This document is Addendum No. 4 to an Invitation for Bids (IFB) issued by the City of Fredericksburg, Virginia for the Renwick Bell Tower Repairs project, IFB #25-0501. The addendum addresses various questions and clarifications regarding the project scope, including the type of stucco material, the sealant peel test requirements, the scope for window and louver repairs, the measurement of parging replacement, and the project timeline. The City has also agreed to allow the contractor to complete submittals in the fall before starting construction in spring 2025, and will work with the contractor to mitigate the need for heating the tower during cold weather construction. Additionally, the City has provided a link to access extensive photographs of the tower.

The project must be completed within 120 days of the notice to proceed, which the City plans to issue within 60 days of the bid due date of September 5, 2024. The City has revised two specification sections related to the project and provided the updated documents with this addendum. No other details regarding pricing, set asides, incumbents, funding, or other salient information are provided in this addendum.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Fredericksburg Telephone: 540.372.1017 P.O. Box 7447 Fax: 540.372.12.15 Fredericksburg, VA 22404-7447

August 20, 2024

ADDENDUM NO.4 TO ALL OFFERORS:

Reference –IFB # 25-0501

Commodity: Renwick Bell Tower Repairs DUE DATE: September 5th, 2024 – 2:00 P.M. EST

The following is a general summary of questions that have been submitted by various vendors, edited for clarity, along with the City’s responses.

1. The keyed Stucco notes on the drawings refer to the repair stucco as lime-based, while the specifications refer to the stucco as cement-based. Please clarify what the material should be.

A. The stucco is cement/lime-based. Please refer to the REVISED Specifications for clarifications.

2. Keyed Window/Louver/Trim note 5 notes that there is to be a peel test on installed sealant. However, there is no further direction or parameters given in the specifications. Please clarify the intent and parameters of the peel test.

A. Perform adhesion on-site test in accordance with ASTM C1521-13 “Standard

Practice for Evaluating Adhesion of Installed Weather proofing Sealant Joints” using the “Tail” procedure, as follows:

a. Method 1: Mark the cut portion of the sealant 1 inch from the adhesive bond. Grasp the sealant “tail” at the mark 1 in from the adhesive bond. Pull the tail at an angle of 90 degrees to the substrate to effectively elongate the 1 inch mark to two times the stated movement capability of the sealant. Record the type of failure that occurs and the distance of the mark from the adhesive bond when failure occurred, or the distance recommended by the manufacturer without causing failure.

B. Perfomr tests at locations selected by Engineer.

C. Conduct field tests for each kind of sealant and joint substrate.

D. Notify Engineer seven days in advance of dates and times when test joints will be erected.

E. Arrange for test to take place with joint-sealant manufacturer’s technical representative.

3. On Drawing 1/S1.1, Window Key Note 7 is pointing to the sill of Window 2E. However, this note is concerned with the wood cornice repairs. Please advise if this note is in the incorrect location, and if so, what the scope intent is.

A. Window Key Note 7 pointing at the sill of Window 2E should be disregarded.

Window Key Note 10 covers sill work.

4. On Drawing 1/S-1.2, the note for the Louver 4N is cut off. Please clarify what the scope intent is.

A. The note for Louver 4N on Drawing 1/S-1.2 should read:

“Louver is dislocated along this side; reset and secure in place”.

5. Workcode X5MS notes that the replacement of parging is in LF amount. Please advise if it should instead be a SF amount.

A. Yes, X5MS should be in SF.

6. In the project documents, it is noted that the project is to be completed within 120 days of the notice to proceed. Please clarify when the notice to proceed will be issued.

A. The City of Fredericksburg will issue the notice to proceed within 60 days of the bid due date.

7. In the project documents, it is noted that the project is to be completed within 120 days of the notice to proceed. Please clarify when the notice to proceed will be issued.

o The intent of this question is to determine whether this project is slated to take place during the fall and into the winter. If that is the case, then the cold temperatures will necessitate tenting and heating the tower, which will have cost implications that need to be included in the base bid.

A. The City of Fredericksburg will work with the contractor to mitigate any need to heat the tower. See the below answer at #8.

8. Please Would the city be amenable to using the fall season to complete submittals and other project startup paperwork before beginning construction in Spring 2025? This would be a more efficient construction schedule than one that necessitated completing submittals during the 120-day construction duration.

A. The City of Fredericksburg is amenable to having the submittals completed in the fall and work starting in the spring. Once work commences, it must be completed in

120-days.

9. The engineer onsite during the pre-bid walkthrough mentioned that there are extensive photographs of the tower that he was willing to share. Can those photos be shared to the bidders?

A. The pictures have been shared via dropbox and the link is:

https://www.dropbox.com/scl/fo/bgrlipm4c266eqrlkvdkj/ACVolfoaCE2pVQjogrhCRP4?rl key=3h2ncfe9kku2mo34jt32fn0dv&st=2kepxd5m&dl=0

B. The following Specification Sections have been revised and included with this addendum:

A. Specification Section 040120.6 “Brick Masonry Repair & Repointing” dated August

20, 2024.

B. Specification Section 092400 “Cement Plastering” dated August 20, 2024.

https://www.dropbox.com/scl/fo/bgrlipm4c266eqrlkvdkj/ACVolfoaCE2pVQjogrhCRP4?rlkey=3h2ncfe9kku2mo34jt32fn0dv&st=2kepxd5m&dl=0 https://www.dropbox.com/scl/fo/bgrlipm4c266eqrlkvdkj/ACVolfoaCE2pVQjogrhCRP4?rlkey=3h2ncfe9kku2mo34jt32fn0dv&st=2kepxd5m&dl=0