SOW - Canby Station SOW R2.docx
DOCX document 2 MB Posted
- Solicitation number
- AC-25-04111
About this file
This document is a Statement of Work (SOW) for the United States Forest Service (USFS) involving the refurbishment of the Canby Station communication shelter located in Modoc Forest, California. The project requires replacing the roof, exterior walls, and trim of a 15' x 18' stand-alone shelter, with specific requirements including installing new plywood decking, PBR panel roofing, T111 siding, and painting in Benjamin Moore Light Yellow. The work must be completed within 30 days of the Notice to Proceed, with a preliminary project schedule due 10 days after contract award.
The associated federal contract opportunity is a market survey seeking qualified vendors for the project, with an estimated cost between $10,000-$30,000. The Federal Aviation Administration (FAA) intends to award a competitive Firm Fixed Price contract to the lowest responsive bidder, with a preference for small businesses, Service-Disabled Veteran Owned Small Businesses (SDVOSB), and 8(a) program participants. Interested vendors must submit responses electronically by 4:00 p.m. Central Time on August 14, 2025, including statements of capability, past performance, business approach, and a rough order of magnitude estimate for the required services.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AJW-L531 / United States Forest Service
1. Introduction and Overview This Statement of Work (SOW) supports the United States Forest Service (USFS) mission to sustain the health, diversity, and productivity of the nation’s forests and grasslands to meet the needs of current and future generations. This initiative addresses systemic maintenance and critical infrastructure issues affecting the USFS tower inventory and its capability to support mission-critical activities. The selected contractor will independently provide technical and logistical services to assist the Federal Aviation Administration (FAA) in fulfilling the objectives outlined in this scope of work.
2. Scope of Work The work involves replacing the roof, exterior walls, and trim of the Canby station communication shelter. All repairs shall comply with applicable standards for the specified structure. The contractor shall provide all necessary tools, equipment, materials, and technical expertise to complete the following tasks:
a. Facility Description:
· Stand-alone shelter with a 15’ x 18’ (270 square feet structure, 351 square feet roof surface area including pitch) communications building, not attached to any other structure.
b. Site-Specific Requirements:
· Remove existing roof shingles, decking, exterior walls, and trim.
· Install new 5/8” plywood roof decking.
· Install ice and water shield underlayment.
· Install 24-gauge Purlin Bearing Rib (PBR) panel roofing according to manufacturer specifications, including all fasteners, drip edges, sculptured rake pieces, pipe jack flashing, ridge caps, and other necessary components to complete roof installation.
· Roof and trim color: Koko Brown.
· Replace existing attic vents with like-for-like products.
· Install new exterior walls and trim with T111 siding.
· Apply primer coat before painting.
· Paint two coats of Benjamin Moore 289 Light Yellow on siding.
· A certified electrician will be required to remove and reinstall the load center when replacing the siding on the front of the building.
· All removed and unused construction materials, property of the contractor, shall be disposed of at the contractor’s expense in an appropriate location.
2.1 Location of Work
· Shelter refurbishment will occur at the USFS field site and office located at:
22489 CA-299 Ste A, Canby, CA 96015.
· Preparation and planning may be conducted at the contractor’s home office and at USFS field offices (field office management approval required).
2.2 Field Work Locations
| Region |
| Forest |
| Forest Name |
| Site Name |
| Site |
Latitude Site Longitude
| 05 |
| 09 |
| MODOC |
| Canby Station |
| 41°26'44.9"N |
| 120°52'08.5"W |
2.3 Schedule
· The contractor must submit a preliminary project schedule within 10 days of contract award for Government approval.
· A final schedule is due two weeks prior to the start of work.
· The project shall be completed within 30 days of the Notice to Proceed.
Key milestones include:
· Contract Award
· Post-Award Conference
· Deployment Readiness Review
· Mobilization
· Field Work Start
· Field Work Completion
· Cleanup and Site Restoration
2.4 Site Access
· The contractor shall provide a schedule for staging equipment, materials, and installation activities.
· Site access will be granted by FAA and USFS.
· Contractors must notify the assigned USFS radio technician of the date, time, and meeting place for each site visit. The technician will advise on necessary vehicles and access requirements.
· All questions regarding scope must be directed to the primary and secondary contacts listed below. Local FS Points of Contact (POCs) do not have authority to modify the SOW or approve cost-incurring decisions.
· If no site POC is provided, contractors may defer to the Primary USFS POC for contact information.
· When emailing contacts, include all primary and secondary contacts in correspondence.
3. Government Equipment Security
a. Physical Security:
· The contractor is responsible for safeguarding all government property provided during the contract. At the end of each work period, facilities, equipment, and materials must be secured.
b. Key Control:
· The contractor shall establish procedures to prevent loss, misplacement, or unauthorized use of government-issued keys or key cards.
4. Applicable Standards
· OSHA Standards (29 CFR 1910 and 1926): All contractors must adhere to applicable safety and health regulations.
· International Building Code (IBC): All work must comply with applicable building codes.
5. Deliverables and Schedule of Delivery
· The remediation plan shall be submitted with the final schedule two weeks prior to the start of work.
· A report documenting completed on-site activities shall be provided.
· The schedule of prework and on-site activities must be submitted by the contractor and approved by the Primary Project POC.
· Final project documents shall be submitted in PDF format.
6. Completion Criteria
· All required project documentation has been provided to and accepted by USFS and FAA.
· All specified scope requirements have been completed and formally accepted.