P Split System R-410A Heat Pump Product Identifier: H 2-Pipe R-410A Nominal Cooling Capacity: -10 10 Ton Heat Type and Nominal Heat Capacity: C00 Airflow: A Standard Motor Voltage: T 208/230-3-60

Installation Options: E

Smart Equipment Controller with Gateway to BACnet MS/TP (Programmable to Modbus or N2)

Additional Options: AA Copper Tube/Aluminum Fin Condenser Coil Product Generation: 5

Field Installed Accessories 1CG0404 - Coil Guard (13.0 lbs) 1HG0429 - Hail Guard (37.0 lbs) 2HG04700524 - Hot Gas Bypass Kit; Includes discharge bypass valve and Copper pipe fittings for field installation. Used to modulate capacity at low load conditions.

(5.0 lbs)

2LA04702012 - Low Ambient To 0° F (3.2 lbs)

2PM04700124 - Phase Monitor Kit

- Includes Control and associated wiring. This accessory provides protection against phase reversal, loss or unbalance. (13.0 lbs)

S1-MP-PRTKIT-0P - MAP

(Multiple Access Portal) Gateway Kit- Replacement MAP gateway protective case, lanyard and communication cable. Use only to replace worn or damaged components. (0.3 lbs)

S1-NSB8BHN041-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, No Display, WHITE, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BHN043-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, No Display, BLACK, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BHN141-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, Warmer/Cooler Display, WHITE, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BHN143-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, Warmer/Cooler Display, BLACK, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BHN240-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, Full Display, WHITE, JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BHN241-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, Full Display, WHITE, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BHN243-0 - Wall Temperature and 3% Relative Humidity Combined Sensor, Full Display, BLACK, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BPN240-0 - Wall Temperature and 2% Relative Humidity Combined Sensor, Full Display, WHITE, JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BPN241-0 - Wall Temperature and 2% Relative Humidity Combined Sensor, Full Display, WHITE, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BPN243-0 - Wall Temperature and 2% Relative Humidity Combined Sensor, Full Display, BLACK, NO JCI LOGO, NS8000 Series (0.4 lbs)

S1-NSB8BTN041-0 - Wall Temperature Sensor, No Display, WHITE, NO JCI LOGO, NS8000

Series (0.4 lbs)

S1-NSB8BTN043-0 - Wall Temperature Sensor, No Display, BLACK, NO JCI LOGO, NS8000

Series (0.4 lbs)

Outdoor Split System Fraser-Johnston Split-System R-410A Outdoor

Page: 5

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5

S1-TEC3630-14-000 - 7 DAY

PROGRAMMABLE

THERMOSTAT, OPTIONAL MSTP

OR N2 COMMUNICATION,

RTU/HEAT PUMP WITH

ECON,FULL COLOR, WHITE, JCI

LOGO (0.8 lbs)

S1-TEC3631-14-000 - 7 DAY

PROGRAMMABLE

THERMOSTAT, OPTIONAL MSTP

OR N2 COMMUNICATION,

RTU/HEAT PUMP WITH ECON,

OCC SENSOR, FULL COLOR,

WHITE, JCI LOGO (0.8 lbs)

S1-TEC3631-16-000 - 7 DAY

PROGRAMMABLE

THERMOSTAT, OPTIONAL MSTP

OR N2 COMMUNICATION,

RTU/HEAT PUMP WITH ECON,

OCC SENSOR, FULL COLOR,

WHITE, NO LOGO (0.8 lbs)

S1-YK-MAP1810-0P - MAP

(Multiple Access Portal) Gateway- For use with SimplicitySE Control.

(0.2 lbs)

S1-YK-MAP1810-0S - Stationary MAP Gateway (Includes MAP Gateway, Field Bus Adapter, Mounting Bracket and 100 to 240 VAC Power Supply). US-compatible counties. (1.9 lbs)

Page: 7

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5

Consolidated Drawing

Page: 8

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5 Quantity: 2 Tag #: CU-1,2

Piping & Connection

Page: 9

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5

Corner Weights & Center of Gravity

Page: 10

Project Name: PCC SE Center MDF Unit Model #: PH-10C00ATEAA5

Cooling Performance

Total gross capacity 121.9 MBH Sensible gross capacity 99.0 MBH Total net capacity 115.8 MBH Sensible net capacity 92.9 MBH Entering DB temp. 80.0 °F Entering WB temp. 66.0 °F Leaving DB temp. 58.5 °F Leaving WB temp. 56.8 °F

Heating Performance Entering DB temp. 60 °F Supply air 4265 CFM

Supply Air Blower Performance Supply air 4265 CFM Ext. static pressure 0.5 IWG Addl. Unit Losses (Options/Accessories) 0.03 IWG Blower speed 831 RPM Max BHP of Motor (including service factor) 2.30 HP Duct location Horizontal Motor rating 2.00 HP Actual required BHP 1.88 HP Power input 1.77 kW Elevation 0 ft.

Drive type BELT

Indoor Electrical Data Power supply 208-3-60 Unit min circuit ampacity 7.30 Amps Unit max over-current protection 15 Amps

Indoor Dimensions & Weight Hgt 65 in. Len 30 in. Wth 56 in.

Weight with factory installed options 562 lbs.

Indoor Clearances Side w/Piping 24 in.

Side Opposite Piping 24 in.

Side w/ Return Air 24 in.

Side w/ Supply Air 24 in.

Note: Please refer to the tech guide for listed maximum static pressures

10 Ton

• Fraser-Johnston split system units are manufactured at an ISO 9001 registered facility

Unit Features

• Unit Cabinet Constructed of Powder Painted Steel, Certified At 750 Hours Salt Spray Test (ASTM B-117 Standards).

• Easily converted in the field from vertical to horizontal configuration.

• Slide-out Composite Drain Pan

• Single Circuit Refrigeration

• Adjustable balanced port TXV's

• 2.0 HP Motor and Adjustable Sheave Belt Drive

• Unit ships with 2" Throwaway filters with a standard filter rack that will accept up to 4" filters.

• Short Circuit Current: 5kA RMS Symmetrical

• Intellispeed VFD w/Bypass Warranty

• One (1) Year Limited Warranty on all Other Parts

• Five (5) Year limited Warranty on Electric Heating Elements

Indoor Split System Fraser-Johnston Split-System Indoor

Page: 11

Project Name: PCC SE Center MDF Unit Model #: NS-10C00CTCAA4 Quantity: 2 Tag #: AC-1,2 System: PH-10C00ATEAA5,NS-10C00CTCAA4

Additional Electrical Data

Power supply 208-3-60 Unit min circuit ampacity 7.3 Amps Unit max over-current protection 15 Amps Min Voltage 187 V Max Voltage 252 V Indoor Mtr Voltage 208-3-60 Indoor Mtr FLA 5.8

Page: 12

Project Name: PCC SE Center MDF Unit Model #: NS-10C00CTCAA4

Factory Installed Options

NS-10C00CTCAA4

Equipment Options Option(s) Selected

Product Category: N Split System R-410A Air Handler Product Identifier: S 2-pipe w/Intellispeed Nominal Cooling Capacity: -10 10 Ton Heat Type and Nominal Heat Capacity: C00 Airflow: C 2.0 HP Motor Voltage: T 208/230-3-60 Installation Options: C Intellispeed VFD w/Bypass Additional Options: AA Composite Drain Pan

Field Installed Accessories 1BP0401 - Return Air Block Off Panel (10.7 lbs)

1BS0410 - Base Section (60.0 lbs) 1HW0410 - 2 Row Deep Hot Water Coil (When this accessory is installed, DO NOT operate above the Supply Fan Motor rated HP) (128.0 lbs)

1NF0456 - Single Row Steam Coil (When this accessory is installed, DO NOT operate above the Supply Fan Motor rated HP) (135.0 lbs)

1RG0416 - Return Air Grille (11.0 lbs)

2HJ04701025 - 10 kW 208/230-3 Electric Heat (45.0 lbs)

2HJ04701625 - 16 kW 208/230-3 Electric Heat (47.0 lbs)

2HJ04702625 - 26 kW 208/230-3 Electric Heat (47.0 lbs)

2HJ04703625 - 36 kW 208/230-3 Electric Heat (51.0 lbs)

Page: 13

Project Name: PCC SE Center MDF Unit Model #: NS-10C00CTCAA4

NS/NW Piping, Electrical, & Duct Opening Connection Sizes

Page: 14

Quantity: 2 Tag #: AC-1,2

Typical Applications

Page: 15

Dimensions 7.5 to 10 Ton P1

Page: 16

Dimensions 7.5 to 10 Ton P2

Page: 17

NS/NW 7.5 thru 20 Ton Corner Weights & Gravity

Page: 18

QUESTIONS AND PCC’S ANSWERS TO THOSE QUESTIONS

ITB – SE CAMPUS MDF HVAC REPLACEMENT

PCC has received the following 12 questions, and is providing the answers below. The last item is an informal substitution request, and PCC’s decision to that request also is provided.

Question 1: Please confirm that the controls scope- inclusive of wiring and programing will not be in the scope of the Prime contractor and will be handled by the owner separately.

PCC’s answer to Question 1: Confirmed and correct.

Question 2: Please tell us the full name of “N.C.C” responsible for the controls work.

PCC’s answer to Question 2: Northwest Control Company

Question 3: Will NCC post balance the system? We were assuming that the prime would conduct a pre-balance.

PCC’s answer to Question 3: The prime should hire certified TAB firm to include the pre and post balance as part of their scope.

Question 4: Is the expectation to salvage any of the AC unit being removed from the roof or can we dispose of it?

PCC’s answer to Question 4: Bidders shall cast their bid based on the understanding the selected contractor will remove and dispose of the AC units.

However, PCC reserves the right to discuss any salvage of the existing AC units and the duct work as a possible Change Order with the selected contractor.

Question 5: Will we be able to stage a crane to remove the AC unit from the roof?

PCC’s Answer to Question 5: Yes. The interior parking lot will be a good place to stage a crane.

Question 6: Please provide pictures of the existing roof area for reference.

PCC’s answer to Question 6: Pictures and notes of the roof area, and the roof access are provided as attached to this Addendum #1.

Question 7: May we assume that there is no drywall or painting scope within this project?

PCC’s answer to Question 7: Correct. No drywall, nor painting is part of the project scope of work.

Q&A Continued on Next Page

QUESTIONS AND PCC’S ANSWERS TO THOSE QUESTIONS

ITB – SE CAMPUS MDF HVAC REPLACEMENT

Question 8: What Is the desired extent of protection desired for the data racks?

PCC’s Answer to Question 8: Electronics are to remain active for the duration of the project. The protection required would provide safety from physical damage while allowing the equipment to be properly ventilated. Assuming all the servers will remain active during the construction, and all the electronic equipment will need to be protected would still allow the heat to be ventilated.

Question 9: What is the expectation for temporary HVAC service in this space?

PCC’s Answer to Question 9: Temporary service has already been provided by PCC with the Move and Cool Units.

Question 10: Is it assumed that should there be any long lead items that the final completion date may shift?

PCC’s Answer to Question 10: PCC would like to avoid delays but understand there are procurement and supply chain challenges. We will work with the selected contractor to resolve these challenges and may adjust our project completion date.

Question 11: Is it agreed that substitutions for material that may arrive earlier to avoid long lead items be reviewed/considered?

PCC’s Answer to Question 11: Yes, substitutions will be considered from the selected Contractor to avoid long lead times, but will need to be approved by the engineer and PCC.

Question 12: If there is a COVID-19 shutdown in the school unrelated to the prime contractor's work will they also be required to pause work?

PCC’s Answer to Question 12: A pause in work will depend on the situation and will be discussed, should the need arise, with the selected contractor and PCC.

Informal Substitution Request:

Table 2 on sheet E1.2 specifies that the conduit for these circuits will be “RMC”. I would like to propose that we substitute Electrical Metallic Tubing (EMT) for all locations where the raceway is not subject to severe physical damage.

PCC’s decision as to this request: PCC would accept EMT in the building. On the roof where the conduit is subject to weather and variable conditions, we require RMC.

Roof Access for Mt Tabor building

Stairs leading to roof & Roof Hatch

Roof has multiple tiers existing AC unit is on the top tier.

Existing AC units supporting the MDF Room. The one on the left is the Compu-air and the one on the right is the split Daikin.

Close up Daikin & disconnect

Close up Compu-air

Existing roof penetration supporting both units and additional antenna cabling located on the roof.

Backside of Compu- air & disconnect

Inside roof access dugout. Pathway to inside unit

Overall view of the exiting two units on roof.

SE CAMPUS MDF HVAC REPLACEMENT PROJECT

PCC Solicitation Number: P&CC21-014-ITB Public Bid Opening Information

The Public Bid Opening will be held Thursday, February 3, 2022 commencing at 2:05PM (Pacific) by Zoom teleconference.

The logon information to attend is presented below:

Join Zoom Meeting https://portlandcc.zoom.us/j/94847993102?pwd=LzZ4N3ZFSUZ5RUhhZjBMaktlRXdIQT09

Meeting ID: 948 4799 3102 Passcode: 346315 One tap mobile +13462487799,,94847993102#,,,,*346315# US (Houston) +16699006833,,94847993102#,,,,*346315# US (San Jose)

Dial by your location +1 346 248 7799 US (Houston) +1 669 900 6833 US (San Jose) +1 253 215 8782 US (Tacoma) +1 312 626 6799 US (Chicago) +1 646 876 9923 US (New York) +1 301 715 8592 US (Washington DC) Meeting ID: 948 4799 3102 Passcode: 346315

---- End of Public Bid Opening Information ---https://www.google.com/url?q=https%3A%2F%2Fportlandcc.zoom.us%2Fj%2F94847993102%3Fpwd%3DLzZ4N3ZFSUZ5RUhhZjBMaktlRXdIQT09&sa=D&ust=1643587729933000&usg=AOvVaw0FB3n-Pa2DeRSYgY5uWc96

Addendum 1 - ITB SE Campus MDF HVAC Replacement Project.pdf
ITB Addendum 1 - SE Campus MDF HVAC Replacement.pdf
The purpose of this Addendum is to provide four items of information. These four items follow this Addendum Number 1 Cover Page.
1) Attendance Record at the Mandatory Pre-Bid Conference and Site Inspection
2) Two Substitution Request Forms Submitted and PCC’s Decisions on those requests
3) Questions and Answers, including the requested photographs of the roof project area
4) Public Bid Opening information and teleconference logon details
Attendance Record - ITB - SE Campus MDF HVAC Replacement.pdf
Substitution Requests - ITB SE MDF HVAC Replacement Project - Executed.pdf
Substitution Request - Air Reps.pdf
Solicitation No PCCS21-014-ITB_SE Campus MDF HVAC Replacement_CU-1,2 and AC-1,2 Prior Substitution Request 001 from Sustainable Mechanical Systems.pdf
CU-1,2 and AC-1,2 Prior Substitution Request 001 from Sustainable Mechanical Systems.pdf
MDF HVAC ITB WITH CONTRACT.pdf
Dec 17 Draft ITB - PAGE NUMBERS - SE Campus MDF HVAC Replacement Project.pdf
ATTACHMENT I - SUBSTITUTION REQUEST FORM
Solicitation No PCCS21-014-ITB_SE Campus MDF HVAC Replacement_CU-1,2 and AC-1,2 Prior Substitution Request 001 from Sustainable Mechanical Systems.pdf
FJ AC-CU-1,2 Preliminary Submittal.pdf
Questions, Answers, and Roof Photos - ITB SE MDF HVAC Replacement.pdf
QUESTIONS and ANSWERS - ITB SE MDF HVAC.pdf
Mt Tabor Building Roof (1).pdf

SE CAMPUS MDF HVAC REPLACEMENT PROJECT.pdf

Mt Tabor Building Roof Photos.pdf

File details come from the government source that posted it. Updated .