Addenda No. 1 8-8.docx
DOCX document 50 KB Posted
- Attached to
- 25-0501 Renwick Bell Tower Repair
- Solicitation number
- 71801
- Issued by
- Colonial Heights City, Virginia
About this file
This document is an Addendum No. 1 issued by the City of Fredericksburg, Virginia in relation to IFB # 25-0501 for the Renwick Bell Tower Repairs project. The addendum summarizes questions asked and responses provided at the pre-bid meeting. Key details include: the project timeline is 4 months, the work hours are 7AM to 7PM Monday through Friday, 9AM to 9PM Saturday and Sunday, and there are no fees for right-of-way parking. The contractor has the option to use either a portable manlift or scaffolding to access the bell tower, and there are requirements for repairing the exterior stucco, brick masonry, and architectural stone elements using historically accurate materials and techniques.
The contract opportunity is for the Renwick Bell Tower Repair project located in Stafford County, Virginia. The due date for bids is August 19th, 2024 at 2:00 PM EST. Permits are required and should be included in the contractor's pricing. There are no fees for building permits, but the contractor is responsible for obtaining them. The contractor is expected to broom sweep the interior of the bell tower as part of the cleanup.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Fredericksburg Telephone: 540.372.1017 P.O. Box 7447 Fax: 540.372.12.15 Fredericksburg, VA 22404-7447
August 8, 2024
ADDENDUM NO.1 TO ALL OFFERORS:
Reference –IFB # 25-0501 Commodity: Renwick Bell Tower Repairs DUE DATE: August 19th, 2024 – 2:00 P.M. EST
The following is a general summary of the questions asked at the pre-bid meeting, edited for clarity, along with the City’s responses.
1. When will the City issue a Notice to Proceed date, once a vendor is selected?
A. TBD
2. Can the entrance of the building be used for staging?
A. Yes, inside of the building is an open space for staging.
3. Should all of the dimensions for the wood ledgers match perfectly?
A. No. There are allowable tolerances for the new wood ledgers and joists (and other new framing members). In general, members should be within ¼ inch of specified dimensions. As discussed at the pre-bid meeting, the type of species to be used for replacement and supplemental members is to be determined based on available stock. We will work with the selected Contractor to determine the wood species’ that are available and the available sizes of wood members from the selected species.
4. Are there bathrooms available inside of the building?
A. Yes, bathroom are available inside of the building for usage.
5. Where will the dumpster be staged?
A. Dumpsters can be staged in front of the building in reserved parking areas or behind the building.
6. Where are the contractors allowed to park?
A. In front of the building. There is also a small parking area in the back of the building.
7. Are there fees for right-of-way parking?
A. No, there are no fees for right-of-way parking.
8. Are there fees for building permits?
A. Yes and should be included
9. Is there a basement? Would contractor need access to the basement?
A. No
10. What are the working hours to block off the parking spots?
A. 7AM to 7PM Monday thru Friday, 9AM to 9PM Saturday, Sunday, and holidays
11. What is the tolerance for variance of matching dimensions on the various joists?
A. Within ¼ inch of specified dimensions (see comments at Question 3 above).
12. How is the contractor expected to clean the inside of the bell tower?
A. The bell tower should be broom swept.
13. Is there lead paint?
A. Assume there is lead paint and plan accordingly
14. What is the projected timeline of this project?
A. Four months
15. Renwick building access (does vestibule need to remain open or are there other access points)?
A. No, the vestibule is not currently open and can remain closed throughout construction. There are other entry points on the south and north sides of the building
16. What options are available for accessing the bell tower from the exterior?
A. The Contractor has the option of utilizing either a portable manlift or scaffolding. As discussed at the pre-bid meeting, if the Contractor elects to use a portable manlift, they will need to obtain a right-of-way permit for closure of parking spaces and one travel lane in front of the building to accommodate safe operation of the manlift. If the Contractor elects to utilize scaffolding, the Contractor will need to submit shop drawings of the scaffolding for review and approval.
17. Is there a crawlspace under the vestibule?
A. To our knowledge there is not a crawlspace under the vestibule.
18. What are requirements for stucco patching? Is sampling required?
A. Requirements for repair of the exterior stucco are stipulated in Specification Section 092300 “Cement Plaster (Stucco) Repair”. The specification does not stipulate that sampling of the existing stucco is required; however, it does require preparation of mock-up repairs for review and approval. Although the stucco is not original to the building, the intent of this project is to replicate existing materials as much as possible. As such, the Contractor shall take samples of the existing stucco and submit them to a qualified laboratory/materials manufacturer for analyses; and, the repair mortars should match existing components.
19. What are acceptable materials for brick mortar and interior parging repair at window/louver openings?
A. Requirements for brick masonry repair and repointing; and, repair deteriorated parging at window/louver openings; and repair of architectural stone elements are stipulated in Specification Section 040120.6 “Brick Masonry Repair & Repointing”. In Paragraph 2.5 “Miscellaneous Materials”, Paragraph A, this Specification references Portland Cement as an approved material. Please note that the use of Portland Cement is strictly limited to patching mortars wherein the mortar is used to recreate a missing portion of an existing brick unit or architectural stone unit. REI anticipates that there will be limited applications for this type of repair with the brick masonry and the more typical repair of a deteriorated brick masonry unit will be replacement with an historic brick. As stipulated in the Specification, all repointing and parging repair is to be performed with historically accurate, lime-based repair mortars.
image1.png