ADDENDUM #1 FOR NW CHILLER BID 19-7.pdf

PDF 770 KB Posted

Attached to
CHILLER REPLACEMENT AT NORTHWOOD ELEMENTARY SCHOOL
Solicitation number
RFP ROY 190000001877 2
Issued by
Macomb County, Michigan

About this file

This is Addendum #1 to a design/build bid issued by Royal Oak Schools for a Medium Pressure UV System at Royal Oak Middle School Pool. The project bid was originally due on Monday, April 29, 2018 at 11:00 AM local time. A pre-bid meeting was held on April 18, 2019, with an attendee sign-in sheet included as an attachment. Bidders interested in scheduling additional job site visits must contact Mark Paulus at mark.paulus@royaloakschools.org or (248) 880-6791, or Patrick Murphy at patrick.murphy@royaloakschools.org. All site visits must be scheduled in advance, and no unscheduled building visits are permitted.

The addendum clarifies a discrepancy regarding warranty duration between the front-end documents and specification section 131500. The warranty period shall be three years, superseding the conflicting 18-month duration referenced in other contract documents. All questions regarding the project should be directed to Mark Paulus using the contact information provided above.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM 1

Project: Design/Build Medium Pressure UV System at Royal Oak Middle School Pool

Bid Due date: Monday, April 29, 2018 at 11:00 AM Local Time (unchanged)

I. General Information

1. For questions contact Mark Paulus at mark.paulus@royaloakschools.org or (248) 880-

6791.

2. A review of the documents occurred at the pre-bid meeting.

3. If any bidders would like schedule another job site visit, contact Mark Paulus or Pat

Murphy at patrick.murphy@royaloakschools.org. Do not visit the building without a scheduled visit.

4. A schedule review occurred at the pre-bid meeting.

5. Attached is the sign in sheet for the pre-bid meeting held on April 18, 2019.

II. Questions and Answers

1Q. The warranty duration in the front end documents says 18 months and in specification section 131500 says 3 years. Please confirm duration.

1A. The warranty duration shall be 3 years.

END