Plumbing Services at the Florida State Fire College
Solicitation number
ITB-03548
Issued by
Marion County, Orlando City, Florida

About this file

This document is an addendum to an Invitation to Bid (ITB) issued by the Florida Department of Financial Services, Division of State Fire Marshal, for plumbing services at the Florida State Fire College. The addendum includes questions and answers as well as modifications to the ITB.

The ITB seeks competitive sealed responses from qualified vendors to provide plumbing services. The contract term is for 3 years with a 3-year renewal option. The addendum revises the requirements for a licensed master plumber or licensed general contractor, clarifies the position descriptions, and provides pricing instructions for the initial and renewal contract terms. There will be a mandatory pre-response conference on 12/15/22.

View the file

Other files

File Type Posted
2223-02 ITB FM_Plumbing_Svcs.pdf PDF
Exhibit1.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB No. 2223-02 ITB FM Addendum 1

QUESTIONS AND ANSWERS

2223-02 ITB FM

Plumbing Services for the Florida State Fire College

Addendum No. 1

Failure to file a protest within the time prescribed in section 120.57(3), Florida Statutes, or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes.

This Addendum consists of the following sections:

A. Questions and Answers B. Modifications to the ITB

Below are the questions and answers related to this solicitation. In the table below, the Department of Financial Services (Department) has answered each of the questions submitted by potential respondents.

No. Attachment Identifier

Section Number

Sub-Section Reference

Item Reference

Page No. Question Department Response

1. Attachment 3 Price Response Form

Position Description 1 of 2 Being the General Contractor do I have to have a Master plumber on the payroll full time or is on an as needed basis acceptable? I am a Journeyman plumber. Having a Master Plumber full time would be very expensive and their expertise aren’t required daily.

See revised Attachment 3, Price Response Form.

2 Attachment 3 Price Response Form

Position Description 2 of 2 Need clarification of Item 3 – under Position Description – the first description says Licensed Plumber – do they mean Master Plumber?

See revised Attachment 3, Price Response Form.

3 Attachment 3 Price Response Form

Renewal Contract Term Pricing

2 of 2 Item 3 & 4 – Because this is the initial bid for WaterTech, do I need to fill this portion out?

Yes.

B. Modifications to the ITB: Insertions to the ITB are indicated by an underscore, deletions are indicated by a strikethrough. Please be advised that the following changes are also noted within the posted document titled 2223-02 ITB FM.

Attachment 3

DEPARTMENT OF FINANCIAL SERVICES

2223-02 ITB FM

Price Response Form

Attachment 3

The Contractor must enter hourly rates for labor services used in performing all work which may be required during the period of the contract. Labor rates shall be paid for productive hours only. Labor rates shall include all direct and indirect costs such as transportation, overhead, contractor supervision, and profit, etc. The Respondent must provide a price for each item listed below or its bid shall be deemed non-responsive and rejected. The prices quotes will be all inclusive to perform the required services under this Contract. The Contractor shall furnish all of the necessary personnel, labor, equipment, services, materials, permits, licenses and insurance, replacement parts, and otherwise do all things necessary to complete the services in full accordance with Attachment 2, Statement of Work.

Note: The estimated number of hours per month listed in Items 1 and 2 are for bidding purposes only and do not guarantee a minimum amount of work. The selected Contractor will be paid for actual services provided, as requested by the Department.

INITIAL CONTRACT TERM PRICING – THREE (3) YEARS (36 MONTHS)

ITEM 1

Hourly Labor Rates – Regular time – During Business Hours on Business Days.

Position Description Year 1 Year 2 Year 3 50 Hours Licensed Master Plumber or Licensed General Contractor

@$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

50 Hours Licensed Plumbing Journeyman @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

50 Hours Plumbing Apprentice @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

50 Hours Plumbing Helper @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______ Total Amount for Each Year $____________________ $______________________ $_____________________

Item 1 – Grand Total (Total of Year 1 + Year 2 + Year 3) $____________________

ITEM 2

Labor Rates – Overtime - 5:00 pm to 7:30 am, Mon – Fri, Weekends and Holidays Charge is not to exceed one and one-half (1 ½) times the labor rate for work performed during regular hours.

Year 1 Year 2 Year 3 20 Hours Licensed Master Plumber or Licensed General Contractor

@$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

20 Hours Plumbing Licensed Journeyman

@$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

20 Hours Plumbing Apprentice @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

20 Hours Plumbing Helper @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

Attachment 3

Total Amount for Each Year $____________________ $______________________ $_____________________

Item 2 – Grand Total (Total of Year 1 + Year 2 + Year 3) $_____________________

Total Initial Term (Grand Total of Item 1 + Item 2) $_____________________

RENEWAL CONTRACT TERM PRICING – THREE (3) YEARS (36 MONTHS)

ITEM 3

Hourly Labor Rates – Regular time – 7:30am to 5:00pm, Monday through Friday Position Description Year 1 Year 2 Year 3 50 Hours Licensed Master Plumber or Licensed General Contractor

@$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

50 Hours Plumbing Apprentice @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

50 Hours Plumbing Helper @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______ 50 Hours Plumbing Journeyman @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

Total Amount for Each

Item 3 – Total (Total of Year 1 + Year 2 + Year 3)

ITEM 4

Labor Rates – Overtime - 5:00pm to 7:30am, Mon – Fri, Weekends and Holidays Charge is not to exceed one and one-half (1 ½) times the labor rate for work performed during regular hours.

Year 1 Year 2 Year 3 20 Hours Licensed Master Plumber or Licensed General Contractor

@$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

20 Hours Licensed Plumbing Journeyman @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

20 Hours Plumbing Apprentice @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

20 Hours Plumbing Helper @$________/HR.=$_______ @$________/HR.=$_______ @$________/HR.=$_______

Total Amount for Each

Item 4– Total (Total of Year 1 + Year 2 + Year 3)

Total Renewal Term (Total of Item 3 + Item 4)

Grand Total: (Total Initial Contract Term + Total Renewal Contract Term) Note: Grand Total will be used for Basis of Award