Addendum 1 is a document issued by Romeo-Washington-Bruce Parks and Recreation for a 2024 Asphalt Walking Path Repair, Extension, and Side Playground Parking Lot project located at Bruce Township Park in Bruce, Michigan. The addendum provides critical clarifications for potential bidders, including project completion requirements within the current calendar year, insurance obligations, and detailed specifications for path and parking lot improvements. The project involves repairing and resurfacing 3,400 linear feet of existing walking path, adding a 563 linear foot path extension, and regrading a gravel parking lot to include 2 ADA-compliant and 10 regular parking spaces.

The addendum specifies technical requirements for path repair, including cleaning and filling cracks, removing and replacing uneven asphalt, and resurfacing with Hot Mix Asphalt (HMA). Bidders are instructed to include ground restoration costs in their quotes, covering natural drainage slopes, ground repairs, topsoil, seeding, and straw. The bid documents are available on the rwbparksrec.org website under the BIDS section, and bidders must provide comprehensive insurance as outlined in the vendor packet. The project emphasizes matching new path construction to existing path specifications, using a compacted base and 3" HMA topping.

View the file

Other files

File Type Posted
Addendum 2.pdf PDF
BID PACKET Bruce Twp Park 2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Romeo-Washington-Bruce PARKS AND RECREATION 361 Morton St., Romeo MI 48065

CONTACTS

Clara Russell, Director 586-752-6543 Ext 1406 russellc@rwbpr.org Lynne Walker, Facility Maint. Coordinator 586-752-6543 Ext 1412 walkerl@rwbpr.org

ADDENDUM 1

2024 Asphalt Walking Path Repair, Extension and side playground Parking Lot

CLARIFICATION 1:

Project is to be completed in this calendar year.

Chosen bidder must provide needed insurance as overviewed in vendor packet: rwbparksrec.org (find under BIDS)

CLARIFICATION 2:

Restoration of grounds is expected so include in quote (natural slopes for drainage, ground repairs, topsoil, seed & straw)

CLARIFICATION 3:

Paths are 6 ft wide.

Corrected calculations for bids.

Existing Path: 3,400 LF x 6 ft = 20,400 Sq Ft Path Extension: 563 LF x 6 ft = 3,378 Sq Ft

Clean, tack & fill cracks over 1.5” with HMA.

Smaller cracks rubbler crack fill.

Remove and replace uneven/sunken/broken asphalt on path replacing with 3” HMA.

Resurface existing path with 2” HMA

New Path is to match existing path using compacted base, topped with 3” of HMA

CLARIFICATION 4:

Gravel Parking Lot is to be regraded and leveled using existing material and/or include additional material cost as needed in price.

Include (2) ADA and 10 regular parking spaces as space allows.