PMAA, SEPU, Juniper Road Chip Seal, Maintenance, C27PU1
Solicitation number
DQ1 PMAA 2027000012 4
Issued by
El Paso County, Colorado

About this file

This is an addendum to a request for proposal issued by the Colorado Parks and Wildlife Southeast Regional Office for the Juniper Road Chip Seal maintenance project at Lake Pueblo State Park (Contract ID: C27PU1). The addendum clarifies project requirements regarding striping removal and paint markings. All yellow solid and dashed road centerline striping and ADA emblems in the parking lot that show paint chipping must be removed prior to chip sealing operations. The cost for proper removal of existing striping is to be included in Lump Sum Base Bid Item #5, Restripe all Paint Markings. Final questions regarding the project were due by July 29, 2026 at 10:00 a.m., and completed bid schedules were required to be submitted by email to shaun.gordon@state.co.us by 1:00 p.m. on July 31, 2026. A bid tabulation summary was to be provided to all bidders following the submission deadline.

The addendum does not address pricing terms, set-asides, or other financial details, as it serves solely to clarify specific scope items related to surface preparation and marking work. Proposers were instructed to acknowledge receipt of this addendum on page 1 of their bid schedules to ensure compliance with the revised project specifications.

View the file

Other files

File Type Posted
ATTENDANCE LIST FOR THE PRE BID.pdf PDF
Appendix D - SC6221LMBond (1).docx DOCX document
Appendix B - Drawings.pdf PDF
Appendix A - 2018 CPW GCs 071818 FINAL.pdf PDF
BID DOCUMENTS 071426.pdf PDF
Appendix C - SC622PerfBond (DNR) (1).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Southeast Regional Office | 4255 Sinton Road | Colorado Springs, CO 80907

ADDENDUM ONE

July 29, 2026

Subject: Addendum Number One to: DQ1: 2027*12

PMAA-SEPU-Lake Pueblo State Park – Juniper Road Chip Seal, C27PU1

To Whom It May Concern:

The following items clarify or revise the language of the subject request for proposal and should be considered by all Proposer’s when submitting their proposal. Make sure to note receipt of this addendum on page 1 of the Bid Schedule. Announcements and answers to questions are in Bold type:

1. It was noted that the yellow solid and dashed road centerline striping and the ADA emblem in the parking lot has paint chipping off in several areas. Should we expect to remove the existing striping?

Yes, all yellow solid and dashed road centerline striping and the ADA emblem in the parking lot shall be removed prior to chip sealing. The cost for the proper removal shall be included in the Lump Sum Base Bid Item #5, Restripe all Paint Markings

End of Addendum #1

Final questions were due by July 29, 2026 at 10am. Please make sure to have your completed Bid Schedules emailed to me by 1pm on July 31, 2026 at shaun.gordon@state.co.us . A bid tabulation/summary will be emailed to all bidders.

Thanks, Shaun C. Gordon, RLA Design & Construction Project Manager Colorado Parks and Wildlife Southeast Regional Office 4255 Sinton Road Colorado Springs, Colorado 80907 email: shaun.gordon@state.co.us mailto:shaun.gordon@state.co.us mailto:shaun.gordon@state.co.us