This is a Questions and Answers addendum document issued by the Connecticut Port Authority for RFP No. CPA0026-NLSP-SPP-SPC, concerning long lead electrical equipment for the New London State Pier Shore Power Project. The procurement encompasses four primary electrical components: one 15kV medium-voltage shore power switchgear, one 2.5MVA dual secondary medium-voltage pad-mounted transformer, one 400V to 600V low-voltage pad-mounted transformer, and one neutral grounding resistor. The RFP scope is limited exclusively to equipment procurement, with installation, commissioning, cable routing and pulling, and all construction activities to be performed under separate contracts by others. The solicitation remained open for vendor questions through April 2, 2026 at 4:00 PM EDT, with proposal submissions due April 24, 2026 at 4:00 PM EDT. Shore Power Operator (SPO) vehicles will be provided under a separate contract and are excluded from this procurement package.
All supplied equipment must be compatible with and support integration into a shore power system designed in accordance with international standard IEC/IEEE/ISO 80005, with specifications addressing voltage ratings, insulation levels, 60 Hz frequency compatibility, protection schemes, grounding methods, and system configuration. Equipment ratings and technical data must support coordination for eventual IEC 80005 compliance at the system level, though the complete shore-to-ship power interface system integration responsibility lies outside this contract scope. No estimated budget or contract value is provided in the RFP documentation; vendors are required to submit their own equipment costs and lead times. Delivery terms are specified as Free On Board Destination with vendor-specified payment terms. The solicitation is open to all vendors without set-asides, restrictions, or disadvantaged enterprise designations, and inquiries may be directed to Jill Dowling-Moreno at 860-577-5174 or info@ctportauthority.com.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
455 Boston Post Road, Suite 204 Old Saybrook, CT 06475 Phone: 860-577-5174
CTPortAuthority.com
RFP No. CPA0026-NLSP-SPP-SPC
Questions & Responses
1. Please list each component and the quantity of each to clarify the long lead electrical items that are part of the RFP scope.
I. Medium-Voltage Shore Power Switchgear 15kV – One (1) Qty II. Medium-Voltage Pad-Mounted Transformer (2.5MVA, Dual Secondary) – One (1) Qty
III. Low-Voltage Pad-Mounted Transformer (400V to 600V) – One (1) Qty IV. Neutral Grounding Resistor – One (1) Qty
2. While Zinus will supply CMS vehicle(s), please clarify if SPOs are part of this RFP scope or not. If so, does that include their installation too?
While CMS vehicle(s) will be provided under a separate contract, the procurement and installation of SPOs are excluded from this package. This package is solely the procurement of identified long lead electrical items.
3. Is installation of the requested shore power system components part of the scope? If not, please explain why not?
Installation of shore power system components is not part of this contract. This RFP is limited to the procurement of equipment only. All construction and installation activities will be performed under separate contract(s) by others.
4. Is cable installation and pulling included in the scope? If so, please clearly identify the routes.
Cable installation, routing, and pulling are not included in this scope..
5. Is commissioning a required part of the scope? If not, please explain why not?
Commissioning is not part of this contract. All installation and commissioning activities will be performed by others under separate contract(s).
6. Please explain in greater details than the RFP how the international standard for shore power – IEC/IEEE/ISO 80005 – is to be followed in this project.
The Project intent is to comply with the applicable provisions of the IEC/IEEE/ISO 80005;
however, the proposal’s scope under this contract is limited to the supply of switchgear, transformers, and neutral grounding equipment, and does not include the complete shore-to-ship power interface system.
Accordingly, equipment supplied must be compatible with and supports integration into a shore power system designed in accordance with IEC/IEEE/ISO 80005.
Specific Requirements Within This Scope
I. Equipment ratings (voltage, insulation level, frequency – 60 Hz) shall be consistent with an IEC 80005-compliant shore power system.
II. Switchgear, transformers, and neutral grounding resistor (NGR) shall be designed to support the operational and protection requirements of a compliant shore power installation.
III. Protection schemes, grounding methods, and system configuration shall be coordinated to enable IEC 80005 compliance at the system level.
IV. They shall provide sufficient technical data, interface requirements, and coordination information to support integration with the overall shore power system.
7. While the RFP provides an estimated timeline, what is the port’s estimated budget for this
RFP?
The vendors submitting bids shall provide equipment costs and lead times.
File details come from the government source that posted it. Updated .