This document is the Project Manual for structural repairs to the Renwick Courthouse Bell Tower in Fredericksburg, Virginia. The project is being managed by the City of Fredericksburg and the work is to be performed in accordance with the United States Department of Interior - National Park Service's "Guidelines for Preserving, Rehabilitating, Restoring & Reconstructing Historic Buildings". The repairs include structural wood framing repairs, roofing and flashing repairs, stucco and sealant repairs, window and louver repairs, and brick masonry repairs. The work will be performed on a unit price basis with estimated quantities provided for various types of repairs, and the contractor will be reimbursed based on the actual quantities of work completed. The project bid set is dated May 31, 2024.

The pricing for the project will be based on the unit prices submitted by the contractor, with allowances established for various repair categories. The contract will be awarded to a single prime contractor. There is no indication of any set-asides or incumbent contractors. The work is to be funded by the City of Fredericksburg, but the specific funding sources are not provided. The contract duration and any renewal options are not specified.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual Bid Set

Structural Repairs, Renwick Courthouse Bell Tower

815 Princess Anne Street Fredericksburg, Virginia

May 31, 2024

Renwick Courthouse Bell Tower, Bid Set May 31, 2024 City of Fredericksburg STRUCTURAL REPAIRS

TABLE OF CONTENTS

Division Section Title Pages

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

000101 003143 004321 004322 004373

PROJECT TITLE PAGE

PERMIT APPLICATION

ALLOWANCE FORM

UNIT PRICE FORM

PROPOSED SCHEDULE OF VALUES

SPECIFICATIONS GROUP

General Requirements Subgroup

DIVISION 01 – GENERAL REQUIREMENTS

011000 012100 012200 012500 013100 013200 013233 013300 014000 015000

SUMMARY

ALLOWANCES

UNIT PRICES

SUBSTITUTION PROCEDURES

PROJECT MANAGEMENT AND COORDINATION

CONSTRUCTION PROGRESS DOCUMENTATION

PHOTOGRAPHIC DOCUMENTATION

SUBMITTAL PROCEDURES

QUALITY REQUIREMENTS

TEMPORARY FACITILITES AND CONTROLS

Facility Construction Subgroup

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION 4

DIVISION 04 - MASONRY

040120.6 BRICK MASONRY REPAIR & REPOINTING 16

DIVISION 05 – METALS

050170.51 050170.61

DECORATIVE METAL CLEANING

METAL ROOFING REPAIR

DIVISION 06 – WOODS, PLASTICS, AND COMPOSITES

061310 WOOD FRAMING REPAIRS 5

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

076200 SHEET METAL FLASHING AND TRIM 7

DIVISION 08 - OPENINGS

080152.61 WOOD WINDOW REPAIRS 10

DIVISION 09 – FINISHES

090190.52 092400

MAINTENANCE REPAINTING

CEMENT PLASTER (STUCCO) REPAIR

END OF TABLE OF CONTENTS

000101 - PROJECT TITLE PAGE Page 1 of 1

DOCUMENT 000101 - PROJECT TITLE PAGE

1.1 PROJECT MANUAL

A. Structural Repairs.

B. Renwick Courthouse Bell Tower

C. 815 Princess Anne Street, Fredericksburg, Virginia.

D. Architect Project No. 800.094.

E. Restoration Engineering, Inc.

F. 10503 West Drive, Suite A.

G. Fairfax, Virginia 22030.

H. Phone: (703) 272-7787.

I. Fax: (703) 272-7786.

J. Website: www.rei1.com

K. Issued: May 31, 2024.

L. Copyright 2024 Restoration Engineering, Inc. All rights reserved.

END OF DOCUMENT 000101

003143 - PERMIT APPLICATION Page 1 of 1

DOCUMENT 003143 - PERMIT APPLICATION

1.1 PERMIT APPLICATION INFORMATION

A. This Document with its referenced attachments is part of the Procurement and Contracting Requirements for Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of the Bidders' own investigations. This Document and its attachments are not part of the Contract Documents.

B. Building Permit Application: Complete building permit application and file with authorities having jurisdiction within five days of the Notice to Proceed.

C. Right of Way Permit Application: Complete Right-of-Way permit application and file with authorities having jurisdiction within five days of the Notice to Proceed.

END OF DOCUMENT 003143

004321 - ALLOWANCE FORM Page 1 of 1

DOCUMENT 004321 - ALLOWANCE FORM

1.1 BID INFORMATION

A. Bidder: ____________________________________________________.

B. Project Name: Structural Repairs, Renwick Courthouse Bell Tower.

C. Project Location: 815 Princess Anne Street, Fredericksburg, Virginia

D. Owner: City of Fredericksburg (COF).

E. Engineer: Restoration Engineering, Inc.

F. Engineer Project Number: 800.094.

1.2 BID FORM SUPPLEMENT

A. This form is required to be attached to the Bid Form.

B. The undersigned Bidder certifies that Base Bid submission to which this Bid Supplement is attached includes those allowances described in the Contract Documents and scheduled in §012100 "Allowances."

1.3 SUBMISSION OF BID SUPPLEMENT

A. Respectfully submitted this ____ day of ____________, 2024.

B. Submitted By:_______________________________(Insert name of bidding firm or corporation).

C. Authorized Signature:_______________________________________(Handwritten signature).

D. Signed By:______________________________________________(Type or print name).

E. Title:___________________________________(Owner/Partner/President/Vice President).

END OF DOCUMENT 004321

004322 - UNIT PRICES FORM Page 1 of 4

DOCUMENT 004322 - UNIT PRICES FORM

1.1 BID INFORMATION

A. Bidder: .

B. Project Name: Structural Repairs, Renwick Courthouse Bell Tower.

C. Project Location: 815 Princess Anne Street, Fredericksburg, Virginia.

D. Owner: City of Fredericksburg (COF).

E. Engineer: Restoration Engineering, Inc.

F. Engineer Project Number: 800.094.

1.2 BID FORM SUPPLEMENT

A. This form is required to be attached to the Bid Form.

B. The undersigned Bidder proposes the amounts below be added to or deducted from the Contract Sum on performance and measurement of the individual items of Work and for adjustment of the quantity given in the Unit-Price Allowance for the actual measurement of individual items of the Work.

C. If the unit price does not affect the Work of this Contract, the Bidder shall indicate "NOT

APPLICABLE."

1.3 UNIT PRICES FOR MISCELLANEOUS REPAIRS

A. Unit Price No. 1: Workcode G1MR - General Maintenance & Repair.

1. See §024119 “Selective Demolition”, Para 3.1.

2. _______________________________________ Dollars ($_____________) per Unit.

1.4 UNIT PRICES FOR REPOINTING BRICK MASONRY

A. Unit Price No. 2: Workcode R1MS – Repoint Brick Masonry.

1. See §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.3.

2. ______________________________________ Dollars ($_____________) per Unit.

004322 - UNIT PRICES FORM Page 2 of 4

1.5 UNIT PRICES FOR REPOINTING ARCHITECTURAL STONE MASONRY

A. Unit Price No. 3: Workcode R2MS – Repoint Stone Masonry.

1. See §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.3.

2. ______________________________________ Dollars ($_____________) per Unit.

1.6 UNIT PRICES FOR RESETTING DISPLACED BRICK MASONRY UNIT

A. Unit Price No. 4: Workcode R4MS – Reset Displaced Brick Masonry Unit.

1. See §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.4.

2. ______________________________________ Dollars ($_____________) per Unit.

1.7 UNIT PRICES FOR FOR RESETTING EXISTING ARCHITECTURAL STONE UNIT

A. Unit Price No. 5: Workcode R5MS – Reset Existing Architectural Stone Unit.

1. See §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.4.

2. ______________________________________ Dollars ($_____________) per Unit.

1.8 UNIT PRICES FOR REPLACE CRACKED/BROKEN/MISSING BRICK MASONRY UNIT

A. Unit Price No. 6: Workcode XIMS – Replace cracked/broken/missing brick masonry unit.

1. See §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.5.

2. ______________________________________ Dollars ($_____________) per Unit.

1.9 UNIT PRICES FOR PATCH CRACKED/SPALLED BRICK MASONRY UNIT WITH HISTORIC MORTAR

A. Unit Price No. 7: Workcode X2MS – Patch Cracked/Spalled Brick Masonry Unit with Historic Mortar.

1. See §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.6.

2. ______________________________________ Dollars ($_____________) per Unit.

1.10 UNIT PRICES FOR PATCH CRACKED/SPALLED ARCHITECTURAL STONE WITH HISTORIC MORTAR

A. Unit Price No. 8: Workcode X3MS – Patch Cracked/Spalled Architectural Stone with Historic Mortar.

1. See §04120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.6.

004322 - UNIT PRICES FORM Page 3 of 4

2. ______________________________________ Dollars ($_____________) per Unit.

1.11 UNIT PRICES FOR REPLACING CRACKED/BROKEN/SPALLED/MISSING PARGING

A. Unit Price No. 9: Workcode X5MS - Replace Cracked/Broken/Spalled/Missing Parging.

1. See §04120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.7.

2. ______________________________________ Dollars ($_____________) per Unit.

1.12 UNIT PRICES FOR PATCHING COPPER ROOFING

A. Unit Price No. 10: Workcode R1RF: Patch Copper Roofing.

1. See §050170.61 “Metal Roof Repair”, Paragraph 3.2.

2. ______________________________________ Dollars ($_____________) per Unit.

1.13 UNIT PRICES FOR REPAIRING DETERIORATED WOOD WITH EPOXY PATCH MATERIAL

A. Unit Price No. 11: Workcode R1WD: Repair Deteriorated Wood with Epoxy Patch Material.

1. See §080152.61 “Wood Window Repairs”, Paragraph 3.3.

2. ______________________________________ Dollars ($_____________) per Unit.

1.14 UNIT PRICES FOR REPLACING MISSING/DAMAGED WOOD ARCHITECTURAL ELEMENT

A. Unit Price No. 12: Workcode R2WD: Replace Missing/Damaged Wood Architectural Element.

1. See §080152.61 “Wood Window Repairs”, Paragraph 3.3.

2. ______________________________________ Dollars ($_____________) per Unit.

1.15 UNIT PRICES FOR PATCHING STUCCO

A. Unit Price No. 13: Workcode R1ST: Patch Stucco.

1. See §092400 "Cement Plaster Repair", Paragraph 3.4.

2. ______________________________________ Dollars ($_____________) per Unit.

1.16 UNIT PRICES FOR REPAIRING CRACK IN STUCCO

A. Unit Price No. 14: Workcode R4ST: Repair Crack in Stucco

004322 - UNIT PRICES FORM Page 4 of 4

1. See §092400 "Cement Plaster Repair", Paragraph 3.4.

2. ______________________________________ Dollars ($_____________) per Unit.

1.17 UNIT PRICES FOR INSTALLING CONTROL JOINT IN STUCCO VENEER

A. Unit Price No. 15: Workcode X1ST: Install Control Joint in Stucco Veneer

1. See §092400 "Cement Plaster Repair", Paragraph 3.4.

2. ______________________________________ Dollars ($_____________) per Unit.

1.18 SUBMISSION OF BID SUPPLEMENT

A. Respectfully submitted this ____ day of ____________, 2024.

B. Submitted By:___________________________________(Insert name of bidding firm or corporation).

C. Authorized Signature:___________________________________(Handwritten signature).

D. Signed By:______________________________________________(Type or print name).

E. Title:___________________________________(Owner/Partner/President/Vice President).

END OF DOCUMENT 004322

004373 - PROPOSED SCHEDULE OF VALUES FORM Page 1 of 1

DOCUMENT 004373 - PROPOSED SCHEDULE OF VALUES FORM

1.1 BID FORM SUPPLEMENT

A. A completed Proposed Schedule of Values form is required to be attached to the Bid Form.

1.2 PROPOSED SCHEDULE OF VALUES FORM

A. Proposed Schedule of Values Form: Provide a breakdown of the bid amount, in enough detail to facilitate continued evaluation of bid. Coordinate with the Project Manual table of contents. Provide multiple line items for principal material and subcontract amounts in excess of three (3) percent of the Contract Sum.

B. Arrange schedule of values using AIA Document G703-1992.

1. Copies of AIA standard forms may be obtained from the American Institute of Architects;

https://www.aiacontracts.org/ library; (800) 942-7732.

END OF DOCUMENT 004373

https://www.aiacontracts.org/%20library

011000 – SUMMARY Page 1 of 7

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work under separate contracts.

4. Access to site.

5. Coordination with occupants.

6. Work restrictions.

7. Specification and Drawing conventions.

8. Miscellaneous provisions.

B. Related Requirements:

1. §015000 "Temporary Facilities and Controls".

1.3 PROJECT INFORMATION

A. Project Identification: Structural Repairs at the Renwick Courthouse Bell Tower.

1. Project Location: 815 Princess Anne Street, Fredericksburg, Virginia 22401.

B. Owner: City of Fredericksburg.

1. Owner's Representative: Referred to as COF Representative throughout this document.

C. Engineer: Restoration Engineering, Inc., 10503 West Drive, Suite A, Fairfax, VA 22030.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. General:

011000 – SUMMARY Page 2 of 7

a. The information presented below represents an abbreviated schedule of work to be performed as part of the base bid and does not necessarily reflect the full extent of work. Contractor must thoroughly review all drawings and specifications to understand full extent of requirements.

b. Much of the work to be performed will be reimbursed on a unit price basis, based on unit pricing provided by the contractor with the bid. Estimated quantities for all unit price repairs are detailed in the "allowances". The quantity of repairs delineated in "allowances" shall be included in the base bid. The contractor will be reimbursed for all unit price repairs based on the actual quantity of work completed. Final quantities will differ from actual quantities at the conclusion of the project. As such, discrepancies between actual quantities and estimated quantities will be reconciled via change order at the end of the project. In the course of the work, in instances where the contractor anticipates that a specific unit price repair quantity will exceed the estimated quantity by more than 20 percent, the contractor should notify the engineer and obtain written approval prior to proceeding with repairs.

c. Repairs are intended to be performed in general accordance with the United States Department of Interior - National Park Service’s “Guidelines for Preserving, Rehabilitating, Restoring & Reconstructing Historic Buildings"

1) Preservation: where possible, the intent is to preserve existing structural and architectural elements in their existing condition.

2) Rehabilitation: there is no intent to modify the bell tower for a new use (i.e. public access) and, as such, none of the specified repairs are intended to be construed as rehabilitation of the structure.

3) Restoration: Restoration of original structural elements is confined to replacement, in kind, of some of the existing wood decking. Restoration of original architectural elements is limited to refinishing and repair of the windows, louvers and cornice moldings.

4) Reconstruction: Reconstruction of deteriorated/missing structural or architectural elements is not anticipated.

2. Structural Wood Framing Repairs:

a. See "Keyed Structural Notes" on Contract Drawings for specific information regarding typical structural repairs at existing wood framing members.

b. Contractor will be required to install shoring to perform various repairs; contractor to engage qualified Professional Engineer to provide shoring shop drawings.

c. Wood structural repairs involving replacement of existing members or installation of supplemental reinforcing, to utilize rough sawn timber of approved species. Contractor to submit preferred wood species, for verification, based on readily available timber, basis of design is white oak, no. 2 or better.

d. Fasteners securing new wood structural members shall be stainless steel or other, approved non-corrosive materials. Fasteners should be countersunk and covered with approved wood putty or plugs to limit exposure.

e. Fastener holes should be pre-drilled when located at or near edges/ends of members.

3. Roofing/Flashing Repairs:

a. See "Keyed Roofing Notes" on Contract Drawings and Unit Price Schedule for specific roofing/flashing repair information at designated locations.

011000 – SUMMARY Page 3 of 7

b. Carefully document existing conditions and then clean existing copper cupola roofing to remove existing bird feces and other materials. Do not use overly aggressive chemicals or high pressure spray.

c. Fabricate and install new stepped, copper receivers and counterflashing at bell tower walls and referenced chimneys, above main roof, as shown on referenced details (see stucco notes).

4. Stucco/Sealant Repairs:

a. See "Keyed Stucco Notes" on Contract Drawings and Unit Price Schedule for specific stucco repair information at designated locations.

b. Carefully sawcut and remove existing stucco as required to install new stepped, copper receivers and counterflashing (see 3.3 above); patch stucco following flashing installation as shown on Contract Drawings.

c. Remove and replace existing sealant/backer rod at perimeter of all tower openings including windows and louvers.

5. Window/Louver Repairs:

a. See "Keyed Window/Louver Notes" on Contract Drawings and Unit Price Schedule for specific window/louver repair information at designated locations.

b. Contractor to carefully restore original wood framed windows including removal and reinstallation of sashes, replacement of putty glazing, cleaning/stripping/scraping and painting.

c. Contractor to carefully restore original wood framed louvers including cleaning/stripping/scraping and painting.

d. Contractor to carefully restore original wood framed cornice including cleaning/stripping/scraping and painting.

e. Contractor to repair deteriorated/missing window, louver and cornice elements in conjunction with general restoration work.

6. Brick Masonry Repairs:

a. See "Keyed Masonry Notes" on Contract Drawings and Unit Price Schedule for specific masonry repair information at designated locations.

b. Contractor to perform extensive repointing on interior of bell tower. See Contract

Drawings for repointing guidelines and specifications.

c. Masonry repair materials must be historically accurate and compatible with existing materials. Contractor to submit samples for testing and analysis to determine optimum repair materials.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.5 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

011000 – SUMMARY Page 4 of 7

B. Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Although the building is currently unoccupied, Contractor to limit use of Project site to work in areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the work is indicated or designated staging areas.

2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

c. Owner will provide interior space for contractor staging and storage provided the

Contractor maintains the interior staging area in a clean condition throughout construction.

3. Parking and Drive Lane: It is assumed that the Contractor will need to obtain a partial Right-of- Way closure permit, from the City of Fredericksburg, to accommodate delivery and operation of a manlift throughout construction operations. The Contractor must meet all permit requirements and maintain temporary protections and traffic control devices throughout construction.

4. Interior restroom facilities will be available to the Contractor provided the Contractor maintains the restrooms in a clean condition during construction operations.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.6 COORDINATION WITH OCCUPANTS

A. Partial Owner Occupancy: The Owner (or other Contractors) may temporarily occupy some areas on the premises during entire construction period, despite the fact that the building is currently unoccupied. Coordinate with Engineer and COF Representative regarding facility operations, throughout construction. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from COF Representative and authorities having jurisdiction.

2. Provide not less than 72 hours' notice to COF Representative of activities that will affect Owner's operations.

B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion

011000 – SUMMARY Page 5 of 7 of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work to between 7:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by COF and authorities having jurisdiction.

1. Weekend Hours: Weekend work must be scheduled with and agreed upon by COF Representative three (3) days prior to commencement of work. COF Representative must be provided with notification of work occurring during weekend hours.

2. Early Morning Hours: Comply with City of Fredericksburg noise ordinance.

3. Hours for “Noisy” Demolition Work: Noisy" work shall be performed in accordance with applicable noise ordinances and should generally be limited to between 7:00 a.m. and 6:00 p.m.

4. The Contractor shall submit and obtain the COF Representative’s approval of the proposed work schedule prior to starting work. Notify the Owner immediately of deviations in the work schedule.

C. On-Site Workday Restrictions: Do not perform work resulting in noisy activity on-site during work black-out days indicated below:

1. Memorial Day

2. 4th of July

3. Labor Day

4. Thanksgiving Weekend

5. Christmas Eve and Christmas Day

6. New Year’s Day

D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by COF or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify COF Representative not less than two (2) days in advance of proposed utility interruptions. All interruptions are limited to a maximum of 24 hours.

2. Obtain COF Representative’s written permission before proceeding with utility interruptions.

E. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with COF Representative.

011000 – SUMMARY Page 6 of 7

1. Notify COF Representative not less than two (2) days in advance of proposed disruptive operations.

F. Restricted Substances: Use of tobacco products and other controlled substances within the existing building or on Project site is NOT permitted.

G. Employee Identification: Provide identification tags or uniforms for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

H. Employee Screening: Comply with COF Representative’s requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with COF Representative.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

1.9 QUALITY ASSURANCE

A. Observation Reports will NOT include items from previous reports. Consequently, the Contractor must submit documentation acknowledging that they have reviewed Engineer's reports and addressed the referenced items accordingly. Previous Observation Reports will be reviewed at progress meetings to clarify Contractor requirements.

011000 – SUMMARY Page 7 of 7

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

012100 - ALLOWANCES Page 1 of 5

SECTION 012100 - ALLOWANCES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

B. Types of allowances include the following:

1. Unit-cost allowances.

C. Related Requirements:

1. §012200 "Unit Prices".

2. §024119 “Selective Demolition”.

3. §04120.6 “Brick Masonry Repair and Repointing”.

4. §050170.61 “Metal Roof Repair”.

5. §80152.61 “Wood Window Repairs”.

6. §092400 “Cement Plaster Repair”.

1.3 DEFINITIONS

A. Allowance is a quantity of work or dollar amount established in lieu of additional requirements, to be included in the “Base Bid” used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.

1.4 INFORMATIONAL SUBMITTALS

A. Submit shop drawings and other documentation as required to show location of unit price repairs included in the allowance.

1.5 ALLOWANCES

A. Allowance shall include cost to Contractor of specific products and materials ordered by COF Representative or selected by Engineer under allowance and shall include taxes, freight, and delivery to Project site.

012100 - ALLOWANCES Page 2 of 5

B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by COF Representative or selected by Engineer under allowance shall be included as part of the Contract Sum and not part of the allowance.

1.6 ADJUSTMENT OF ALLOWANCES

A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.

1. Include installation costs in purchase amount only where indicated as part of the allowance.

2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.

3. Submit substantiation of a change in Scope of Work, if any, claimed in Change Orders related to unit-cost allowances.

B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.

1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.

2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

012100 - ALLOWANCES Page 3 of 5

3.3 SCHEDULE OF ALLOWANCES FOR GENERAL MAINTENANCE AND REPAIR

A. Allowance No. 1: Quantity Allowance: Include 50 manhours of Workcode G1MR “Miscellaneous General Maintenance & Repair” as specified in §024119 "Selective Demolition", Paragraph 3.1.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.4 SCHEDULE OF ALLOWANCES FOR REPOINTING BRICK MASONRY

A. Allowance No. 2: Quantity Allowance: Include 1000 square feet of Workcode R1MS “Repointing Brick Masonry” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.3.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.5 SCHEDULE OF ALLOWANCES FOR REPOINTING ARCHITECTURAL STONE MASONRY

A. Allowance No. 3: Quantity Allowance: Include 500 lineal feet of Workcode R2MS “Repointing Architectural Stone Masonry” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.3.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.6 SCHEDULE OF ALLOWANCES FOR RESETTING DISPLACED BRICK MASONRY UNIT

A. Allowance No. 4: Quantity Allowance: Include 20 each (brick) of Workcode R4MS “Reset Displaced Brick Masonry Unit” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.4.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.7 SCHEDULE OF ALLOWANCES FOR RESETTING DISPLACED ARCHITECTURAL STONE UNIT

A. Allowance No. 5: Quantity Allowance: Include 5 each (stone) of Workcode R5MS “Reset Displaced Architectural Stone Unit” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.4.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

012100 - ALLOWANCES Page 4 of 5

3.8 SCHEDULE OF ALLOWANCES FOR REPLACING CRACKED/BROKEN/MISSING BRICK MASONRY

UNIT

A. Allowance No. 6: Quantity Allowance: Include 10 each (brick) of Workcode X1MS “Replace Cracked/Broken/Missing Brick Masonry Unit” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.5.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.9 SCHEDULE OF ALLOWANCES FOR PATCHING CRACKED/SPALLED BRICK MASONRY UNIT WITH

HISTORIC MORTAR

A. Allowance No. 7: Quantity Allowance: Include 100 each (brick) of Workcode X2MS “Patch Cracked/Spalled Brick Masonry Unit with Historic Mortar” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.6.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.10 SCHEDULE OF ALLOWANCES FOR PATCHING CRACKED/SPALLED ARCHITECTURAL STONE WITH

HISTORIC MORTAR

A. Allowance No. 8: Quantity Allowance: Include 15 each (location) of Workcode X3MS “Patch Cracked/Spalled Architectural Stone with Historic Mortar” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.6.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.11 SCHEDULE OF ALLOWANCES FOR REPLACING CRACKED/BROKEN/SPALLED/MISSING PARGING

A. Allowance No. 9: Quantity Allowance: Include 500 lineal feet of Workcode X5MS “Replace Cracked/Broken/Spalled/Missing Parging” as specified in §040120.6 “Brick Masonry Repair & Repointing”, Paragraph 3.7.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.12 SCHEDULE OF ALLOWANCES FOR PATCHING COPPER ROOFING

A. Allowance No. 10: Quantity Allowance: Include 20 each (location) of Workcode R1RF “Patch Copper Roofing” as specified in §050170.61 “Metal Roof Repair”, Paragraph 3.2.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit

012100 - ALLOWANCES Page 5 of 5

3.13 SCHEDULE OF ALLOWANCES FOR REPAIRING DETERIORATED WOOD WITH EPOXY PATCH

MATERIAL

A. Allowance No. 11: Quantity Allowance: Include 50 cubic inches of Workcode R1WD “Repair Deteriorated Wood with Epoxy Patch” as specified in §080152.61 “Wood Window Repairs”, Paragraph 3.3.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.14 SCHEDULE OF ALLOWANCES FOR REPLACING MISSING/DAMAGED WOOD ARCHITECTURAL

ELEMENT

A. Allowance No. 12: Quantity Allowance: Include 100 manhours of Workcode R2WD “Replace Missing/Damaged Wood Architectural Element” as specified in §080152.61 “Wood Window Repairs”, Paragraph 3.4.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.15 SCHEDULE OF ALLOWANCES FOR PATCHING STUCCO

A. Allowance No. 13: Quantity Allowance: Include 100 square feet of Workcode R1ST “Patch Stucco” as specified in §092400 “Cement Plaster Repair”, Paragraph 3.4.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.16 SCHEDULE OF ALLOWANCES FOR REPAIRING CRACK IN STUCCO

A. Allowance No. 14: Quantity Allowance: Include 200 lineal feet of Workcode R4ST “Repair Crack in Stucco” as specified in §092400 “Cement Plaster Repair”, Paragraph 3.5.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit Prices."

3.17 SCHEDULE OF ALLOWANCES FOR INSTALLING CONTROL JOINT IN STUCCO VENEER

A. Allowance No. 15: Quantity Allowance: Include 20 lineal feet of Workcode X1ST “Install Control Joint in Stucco Veneer” as specified in §092400 “Cement Plaster Repair”, Paragraph 3.6.

1. Coordinate quantity allowance adjustment with unit-price requirements in §012200 "Unit

END OF SECTION 012100

012200 - UNIT PRICES Page 1 of 5

SECTION 012200 - UNIT PRICES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

B. Related Requirements:

1. §012100 "Allowances".

2. §024119 “Selective Demolition”.

3. §040120.6 “Brick Masonry Repair and Repointing”.

4. §050170.61 “Metal Roof Repair”.

5. §80152.61 “Wood Window Repairs”.

6. §092400 “Cement Plaster Repair”.

C. Retain subparagraph below only if unit prices may be employed as a result of special testing and inspecting procedures required by local codes and specified in Division 01.

1.3 DEFINITIONS

A. Unit price is an amount, incorporated into the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1. At each location where unit price repairs are performed, record the location and type of each repair to be performed on a roof plan and spreadsheet. Submit unit price documentation with each invoice and provide both the Owner and Engineer with a copy. Engineer will review the submitted quantities and the approved quantities shall be used for Contractor payment.

1.4 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

012200 - UNIT PRICES Page 2 of 5

B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF UNIT PRICES FOR GENERAL MAINTENANCE AND REPAIRS

A. Unit Price No. 1: Workcode G1MR – General Maintenance & Repair.

1. Description: Perform miscellaneous maintenance and repair work according to §024119 "Selective Demolition", Paragraph 3.1.

2. Unit of Measurement: Per Manhour.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.2 SCHEDULE OF UNIT PRICES FOR REPOINTING BRICK MASONRY

A. Unit Price No. 2: Workcode RIMS – Repoint Brick Masonry.

1. Description: At locations where existing brick masonry mortar is deteriorated, repoint existing brick masonry wall using approved, lime based and historically matched mortar in accordance with §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.3.

2. Unit of Measurement: Square Foot.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.3 SCHEDULE OF UNIT PRICES FOR REPOINTING ARCHITECTURAL STONE MASONRY

A. Unit Price No. 3: Workcode R2MS – Repoint Stone Masonry.

1. Description: At locations where mortar in existing stone masonry is deteriorated, repoint existing architectural stone masonry elements using approved, lime based and historically matched mortar in accordance with §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.3.

2. Unit of Measurement: Lineal Foot.

012200 - UNIT PRICES Page 3 of 5

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100 "Allowances."

3.4 SCHEDULE OF UNIT PRICES FOR RESETTING DISPLACED BRICK MASONRY UNIT

A. Unit Price No. 4: Workcode R4MS – Reset Displaced Brick Masonry Unit.

1. Description: At locations where existing brick masonry unit is displaced, reset existing displaced brick in accordance with §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.4.

2. Unit of Measurement: Each (Brick).

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.5 SCHEDULE OF UNIT PRICES FOR RESETTING EXISTING ARCHITECTURAL STONE UNIT

A. Unit Price No. 5: Workcode R5MS – Reset Existing Architectural Stone Unit.

1. Description: At locations where existing architectural stone unit is displaced, reset existing displaced architectural stone in accordance with §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.4.

2. Unit of Measurement: Each (Stone).

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.6 SCHEDULE OF UNIT PRICES FOR REPLACE CRACKED/BROKEN/MISSING BRICK MASONRY UNIT

A. Unit Price No. 6: Workcode XIMS – Replace cracked/broken/missing brick masonry unit.

1. Description: At locations where existing brick is deteriorated and cannot be repaired, replace existing cracked/broken/missing brick masonry unit in accordance with §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.5.

2. Unit of Measurement: Each (Brick).

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.7 SCHEDULE OF UNIT PRICES FOR PATCH CRACKED/SPALLED BRICK MASONRY UNIT WITH

HISTORIC MORTAR

A. Unit Price No. 7: Workcode X2MS – Patch Cracked/Spalled Brick Masonry Unit with Historic Mortar.

1. Description: At locations where existing brick is cracked/spalled but can be repaired, patch existing broken brick using historically matched repair mortar in accordance with §040120.6 "Brick Masonry Repair and Repointing", Paragraph 3.6.

2. Unit of Measurement: Each (Brick)

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

012200 - UNIT PRICES Page 4 of 5

3.8 SCHEDULE OF UNIT PRICES FOR PATCH CRACKED/SPALLED ARCHITECTURAL STONE WITH

HISTORIC MORTAR

A. Unit Price No. 8: Workcode X3MS – Patch Cracked/Spalled Architectural Stone with Historic Mortar.

1. Description: At locations where existing stone is cracked/spalled but can be repaired, patch existing broken brick usint historically matched repair mortar in accordance with §040120.6 "Brick Masonry Repair and Repoint", Paragraph 3.6.

2. Unit of Measurement: Each (Location)

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.9 SCHEDULE OF UNIT PRICES FOR REPLACING CRACKED/BROKEN/SPALLED/MISSING PARGING

A. Unit Price No. 9: Workcode X5MS – Replace Cracked/Broken/Spalled/Missing Parging.

1. Description: Replace existing cracked/broken/spalled/missing lime mortar parging using historically matched lime repair mortar in accordance with §040120.6 “Brick Masonry Repair & Repointing” Paragraph 3.7.

2. Unit of Measurement: Lineal Foot.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.10 SCHEDULE OF UNIT PRICES FOR PATCHING COPPER ROOFING

A. Unit Price No. 10: Workcode R1RF – Patch Copper Roofing.

1. Description: Remove existing deteriorated solder patch and install new copper patch at locations designated by Engineer and in accordance with §050170.61 “Metal Roof Repair”, Paragraph 3.2.

2. Unit of Measurement: Each (Location).

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.11 SCHEDULE OF UNIT PRICES FOR REPAIRING DETERIORATED WOOD WITH EPOXY PATCH

MATERIAL

A. Unit Price No. 11: Workcode R1WD – Repair Deteriorated Wood with Epoxy Patch Material.

1. Description: At locations where the wood at window/louver is deteriorated, apply consolidant and epoxy patch material in accordance with Manufacturer’s instructions, approved mock-up and §080152.61 “Wood Window Repairs”, Paragraph 3.3.

2. Unit of Measurement: Cubic Inch.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.12 SCHEDULE OF UNIT PRICES FOR REPLACING MISSING/DAMAGED WOOD ARCHITECTURAL

ELEMENT

A. Unit Price No. 12: Workcode R2WD – Replace Missing/Damaged Wood Architectural Element.

012200 - UNIT PRICES Page 5 of 5

1. Description: At locations where the wood framed window is deteriorated beyond repair, replace deteriorated/missing wood frame/trim/sash componenet at window/louver. Mill wood to match profile of existing and secure with stainless steel hardware in accordance with §080152.61 “Wood Window Repair”, Paragraph 3.4.

2. Unit of Measurement: Per Manhour.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in

§012100 "Allowances."

3.13 SCHEDULE OF UNIT PRICES FOR PATCHING STUCCO

A. Unit Price No. 13: Workcode R1ST – Patch Stucco.

1. Description: In areas where existing stucco is deteriorated, remove loose/delaminated stucco from substrate, prep substrates and surrounding stucco and install stucco patch in accordance with §092400 "Cement Plaster Repair", Paragraph 3.4.

2. Unit of Measurement: Square Foot.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.14 SCHEDULE OF UNIT PRICES FOR REPAIRING CRACK IN STUCCO

A. Unit Price No. 14: Workcode R4ST – Repair Crack in Stucco

1. Description: At locations approved by Engineer prior to repair, repair crack in existing stucco in accordance with approved mock up and §092400 "Cement Plaster Repair", Paragraph 3.5.

2. Unit of Measurement: Lineal Foot.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

"Allowances."

3.15 SCHEDULE OF UNIT PRICES FOR INSTALLING CONTROL JOINT IN STUCCO VENEER

A. Unit Price No. 15: Workcode X1ST – Install Control Joint in Stucco Veneer

1. Description: Install new control joint in stucco veneer in accordance with approved mock up;

carefully saw cut veneer to accommodate installation of new backer rod and sealant, apply approved aggregate in fresh sealant to mimic stucco texture in accordance with §092400 "Cement Plaster Repair", Paragraph 3.6.

2. Unit of Measurement: Lineal Foot.

3. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in §012100

END OF SECTION 012200

012500 - SUBSTITUTION PROCEDURES Page 1 of 4

SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. §012100 "Allowances".

2. §012200 “Unit Prices”.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or COF Representative that are not required in order to meet other Project requirements but may offer advantage to Contractor or COF Representative.

1.4 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.

b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

012500 - SUBSTITUTION PROCEDURES Page 2 of 4

c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of Engineers and Owners.

h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from

ICC-ES or other relevant agency.

j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the

Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

2. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within seven (7) days of receipt of a request for substitution. Engineer will notify Contractor of acceptance or rejection of proposed substitution within fifteen (15) days of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Engineer's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Engineer does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

012500 - SUBSTITUTION PROCEDURES Page 3 of 4

1.6 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

1.7 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than fifteen (15) days prior to time required for preparation and review of related submittals.

1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested…