A21 - SOW JHK_Lab_24MAR26.pdf
PDF 283 KB Posted
- Attached to
- JHK RIGHT WING DIKE SOIL SAMPLING
- Solicitation number
- W912PM26QA026
About this file
This is a Statement of Work (SOW) for geotechnical and environmental laboratory testing services related to the John H. Kerr Dam Right Wing Dike Toe Drain Replacement project in New Hanover County, North Carolina, dated March 24, 2026.
The Contractor shall conduct geotechnical soils laboratory testing on soil samples collected from the foundation of an excavated trench near the John H. Kerr Dam in Boydton, Virginia. The samples consist predominantly of sandy silts and sandy clay soils (ML and CL classifications). Testing shall be performed by a USACE-validated laboratory in accordance with ASTM methods and completed within 70 calendar days of sample receipt. The specific tests required include: ASTM D6913 Soils Gradation Testing (101 samples), ASTM D4318 Atterberg Limits (101 samples), ASTM D2216 Soils Moisture Content (20 samples), ASTM D2974 Soils Organic Content (5 samples), ASTM D2434 Permeability Constant Head (10 samples), and ASTM D5084 Permeability Falling Head (10 samples). Gradation testing shall utilize 16 specified sieve sizes. The Contractor must retain all sample materials until project closeout, and only completed tests will be paid.
Work shall be performed in three phases with specific submittal deadlines: Phase 1 (15 calendar days) covering approximately 63 "South" samples, Phase 2 (10 calendar days) covering approximately 38 "North" samples, and Phase 3 (24 calendar days) covering approximately 20 blended samples for permeability testing. Following Phase 3 completion, the Contractor shall submit a cumulative Draft Lab Report for USACE review, then a Final Lab Report revised per government comments within 3 calendar days. All submittals must include raw lab data in MS Excel and PDF formats, with the Final Report titled "John H. Kerr Right Wing Dike Toe Drain Replacement, Trench Foundation Geotechnical Laboratory Soils Testing Results" and submitted electronically to designated USACE points of contact. Cost proposals shall be submitted based on two contract line items: Lab Fees and Supplies, and Conduct Geotechnical Soils Testing and Reporting. The Contracting Officer is Mrs. Rosalind Shoemaker, with the Contracting Officer's Representative as Mr. Walter T. Haven, P.G., and technical point of contact as Mr. Kelley Kaltenbach, P.G., all at the Wilmington District of the U.S. Army Corps of Engineers.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
John H. Kerr Dam Right Wing Dike Toe Drain Replacement
2026 Geotechnical and Environmental Laboratory Testing Services New Hanover County, North Carolina
March 24, 2026
I. GENERAL REQUIREMENTS
General.
The Contractor shall furnish all services, labor, equipment, supplies, tools and incidentals necessary to perform geotechnical soils laboratory testing. Testing shall be conducted by a USACE-validated lab in accordance with ASTM methods and quantities described herein. All work within this SOW shall be completed within 70 calendar days of sample receipt by the lab. The soil samples are predominantly sandy silts and sandy clay soils (ML and CL) collected from the foundation of an excavated trench in the vicinity of the John H. Kerr Dam Right Wing Dike, located near Boydton, VA. The numbers and types of test procedures requested are provided in Table 1.
Responsibility The Contractor shall furnish qualified personnel, services, and equipment to ensure the accomplishment of work specified in this SOW. The Contractor is responsible for maintaining the submittal timeline outlined in Table 2.
Direction The Contractor shall accept directions only from the Wilmington District Contracting Officer (KO), Mrs.
Rosalind Shoemaker (910-251-4436) or her designee. Requests or desires of the Users, Using Agency, or any other party made directly to the Contractor shall be immediately brought to the attention of the KO for this Contract. Any changes to this SOW must be authorized in writing by the KO.
Coordination The Contracting Officer’s Representative (COR) is Mr. Walter T. Haven, P.G. (910-251-4495), and he shall be the Contractor’s point of contact (POC) for all submittals and timeline execution. The technical point of contact is Mr. Kelley Kaltenbach, P.G. (910-251-4623). The Contractor’s project manager shall provide a weekly email update to Wilmington District personnel to inform them of contract progress and to review submittals.
The Contractor shall designate a project manager who shall be the principal point of contact for the Wilmington District in administering this contract. The Contractor's project manager shall be responsible for all coordination to ensure the work is accomplished in a professional manner. Any directions given that are viewed by the Contractor as a change to the SOW affecting contract fee or time shall be brought to the immediate attention of the KO or the COR. Contact information is provided below:
Walter T. Haven, P.G.
Walter.T.Haven@usace.army.mil U.S. Army Corps of Engineers Wilmington District Attn: Walter Haven, P.G.
69 Darlington Avenue Wilmington, NC 28403-1343
Kelley J. Kaltenbach, P.G.
Kelley.J.Kaltenbach@usace.army.mil U.S. Army Corps of Engineers Wilmington District Attn: Kelley Kaltenbach, P.G.
69 Darlington Avenue Wilmington, NC 28403‐1343
II. STATEMENT OF SERVICES
Description of Work.
1. The Contractor shall perform geotechnical and environmental soils testing. Specific tests include:
• ASTM D6913, “Particle‐Size Distribution (Gradation) of Soils Using Sieve Analysis.”
Assume no more than 101 samples for lab testing. Sieve sizes are described below.
• ASTM D4318, “Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils.” Assume no more than 101 samples for lab testing.
• ASTM D2216, “Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass.” Assume no more than 20 samples for lab testing.
• ASTM D2974, “Standard Test Methods for Moisture, Ash, and Organic Matter of Peat and Other Organic Soils.” Assume no more than 5 samples for lab testing.
• ASTM D2434, “Measurement of Hydraulic Conductivity of Coarse-Grained Soils.” For estimating purposes, assume 10 samples for lab testing. Assume no more than 20 total samples for combined permeability (Constant or Falling Head) lab testing.
• ASTM D5084, “Measurement of Hydraulic Conductivity of Fine-Grained Soils.” For estimating purposes, assume 10 samples for lab testing. Assume no more than 20 total samples for combined permeability (Constant or Falling Head) lab testing.
The following sieve sizes shall be used for gradation testing (ASTM D6913): 1-in., 3/8-in., No. 4, No.7, No. 10, No. 14, No. 18, No. 25, No. 35, No. 40, No. 60, No. 80, No. 120, No. 170, and No.
200, and No. 230.
USACE personnel shall be responsible for delivery of all soil samples to the Contractor or his/her local representative. USACE will only pay for tests completed. The requested number of reconstituted, remolded Permeability tests (Constant or Falling Head) may vary based on results of Phase 1 and Phase 2 submittals. The Contractor shall retain all material of respective individual samples or requested sample blends until project closeout.
Performance Period.
Refer to Table 2. The period of performance for this contract is 70 calendar days from sample receipt by the lab.
Cost Proposal.
The Contractor shall submit a detailed cost proposal to USACE based on the Contract Line Items described in Table 3.
Submittals.
The Contractor shall perform the lab testing in phases. Refer to Table 2 for Phased Submittal timelines.
Submittal phases do not constitute a description of means and methods, and do not limit the scope of requested work that may be performed within the respective phase.
1. Phase 1 Submital shall include raw lab data covering approximately (63) samples denoted by “South” in a USACE-provided, future lab sample manifest. Test results due in this Phase 1
Submittal include raw lab data for ASTM D6913 Soils Gradation Testing and ASTM D4318 Atterberg Limits performed on each of approximately (63) samples. Phase 1 Submittal will also include raw data for no more than (20) ASTM D2216 Soils Moisture Content and no more than
(5) ASTM D2974 Soils Organic Content tests.
2. Phase 2 Submittal shall include raw lab data covering approximately (38) samples denoted by “North” in a USACE-provided, future lab sample manifest. Test results due in this Phase 2 Submittal include raw lab data for ASTM D6913 Soils Gradation Testing and ASTM D4318 Atterberg Limits performed on each of approximately (38) samples. Phase 2 Submittal will also include raw data for no more than (20) ASTM D2216 Soils Moisture Content and no more than
(5) ASTM D2974 Soils Organic Content tests.
3. Phase 3 Submittal shall include raw lab data covering approximately (20) blended samples denoted in a USACE-provided instruction, due to the Contractor from the government prior to the start of Permeability testing. Test results due in this Phase 3 Submittal include raw lab data for Permeability tests performed on respective samples marked for Permeability testing by either ASTM D2434 (Constant Head) or ASTM D5084 (Falling Head). These raw lab data, combined with Phases 1 and 2 submittals shall be incorporated into the cumulative Draft Lab Report.
Following completion of Phase 3 work, the Contractor shall submit a cumulative digital Draft Lab Report covering all tests from all Phases to USACE for government review and comment. The Draft Lab Report shall include, at a minimum, all laboratory data for all samples tested in accordance with the ASTM methods described. The report shall include gradation tables and curves for each soil sample tested, to include tabulation and graph format of the percentage passing each sieve. The mean and median grain size of each sample shall also be reported in the grain size statistics. Individual soil sample worksheets shall include the project name, laboratory name, sample identification number, and the date the sample was tested. The Contractor shall furnish digital files containing all lab test data in MS Excel and PDF formats.
The Contractor shall then revise the Draft Lab Report per USACE comments as part of Final Lab Report development. The Contractor shall furnish a Final Lab Report to USACE in accordance with Table 2.
Submittals shall be sent electronically to the KO, COR and Technical POC listed below:
• Rosalind.M.Shoemaker@usace.army.mil (or her designee).
• Walter.T.Haven@usace.army.mil; and
• Kelley.J.Kaltenbach@usace.army.mil.
The Final Report shall be titled; “John H. Kerr Right Wing Dike Toe Drain Replacement, Trench Foundation Geotechnical Laboratory Soils Testing Results,” and it shall contain all the elements and requirements specified in this SOW. Digital copies of the Final Report shall be submitted by the Contractor and deemed acceptable by USACE before final payment is made.
Final Submittals (digital) shall be submitted to the following recipient:
Mr. Walt Haven, P.G. (CESAW‐ECE‐G), Geologist, Geotechnical and Dam Safety Section, 69 Darlington Avenue, Wilmington, NC 28403‐1343.
Walter.T.Haven@usace.army.mil.
mailto:Rosalind.M.Shoemaker@usace.army.mil
Anti-Terrorism and Operations Security.
ATOPSEC #1: General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures.
The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
ATOPSEC #14: Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart
22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
Payment Process The Contractor shall submit an invoice to the COR after all work has been completed. The invoice will be reviewed and verified by the KO and COR. USACE will only pay for tests completed., which may vary based on the results of Phase 1 and Phase 2 submittals.
Request for Payment.
The Contractor shall provide a copy of the invoice on completion of agreed services. The invoice shall be provided through the US Postal Service or email, to the Technical Point of Contact or the Contracting https://www.e-verify.gov/)
Officer’s Representative (POC/COR). The contractor shall ensure that the following are included in the invoice:
• Contract #
• Invoice #
• Company Name
• Invoiced Line Item(s) must match the Contract Line Item(s)
• Small Business, Veteran Owned, or 8A – If applicable, indicate on invoice
Table 1. Lab Testing Details.
Laboratory Testing
Geotechnical Soils Testing Quantity Units A. ASTM D6913 Soils Gradation Testing 101 Test B. ASTM D4318 Atterberg Limits 1-pt 101 Test C. ASTM D2216 Soils Moisture Content 20 Test D. ASTM D2974 Soils Organic Content 5 Test E. ASTM D2434 Permeability Constant Head 10 Test F. ASTM D5084 Permeability Falling Head 10 Test
Table 2. Activity Description and Timeline.
Activity Duration
(Calendar days)
USACE
Responsibility Contractor
Responsibility Contract Award 1 X USACE Delivery of Soil Samples to Lab 6 X Laboratory Analysis Phase 1 and Submit 15 X Laboratory Analysis Phase 2 and Submit 10 X SAW Review and Detailed Request for Phase 3 Testing 3 X Laboratory Analysis Phase 3 and Submit 24 X Draft Lab Report - Generate and Submit 5 X SAW Review of Draft Report 7 X Final Lab Report - Generate and Submit 3 X USACE Review and Acceptance 3 X
If the Contractor encounters unforeseen delays in meeting an event on the timeline, the Contractor’s Project Manager shall notify the KO and COR in writing no earlier than 5-business days prior to the due date. The Contractor shall describe the circumstances that led to the delay, his or her immediate actions to mitigate impacts to schedule, and event/timeline updates.
Table 3. Cost Proposal Contract Line Items
Item No.
Description Quantity Unit Unit Cost
Subtotal Cost
0001 Lab Fees and Supplies 1 Job 0002 Conduct Geotechnical Soils Testing and Reporting 1 Job
| General. |
| Direction |
| Coordination |
| II. STATEMENT OF SERVICES |
| Description of Work. |
| Performance Period. |
| Refer to Table 2. The period of performance for this contract is 70 calendar days from sample receipt by the lab. |
| Cost Proposal. |
| Submittals. |
| Anti-Terrorism and Operations Security. |
| Payment Process |
| Request for Payment. |