Addendum 1 Bid Pack 3B.pdf

PDF 492 KB Posted

Attached to
472/17398. SMD Bid Pkg 3 Razor Ribbon Project - Various CFs
Solicitation number
RFQ-171-180000000615-4
Issued by
Kalamazoo County, Michigan

About this file

This is Addendum No. 1 issued by Matrix Consulting Engineers, Inc. for correctional facility projects at five Michigan facilities: Charles Egeler, Gus Harrison, Lakeland, Parnall, and Thumb Correctional Facilities. The addendum modifies the original bid documents, extending the bid due date to June 13, 2018, and clarifying that the project schedule may start up to September 17, 2018, with completion required within 150 days of the start date. The projects appear to involve razor ribbon replacement and perimeter fence enhancements at various facilities, as evidenced by the meeting attendance records included.

The addendum includes meeting attendance records from five separate pre-bid meetings held on May 21-22, 2018, at different times for each facility. The meetings were attended by representatives from various companies including Matrix, SDVGC, Nationwide, MKC Group, MGT Fence, MDOC, and others. A significant modification noted for the Parnall Correctional Facility project is that a building will no longer be demolished as previously specified. Sign sheets were attached for all facilities, and drawings were reissued for each location.

View the file

Other files

File Type Posted
Specifications - 3B 17398.pdf PDF
Drawings - 3B Thumb.pdf PDF
Drawings - 3B Egeler.pdf PDF
Drawings - 3B Lakeland.pdf PDF
Drawings - 3B Parnall.pdf PDF
LEIN Request REV 04-2018 Bid Pkg 3.pdf PDF
Addendum 2 Bid Pack 3B - SIGMA.pdf PDF
Addendum 3 Bid Pack 3B.pdf PDF
Drawings - 3B Gus Harrison.pdf PDF
Advertisement Bid Pkg 3B 17398.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CO N S U LT I N G EN G I N E ER S , I N C.

1601 E. GRAND RIVER, LANSING, MI 48906

PHONE: (517) 487-2511

FAX: (517) 487-2544

ADDENDUM NO. 1

Date: 05/24/18 Project Name:

Charles Egeler Correctional Facility- File # 472/17403.SMD - INDEX NO. 60230

Gus Harrison Correctional Facility- File # 472/17402.SMD – INDEX NO. 24590

Lakeland Correctional Facility- File # 472/17399.SMD – INDEX NO. 45730

Parnall Correctional Facility- File # 472/17430.SMD– INDEX NO. 21100

Thumb Correctional Facility- File # 472/17398.SMD– INDEX NO. 34660

This Addendum is issued for the purpose of modifying and/or clarifying the original Contract Documents and shall take precedence over them.

All work included herein shall be in accordance with the original drawings and specifications except as specifically noted herein. All incidental items required to provide the following modifications shall be included even though not specifically described.

This addendum is being sent to all bidders receiving plans and specifications. Receipt of this Addendum shall be noted on the Bid Summary in the appropriate location.

Clarification and Questions:

A1.1 Clarification: Bid due date has extended to June 13, 2018.

A1.2 Clarification: project schedule contract may start project up to September 17, 2018 complete within 150 Days of start date.

Charles Egeler: (Drawings Reissued)

A1.3 Sign sheet attached

ADDENDUM NO. 1

Gus Harrison: (Drawings Reissued)

A1.1 Sign sheet attached.

Lakeland: (Drawings Reissued)

Parnall: (Drawings Reissued)

A1.1 Building will no longer be demolished.

A1.2 Sign sheet attached.

Thumb: (Drawings Reissued)

End of Addendum No. 1