This document is Addendum 1 to the bidding documents for the Cooper Street Correctional Facility - Asphalt Repairs contract, issued by the Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Design and Construction Division. The addendum provides clarifications and details regarding the project, including a 120-day contract duration, the ability to have two crews working simultaneously (one inside the secured area and one outside), the requirement for concrete work at the food services loading dock to be completed first, and that material testing will be provided through the Professional Services Consultant's (PSC) contract. The addendum also notes that an administrative gate manifest can be used to expedite entry of materials into the secured area, bathroom facilities will be made available by the facility, and no electrical work will be required by the contractor. A pre-bid sign-in sheet is attached.
The contract opportunity is for asphalt repairs at the Cooper Street Correctional Facility in Jackson County, Michigan. The bid opening date is March 6, 2024. The addendum indicates that Ground Penetrating Radar is required for areas where underground storm sewer and electrical lines will be installed, and any found utilities shall be hydro-excavated, with payment for hydro-excavation coming from an allowance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
2/26/2024
PROJECT NAME
Cooper Street Correctional Facility – Asphalt Repairs
FILE NUMBER
472/23353.DPL
PROFESSIONAL
Beckett & Raeder, Inc.
PROJECT DIRECTOR
David Lenz, AIA
BID OPENING DATE:
3/6/2024
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
Pre-Bid Walk-Through Notes:
1. Contract duration will be 120 days from the Notice to Proceed.
2. Two crews can be working simultaneously, one inside the secured area, one outside the secured area.
3. Concrete work at the food services loading dock shall be completed first in order to avoid impacts to new asphalt. This concrete shall be completed in two or more phases.
4. Material testing shall be provided through the PSC’s contract – not the contractor.
5. An administrative gate manifest can be created to expedite entry of materials inside the secured area.
6. Bathroom facilities will be made available by the facility.
7. Sallyport concrete is not part of the scope of work. Access to the sallyport shall be maintained at all times.
8. Pavement work at each housing unit shall be completed in two or more phases, noting that access to one door shall be maintained at all times.
9. No electrical work shall be required by the contractor, as the facility will be responsible for disconnecting the compactor.
10. Ground Penetrating Radar is required for areas where underground storm sewer and electrical lines will be installed. If something is found, it shall be hydro-excavated. Payment for hydro-excavation shall be out of the allowance.
Other Items:
1. Pre-Bid Sign-In Sheet is attached.
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: Kristofer Enlow, P.E., Beckett & Raeder, Inc. DATE: 2/26/2024
APPROVED BY:
PROJECT DIRECTOR: DATE: 2/26/2024