About this file

This is Addendum No. 1 to a Request for Proposal issued by the Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division for professional services related to the Hartwick Pines State Park Visitors Center Exhibit Space project (File Number 171/22325.HJD). The addendum, dated November 7, 2025, provides clarifications and modifications to the original RFP. The proposal due date has been extended to November 20, 2025, with a questions due date of November 12, 2025. The addendum includes original building construction drawings dated August 16, 1991, encompassing site plans, site utility plans, architectural, structural, mechanical, and electrical drawings that proposers must field verify. A pre-proposal meeting was conducted with an attendee sign-in sheet included as an attachment. The project will be awarded to a General Contractor using DTMB's typical bid process, with no Construction Manager assigned to this project.

The proposing professional services consultant (PSC) must provide a comprehensive breakdown of personnel hours and billing rates for the entire project team, including all subconsultants, using specified forms (III-2-A, III-2-B, and III-2-C). Item II-5 Budget Analysis must be excluded from proposals. The PSC must include exhibits in demolition bid documents, with exhibits to be salvaged by the contractor and turned over to the Department of Natural Resources. The project is funded with recently available non-ARPA funds and was separated from concurrent visitor center renovation work to avoid conflicts with ARPA-funded project deadlines set for December 2026. The project director is Heather DeKorte, RA.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 2/22) HJD_2025-1106

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 1

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.

Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO: ALL PROPOSERS DATE ISSUED: November 7, 2025

PROJECT NAME:

Hartwick Pines State Park Visitors Center Exhibit Space

FILE NUMBER:

171/22325.HJD

PROJECT DIRECTOR: Heather DeKorte, RA PROPOSAL DUE DATE: November 20, 2025

ADDENDUM ITEMS:

Attachments:

1. See appended sign-in sheet from Pre-Proposal meeting.

2. The following drawings are included with this addendum. PSC must field verify all existing conditions.

a. Visitor Center original building construction drawings dated 8/16/1991. Set includes site plan, site utility plan, architectural, structural, mechanical, and electrical.

Clarifications:

1. DTMB is requesting a break-down of personnel hours and billing rates of the PSC’s entire team, including consultants. Include sub-consultant personnel information on forms III-2-A Position, Classification, and Employee Billing Rate Information and III-2-B Fee with Anticipated Hours and Billing Rate. Include sub-consultant’s total fees per Phase on form III-2-C Authorize Reimbursables.

2. Exclude Item II-5 Budget Analysis from the proposal.

3. PSC must include exhibits in the demolition bid documents. The exhibits will be salvaged by Contractor and turned over to DNR.

4. The proposal due date has been extended to November 20, 2025.

5. Questions due date has been extended to November 12, 2025.

Questions and Answers:

Q1. Referencing Page 8 of the “RFP Billable Rates” document, do billable rate calculation requirements apply to the entire project team including subconsultants, or is this requirement limited to the Prime PSC only?

A1. Billable rate information requirements apply to the entire project team including sub-consultants. See Clarification #2 above.

Q2. Will the construction methodology be General Contractor or Construction Manager? If Construction Manager, what firm would that be?

A2. This project will use the typical DTMB bid process and will be awarded to a General Contractor. There is not a Construction Manager on this project.

Q3. Why isn’t this project being included in the current V.C. renovation scope?

A2. The Hartwick Pines Exhibits project was originally put on hold because the DNR did not have sufficient funds to cover the fabrication/installation of the exhibits and the renovation of the exhibit space. Recently, the funds have become available, but they are not ARPA funds. Since the timing of the new construction on the exhibits doesn’t align with the existing construction project at the Visitor Center and since the funds are not ARPA, it did not make sense to add this work into current ARPA-funded contracts. DNR preferred to issue this work as a separate project to avoid conflicts with the ARPA-funded project deadlines coming in December 2026.

APPROVED BY: PROJECT DIRECTOR, Heather DeKorte, RA DATE 11/6/2025