This Construction Bid Addendum No. 1 is issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration Design and Construction Division for the Bay City State Park Campground Improvements project. The project, managed by professional firm Beckett & Raeder, Inc. with Project Director Chris Schanbeck, PE, involves campground infrastructure improvements at Bay City State Park. Key dates include a mandatory pre-bid meeting held on March 28, 2026 at 1:00 PM at 3582 State Park Drive, Bay City, Michigan, with the addendum issued on November 4, 2026. The bidder question deadline was extended to November 11, 2026 at 5:00 PM due to Veterans' Day conflict, with bids due November 18, 2026 at 2:00 PM via electronic submission to SIGMA VSS. The anticipated State Ad Board approval is December 15, 2026, with preconstruction kickoff and Notice to Proceed anticipated January 6, 2027. The contract duration is specified as 152 calendar days from Notice to Proceed to Substantial Completion (June 7, 2027), with final completion 21 calendar days thereafter (June 28, 2027), subject to liquidated damages of $1,000 per day after substantial and final completion.
The addendum addresses critical project requirements including directional drilling for waterlines and electrical conduits to minimize excavation and tree impact, hydroseed restoration with selective drill seeding coordinated through a single landscaping subcontractor, and a $150,000 allowance for provisionary or contingency scope. Bidders must submit two ADD alternates for copper conductor (West and East), provide bid security equal to five percent of the base bid, obtain Michigan Contractors License registration, and include the asbestos attestation page. Contractors are responsible for obtaining permits from LARA and Bay County Road Commission, managing 100 percent on-site supervision, and adhering to working hours between 7:00 AM and 6:00 PM on weekdays only unless written permission is granted. The project emphasizes use of Michigan products and recycled or environmentally friendly materials where price, quality, and performance are equal or superior to alternatives, with performance and payment bonds and comprehensive insurance documentation required after award notification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
11/4/2026
PROJECT NAME
Bay City State Park Campground Improvements
FILE NUMBER
751/22413.CTS
PROFESSIONAL
Beckett & Raeder, Inc.
PROJECT DIRECTOR
Chris Schanbeck, PE
BID OPENING DATE:
11/18/2026
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
Pre-Bid Walk-Through Notes:
1. Bids will be due 1-week later due to Veterans’ Day conflict. Bid Due Date: November 18th at 2:00 p.m.
2. Bidder question deadline will be extended 1-week to November 11th at 5:00 p.m.
3. Waterlines and electrical conduits are to be primarily directionally drilled/bored to limit excavations and impacts to the roads and trees.
4. Hydroseed with some initial large areas drill seeded is preferred for restoration. Coordinate restoration work for various disciplines excavations through a single landscaping subcontractor.
Other Items:
1. Pre-Bid Sign-In Sheet is attached.
2. Mandatory Pre-bid Meeting Agenda is attached.
3. Bidders Questions and PSC Responses
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: Kristofer Enlow, P.E., Beckett & Raeder, Inc. DATE: 11/4/2026
APPROVED BY:
PROJECT DIRECTOR: DATE: 11/4/2026
MANDATORY PRE-BID MEETING
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
Project: Bay City State Park Campground Improvements
File Number: 751/22413.CTS
Date & Time: Wednesday, March 28, 2026, at 1:00pm
Location: 3582 State Park Drive, Bay City, MI 48706
A. Introductions and Sign-in Sheet
All attendees are to sign-in. Individuals can represent only one firm that may submit a bid.
B. Addendum will be issued to document any questions, issues or changes to the contract documents that arise during bidding. All questions or issues shall be submitted via email including any items discussed in this meeting that are not documented in addendum 1. The sign-in sheet will be issued in addendum 1.
C. During the bid submit alternatives for named or specified materials or equipment for possible approval and inclusion by addendum.
D. Bid Submissions
1. Execute and include all required forms and documents. Refer to Bidder’s Checklist.
a. Note the allowance, $150,000, on the bid schedule to be included in the bid for provisionary or contingency scope.
b. Note 2 ADD alternates for copper conductor (West and East).
c. Bid Security equal to five percent (5%) of the base bid is required.
d. LEO state project registrations (SPR) is required to be submitted with bid.
e. Must include the asbestos attestation page (unsigned) even though marked as
‘Project Does Not Contain Asbestos Abatement’.
2. Bids shall be submitted electronically in Adobe PDF format to SIGMA VSS.
a. Maximum file size for uploading attachments is 25 MB which may require breaking into multiple files.
b. Do not wait until the last minute. Submit early. Pay attention to various inputs (early payment discounts are not considered in bid, etc.)
c. If you experience issues or have questions regarding your electronic submission, you must work through the SIGMA Help Center for assistance and if necessary, receive a ticket number prior to contacting the DCD.
E. Items to be provided by Contractor after notification of award including but not limited to:
Performance and Payment Bonds, Proof of Insurances: Liability (CGL, ULAL/VL, WC, EL) & Builder’s Risk
F. Use Michigan products and recycled and/or environmentally friendly products whenever possible where price, quality and performance are equal to, or superior to non-Michigan products.
G. Owner may request to eliminate entire line items from the bid schedule via a post-bid addendum as necessary to fit within available funding budget. Changes to bid schedule line-item pricing will NOT be permitted as part of this request. All related trades (restoration, etc.), OH&P and General Conditions (taxes, insurance, bonds, permits, fees, supervision, safety, mobilization, travel, closeouts, warranties, etc.) should be applied to each line item accordingly.
RFQ 751/22413.CTS PRE-BID MEETING 10/28/2026
H. No exceptions, qualifications, conditions, etc. are permitted.
I. Schedule
1. November 4, 2026, 2:00pm, any questions must be submitted. Email to kenlow@bria2.com.
MAY BE EXTENDED 1-WEEK.
2. November 11, 2026, 2:00pm, Bids are due on SIGMA VSS. MAYBE EXTENDED 1-WEEK.
3. December 15, 2026, Anticipated State Ad Board approval.
4. January 6, 2026, Anticipated Pre-construction Kickoff Meeting and Notice to Proceed (to be confirmed as contract is executed).
5. Contract Time specified as 152 calendar days from notice to proceed to Substantial
Completion, June 7, 2026. Final completion 21 calendar days after substantial completion, June 28, 2026.
6. Liquidated damages specified at $1,000 per day after substantial and final completion.
7. Contractor to provide the initial (Rev. 0) critical path milestone schedule for review and update as key milestones are adjusted or at least monthly. Include normally anticipated 20% float time for unforeseen delays (weather, deliveries, etc.).
J. Permits - The contractor is responsible for obtaining and paying for all permits required by LARA and Bay County Road Commission Right-of-Way. The Contractor is responsible for coordinating and scheduling all inspections.
K. Project sign is required.
L. Note special warranty requests (primarily electrical where typically 2-years on gear). Contractor to aid in winterization late fall 2027.
M. The Contractor is responsible for managing and supervising the work and must be on site 100% of time.
N. Testing – Beckett & Raeder will perform inspections, tests, or approvals for those materials required to meet quality control standards specified in the contract documents. However, the Contractor must assume full responsibility for coordination and retesting, per Section 00700.
O. Special Working Conditions. Refer to Appendix II for additional information.
1. Working hours shall be daylight hours between 7:00 AM and 6:00 PM during normal business days (Monday through Friday). Additional weekday hours or work on weekends or State Holidays is NOT allowed unless specific written permission is granted.
2. Maintain Secure Entrance to keep public out of campground. Provide all necessary barricading, fencing etc. Direct public to the park staff/headquarters.
3. Park will be moving picnic tables. Contractor to move and replace fire rings as deemed necessary.
4. Coordinate work to prevent damage to existing trees and pavements. Some field adjustments of utilities should be considered a normal part of the work such that unit quantities/lengths are not highly accurate with significant adjustments coordinated with Beckett & Reader. Utilities shall be staked in advance and reviewed with project team prior to construction. Identify areas of additional damage to trees or pavements as early as possible (during bid ideally) for review. Small trees (<6-inch) that require removal shall be included in the Work at no additional cost.
P. PSC to review technical and any additional information followed by site walk.
initiative
Beckett & Raeder, Inc.
535 West William Suite 101 Ann Arbor, MI 48103
734.663.2622 ph
734.663.6759 fx www.bria2.com
Traverse City Office 148 East Front Street Suite 307 Traverse City, MI 49684
231.933.8400 ph
231.944.1709 fx
Petoskey Office 113 Howard Street Petoskey, MI 49770
231.347.2523 ph
231.347.2524 fx
Grand Rapids Office 100 Cesar E. Chavez Ave SW Suite 300 Grand Rapids, MI 49503
616.585.1295 ph
Bay City State Park Campground Improvements
751/22413.CTS
Response to Bidders Questions
1. Q: Can we abandon existing electrical in-place, instead of remove it?
A: Demolition Key Notes on E1.0 and E1.1 describe the scope. The NEC requires that the wiring be removed completely (if installed in conduit), so the demolition work needs to include the complete removal of the existing wiring. The underground conduits can be abandoned in place but must be removed at the demolished pedestal location to at least 24” below finished grade and then cap and abandon in place.
If the existing feeders are direct buried cables, then remove the direct buried cables need to be removed to at least 24” below grade, cap the wiring, tape and tag to indicate abandoned in place and no longer energized.
Conductors cannot be abandoned in place and will need to be removed.
2. Q: 3” to 3.5” conduits will not fit in specified pedestal.
A: 1. Sheet E3.1
a. Revise Conduit & Wiring Schedule Mark 21 & 22 conduit size to be 3” in lieu of 3-1/2” conduit. The 3-600kcmil + 1#1/0 GRD will fit within the 3” conduit noted. Contractor should utilize compact aluminum conductors.
Note that this revision applies only to one (1) feeder (W13), as indicated on the One-Line Diagram.
2. Sheet E3.3
a. Revise Conduit & Wiring Schedule Mark 21 & 22 conduit size to be 3” in lieu of 3-1/2” conduit. The 3-600kcmil + 1#1/0 GRD will fit within the 3” conduit noted. Contractor should utilize compact aluminum conductors.
Note that Mark 21 & 22 feeder sizes are not used for any of the feeders on this sheet (East Campground) and is only revised for reference only related to the feeder sizes serving pedestals.
3. Q: Could you please tell me if we are required to submit the Appendix III - Exhibit 1 – Byrd Anti-Lobbying Certification with our bid proposal?
initiative
A: Yes
4. Q: Are we required to submit State Project Registrations with our proposal?
A: Yes