A21. W912P8-26-B-A002 Solicitation Package including AM0001.pdf

PDF 21 MB Posted

Attached to
FY2025 IDIQ, Atchafalaya Basin, Gulf Intracoastal Waterway (GIWW) and Miscellaneous Projects Cutterhead Dredge
Solicitation number
W912P826BA002
Issued by

About this file

This is a solicitation package for an Indefinite Delivery-Indefinite Quantity (IDIQ) task order contract issued by the U.S. Army Corps of Engineers, New Orleans District, for dredging services. The work consists of furnishing one fully crewed and equipped hydraulic pipeline cutterhead dredge for removal and disposal of shoal material in multiple dredging regions within Louisiana, including Berwick Bay Harbor, Berwick Lock Forebay, Tidewater Point, Morgan City Docks East, GIWW vicinity areas, Port Allen Lock Forebay, Three Rivers, Baton Rouge Harbor, and Old River Lock facilities. The contract period is 24 months commencing from the award date, with task orders issued consecutively during this period. The estimated contract value ranges from $25,000,000 to $100,000,000, with minimum contract value of $10,000.00 and maximum order value not exceeding $40,000,000.00 per task order.

Bidders must select one of five lot options based on dredge discharge pipe diameter (24-inch without or with submerged pump, 27-inch, or 30-inch without or with submerged pump) and submit unit prices for eight bid items including mobilization/demobilization, dredging hours, towing service, picket boat service, bucket dredging, and additional pumping capability. Bidders must provide a completed Cutterhead Dredge Data Sheet demonstrating equipment compliance and documentation proving dredge availability with commencement capability within 240 hours of Notice to Proceed. A pre-award inspection of the dredge is required, and apparent low bidders must establish responsibility through equipment verification and availability documentation, with 24-hour cure periods permitted if deficiencies are identified. The solicitation is a sealed bid (IFB) with electronic submission via email or physical hand delivery to the New Orleans District Contracting Office; bid opening date is to be established by future amendment. Performance and payment bonds equal to 100% of the contract price are required. Bids must acknowledge all amendments and include representations and certifications via SAM.gov registration. Technical inquiries must be submitted through ProjNet at https://www.projnet.org using the provided Bidder Inquiry Key.

View the file

Other files

File Type Posted
Bid Abstract 9-9-2026_SIGNED.pdf PDF
W912P826BA002_AM0003.pdf PDF
W912P826BA002_AM0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OM25065

IFB NO. W912P826BA002

US Army Corps of Engineers New Orleans District

FY2025 IDIQ,

Atchafalaya Basin, Gulf Intracoastal Waterway (GIWW) and Miscellaneous Projects Cutterhead Dredge Louisiana

Construction Solicitation and Specifications

May 2026

DEPARTMENT OF THE ARMY

CORPS OF ENGINEERS, NEW ORLEANS DISTRICT

7400 LEAKE AVENUE

NEW ORLEANS, LOUISIANA 70118-3651

OM 25-065

REPLY TO

ATTENTION OF

May 2026

SOLICITATION: W912P826BA002

FOR: FY2025 IDIQ, Atchafalaya Basin, Gulf Intracoastal Waterway (GIWW) and Miscellaneous Projects Cutterhead Dredge. Specification Numbers OM25065

TO OPEN: By Amendment

Prospective contractors must register in the System for Award Management (SAM). See FAR Clause 52.204-7 for required information. The website for SAM is https://www.sam.gov. As of April 4, 2022, the Federal Government has stopped using the DUNS Number as a unique identifier for entities and switched to a Unique Entity ID generated by SAM.gov. In addition, entities with DUNS Numbers but no SAM.gov registration have been able to get Unique Entity IDs without registering in SAM.gov since October 2021. NOTE: The DUNS Number is no longer used in SAM.gov, eSRS, FSRS, FPDS, CPARS, or FAPIIS.

BIDDERS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS

REQUIRED BY THIS SOLICITATION AND ITS ATTACHMENTS. THE PENALTY FOR MAKING

FALSE STATEMENTS IN BIDS IS PRESCRIBED IN 18 U.S.C. 1001. (FAR 52.214-4 APR 1984)

DESCRIPTION AND MAGNITUDE OF WORK: The work consists of furnishing one fully crewed and equipped hydraulic pipeline cutterhead dredge for the removal and satisfactory disposal of shoal material within any combination of the following Dredging Regions: Berwick Bay Harbor, Berwick Lock Forebay, Tidewater Point, Morgan City Docks East, 20 Grand Point, GIWW vicinity of Mile 99, Wax Lake Outlet, GIWW vicinity of Bayou Shaffer, Port Allen Lock Forebay, Three Rivers, Baton Rouge Harbor (Devil’s Swamp), Old River Lock Forebay and Old River Lock Tailbay. Work may be required in other areas of the New Orleans District.

CAUTION TO BIDDERS: In delivery of hand-carried bids, bidders are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time and for visitor background checks by MVN security when entering the installation at place of bid opening. Such delays DO NOT permit acceptance or consideration of late bids.

NOTE: ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN

ACCORDANCE WITH THE PROVISIONS OF EM 385-1-1 "CORPS OF ENGINEERS SAFETY

AND HEALTH REQUIREMENTS MANUAL", DATED 15 MARCH 2024.

ATTENTION: Contractors must complete, and submit with their bid, the provisions located in Section 00 45 00. A bidder may also submit, in lieu of the completed Section 00 45 00, a complete copy of their Online Representations and Certifications from SAM.gov with an expiration date on or after the date of award.

http://fedgov.dnb.com/webform

ALL INQUIRIES REGARDING THIS SOLICITATION

SHOULD BE MADE TO THE FOLLOWING:

ANGELA C. DAY

CONTRACT SPECIALIST

U.S. ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT

E‐MAIL: ANGELA.C.DAY@USACE.ARMY.MIL

PHONE: (504) 862-1047

COLLECT CALLS NOT ACCEPTED

NOTE: FOR THE MOST PROMPT REPSONSE, PLEASE SEND ALL QUESTIONS VIA

E‐MAIL.

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 10 00 BID SCHEDULE

00 21 00 INSTRUCTIONS TO BIDDERS

00 22 00 SUPPLEMENTARY INSTRUCTIONS

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 70 00 CONDITIONS OF THE CONTRACT

00 72 00 GENERAL CONDITIONS

00 73 00 SUPPLEMENTARY CONDITIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 20.00 10 ENVIRONMENTAL PROTECTION

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 01 50.73 SURVEYS

35 20 23.23 HYDRAULIC DREDGING

35 20 23.23 01 HYDRAULIC DREDGING - BERWICK BAY HARBOR, BERWICK LOCK

FOREBAY, TIDEWATER POINT, MORGAN CITY DOCKS EAST, AND

STOUT'S PASS DREDGING REGION

35 20 23.23 02 HYDRAULIC DREDGING - GIWW VICINITY OF MILE 99, 20 GRAND

POINT, WAX LAKE OUTLET, AND GIWW VICINITY OF BAYOU

SHAFFER DREDGING REGION

35 20 23.23 03 HYDRAULIC DREDGING - PORT ALLEN LOCK FOREBAY DREDGING

REGION

35 20 23.23 04 HYDRAULIC DREDGING - THREE RIVERS DREDGING REGION

35 20 23.23 05 HYDRAULIC DREDGING - BATON ROUGE HARBOR (DEVIL'S SWAMP)

DREDGING REGION

35 20 23.23 06 HYDRAULIC DREDGING - OLD RIVER LOCK FOREBAY AND TAILBAY

DREDGING REGION

35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM PIPELINE

HYDRAULIC DREDGE

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS

IDIQ Atchafalaya Basin, GIWW & Misc. Projects CD OM25065

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 10 00

BID SCHEDULE

PART 1 GENERAL

1.1 BIDDING SCHEDULES

1.2 BID FORM NOTES

1.3 TYPE OF CONTRACT

1.4 CONTRACT PERIOD / ORDERING PERIOD

1.5 BIDDING

1.6 EVALUATION OF BIDS

1.7 BIDDER QUALIFICATIONS

1.8 CONDITIONS OF CONTRACT AWARD

1.9 OTHER BIDDER REQUIREMENTS

1.10 PRE-AWARD INSPECTION OF PLANT

1.11 MINIMUM AND MAXIMUM CONTRACT VALUE AND TASK ORDER VALUE

1.12 DEFINITIONS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 00 10 00 Page 1

SECTION 00 10 00

BID SCHEDULE

PART 1 GENERAL

1.1 BIDDING SCHEDULES

See bid schedules on the following pages.

SECTION 00 10 00 Page 2

SECTION 00 10 00 - BIDDING SCHEDULE

INDEFINITE DELIVERY, INDEFINITE QUANTITY (TASK ORDER) CONTRACT

ATCHAFALAYA BASIN, GULF INTRACOASTAL WATERWAY (GIWW)

AND MISCELLANEOUS PROJECTS

CUTTERHEAD DREDGE

SOLICITATION NO. W912P826BA002

LOT ONE, 24 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITHOUT SUBMERGED PUMP

Bid Item

DESCRIPTION Estimated Quantity

Unit Unit Price

Total Price

0001 INITIAL MOBILIZATION AND

INITIAL DEMOBILIZATION

1 JOB

OPTION

ADDITIONAL MOBILIZATION AND

DEMOBILIZATION

2 EACH TO BE NEGOTIATED PER

NON-CONSECUTIVE TASK

ORDER

0003 DREDGING 5768 HOUR

0004 DREDGE TOWING SERVICE 420 MILE

0005 PICKET BOAT SERVICE 6633 HOUR

0006 PORT ALLEN LOCK FOREBAY

BUCKET DREDGING

1 JOB

ADDITIONAL PUMPING

CAPABILITY FOR DREDGING ITEM

333 HOUR

MOBILIZATION AND

DEMOBILIZATION OF ADDITIONAL

PUMPING CAPABILITY EQUIPMENT

FOR ITEM 0007

1 JOB

TOTAL: LOT ONE BID

SECTION 00 10 00 Page 3

INDEFINITE DELIVERY, INDEFINITE QUANTITY (TASK ORDER) CONTRACT

ATCHAFALAYA BASIN, GULF INTRACOASTAL WATERWAY (GIWW)

AND MISCELLANEOUS PROJECTS

CUTTERHEAD DREDGE

SOLICITATION NO. W912P826BA002

LOT TWO, 24 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITH SUBMERGED PUMP

Bid Item

DESCRIPTION Estimated Quantity

Unit Unit Price Total Price

0001 INITIAL MOBILIZATION AND

INITIAL DEMOBILIZATION

1 JOB

OPTION

ADDITIONAL MOBILIZATION AND

DEMOBILIZATION

2 EACH TO BE NEGOTIATED PER

NON-CONSECUTIVE TASK

ORDER

0003 DREDGING 4002 HOUR

0004 DREDGE TOWING SERVICE 420 MILE

0005 PICKET BOAT SERVICE 4602 HOUR

0006 PORT ALLEN LOCK FOREBAY

BUCKET DREDGING

1 JOB

0007 ADDITIONAL PUMPING

CAPABILITY FOR DREDGING ITEM

267 HOUR

0008 MOBILIZATION AND

DEMOBILIZATION OF ADDITIONAL

PUMPING CAPABILITY EQUIPMENT

FOR ITEM 0007

1 JOB

TOTAL: LOT TWO BID

SECTION 00 10 00 Page 4

INDEFINITE DELIVERY, INDEFINITE QUANTITY (TASK ORDER) CONTRACT

ATCHAFALAYA BASIN, GULF INTRACOASTAL WATERWAY (GIWW)

AND MISCELLANEOUS PROJECTS

CUTTERHEAD DREDGE

SOLICITATION NO. W912P826BA002

LOT THREE, 27 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITHOUT SUBMERGED

PUMP

Bid Item

DESCRIPTION Estimated Quantity

Unit Unit Price

Total Price

0001 INITIAL MOBILIZATION AND

INITIAL DEMOBILIZATION

1 JOB

OPTION

ADDITIONAL MOBILIZATION

AND DEMOBILIZATION

2 EACH TO BE NEGOTIATED PER

NON-CONSECUTIVE TASK

ORDER

0003 DREDGING 4561 HOUR

0004 DREDGE TOWING SERVICE 420 MILE

0005 PICKET BOAT SERVICE 5245 HOUR

0006 PORT ALLEN LOCK FOREBAY

BUCKET DREDGING

1 JOB

0007 ADDITIONAL PUMPING

CAPABILITY FOR DREDGING

ITEM 0003

263 HOUR

0008 MOBILIZATION AND

DEMOBILIZATION OF

ADDITIONAL PUMPING

CAPABILITY EQUIPMENT FOR

ITEM 0007

1 JOB

TOTAL: LOT THREE BID

SECTION 00 10 00 Page 5

INDEFINITE DELIVERY, INDEFINITE QUANTITY (TASK ORDER) CONTRACT

ATCHAFALAYA BASIN, GULF INTRACOASTAL WATERWAY (GIWW)

AND MISCELLANEOUS PROJECTS

CUTTERHEAD DREDGE

SOLICITATION NO. W912P826BA002

LOT FOUR, 30 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITHOUT SUBMERGED

PUMP

Bid Item

DESCRIPTION Estimated Quantity

Unit Unit Price Total Price

0001 INITIAL MOBILIZATION AND

INITIAL DEMOBILIZATION

1 JOB

OPTION

ADDITIONAL MOBILIZATION AND

DEMOBILIZATION

2 EACH TO BE NEGOTIATED PER

NON-CONSECUTIVE TASK

ORDER

0003 DREDGING 3692 HOUR

0004 DREDGE TOWING SERVICE 420 MILE

0005 PICKET BOAT SERVICE 4246 HOUR

0006 PORT ALLEN LOCK FOREBAY

BUCKET DREDGING

1 JOB

0007 ADDITIONAL PUMPING CAPABILITY

FOR DREDGING ITEM 0003

213 HOUR

0008 MOBILIZATION AND

DEMOBILIZATION OF ADDITIONAL

PUMPING CAPABILITY EQUIPMENT

FOR ITEM 0007

1 JOB

TOTAL: LOT FOUR BID

SECTION 00 10 00 Page 6

INDEFINITE DELIVERY, INDEFINITE QUANTITY (TASK ORDER) CONTRACT

ATCHAFALAYA BASIN, GULF INTRACOASTAL WATERWAY (GIWW)

AND MISCELLANEOUS PROJECTS

CUTTERHEAD DREDGE

SOLICITATION NO. W912P826BA002

LOT FIVE, 30 IN. INSIDE DIAMETER (ID) PUMP DISCHARGE WITH SUBMERGED PUMP

Bid Item

DESCRIPTION Estimated Quantity

Unit Unit Price

Total Price

0001 INITIAL MOBILIZATION AND

INITIAL DEMOBILIZATION

1 JOB

OPTION

ADDITIONAL MOBILIZATION AND

DEMOBILIZATION

2 EACH TO BE NEGOTIATED PER

NON-CONSECUTIVE TASK

ORDER

0003 DREDGING 2412 HOUR

0004 DREDGE TOWING SERVICE 420 MILE

0005 PICKET BOAT SERVICE 2774 HOUR

0006 PORT ALLEN LOCK FOREBAY

BUCKET DREDGING

1 JOB

0007 ADDITIONAL PUMPING CAPABILITY

FOR DREDGING ITEM 0003

161 HOUR

0008 MOBILIZATION AND

DEMOBILIZATION OF ADDITIONAL

PUMPING CAPABILITY EQUIPMENT

FOR ITEM 0007

1 JOB

TOTAL: LOT FIVE BID

SECTION 00 10 00 Page 7

1.2 BID FORM NOTES

a. Bidders shall bid on all items including optional items (see "Evaluation of Options" FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.

b. Any bid may be rejected if the Contracting Officer or his/her authorized representative determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only the total price of the bid, but the prices for individual line items as well. Any bid may be rejected if the prices for any line items or subline items are materially unbalanced (see "Rejection of Individual Bids" FAR 14.306 -3).

c. THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442 after Notice of Award. The NTP will be issued after verification of acceptable performance and payment bonds. Within two (2) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Administrative Contracting Officer or his authorized representative.

Physical work cannot start until the Resident Management System is set-up, the Accident Prevention Program and other required submittals have been submitted and approved, and all preliminary meetings called for under the contract have been conducted.

d. A bidder may be rejected as non-responsible if it cannot show the necessary capital, experience, or equipment needed to perform the work described under this solicitation (see "Responsible Prospective Contractors" FAR Subpart 9.1). Before the Government will award a contract based on this solicitation, the apparent low bidder shall establish that it is responsible and entitled to award of the contract.

e. The unit "Job" is synonymous with the previously used term "lump sum".

f. Bidders shall select the bid lot determined by the dredge discharge size. The dredge discharge size is considered to be the least inside diameter of the following: the main pump discharge, the submerged pump discharge, the booster pump discharge, or the discharge pipeline.

1.3 TYPE OF CONTRACT

This solicitation is for an Indefinite Delivery-Indefinite Quantity (Task Order) Contract for one fully operational cutterhead dredge with attendant plant on a hourly basis. The task orders will be placed in accordance with the terms and conditions of this contract as requirements are identified during the stated contract period. Task orders will be issued for all dredging work to be performed under this IDIQ contract.

1.4 CONTRACT PERIOD / ORDERING PERIOD

The contract period / ordering period shall commence on the date of contract award and may remain in effect for a 24 month period. Task orders will be issued to the Contractor consecutively with no interruptions of work. Upon completion of consecutive task orders, the Government will release the dredge to the Contractor. However, after the dredge has been released, additional task orders may be issued during the contract period.

If the Government deems that there is a need for additional work after the

SECTION 00 10 00 Page 8 dredge has been released, an Individual Request for Proposal (RFP) will be sent to the Contractor allowing only the negotiation of Bid Item 0002 "Additional Mobilization and Demobilization", with all other work within the RFP to be paid at the unit prices in the original bid. Upon receipt of the Contractor's proposal, the Government will review the proposal. If mutually agreeable, the non-consecutive task order will be issued. If not mutually agreeable to either party, the Government may seek other contractual means to accomplish the work.

1.5 BIDDING

a. The bidder shall select only one bid lot, determined by the class of dredge intended to be used. Bids which are submitted on an inappropriate bid lot will be declared non-responsive.

b. Bidders shall furnish unit prices for all items listed on the schedule of bid items that require unit prices. If the bidder fails to insert a unit price in the appropriate blank for required items but does furnish an extended total or an estimated amount for such items, the Government will deem the unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED

ESTIMATED AMOUNT FOR ANY REQUIRED ITEM, THE BID WILL BE DECLARED

NON-RESPONSIVE.

1.6 EVALUATION OF BIDS

a. To provide fair competition between dredges of dissimilar sizes and production rates, the hourly dredging quantities have been determined based on the estimated quantity of shoal material to be removed and the nominal production rates of the dredges in each bid lot. The production rates shown in the paragraph entitled "Minimum Production Rate Requirements" located in the Dredging Regions Section(s) were used to make this determination.

b. The nominal dredge production rates listed in this solicitation were conservatively estimated based on an average "Standard" cross-sectional quantity of material for this solicitation's dredging regions, which have variable and dynamic shoaling conditions. It is the bidder's responsibility to make its own assessment of the actual dredging conditions in order to prepare a bid for this work.

c. Award will be made to that responsible bidder presenting the lowest priced responsive bid in response to this solicitation, regardless of the Bid Lot used.

d. The hourly quantities shown on the bid lots (Bid Item, "Dredging") are 100% pay time hours. The actual term of the dredge time may vary as a result of fractional pay time. Refer to Section 35 20 23.23, paragraph entitled "Dredging Item", for additional information.

1.7 BIDDER QUALIFICATIONS

A pre-award survey will be required. Before award, the apparent low bidder shall provide documentation to satisfy the following definitive responsibility criteria. The bidder must establish responsibility by providing sufficient documentation for review and approval for the following criteria: the dredge must meet the equipment requirements as stated in Section 35 20 23.23, paragraph entitled "Size and Equipment of

SECTION 00 10 00 Page 9

Dredge Plant", and the dredge must be available to commence dredging within the time required in the specifications as stated in the paragraph entitled "Conditions of Contract Award". An apparent low bidder who is not able to meet the definitive responsibility criteria will be deemed non-responsible and will be ineligible for award:

Bidders shall furnish in their bid package the following:

(a) A completed "Cutterhead Dredge and Attendant Plant Data Sheet" (see Section 35 20 23.23) for the dredge the Contractor will use under this solicitation; and

(b) Documentation to prove that the dredge and attendant plant are available and not already obligated for the performance of other work which would delay commencement of dredging. If the proposed dredge and attendant plant are not currently performing work or obligated under a contract, the bidder must submit a statement that the dredge and attendant plant can commence dredging within the time required in the specifications. If the proposed dredge and attendant plant are currently performing work or obligated under a contract, the bidder must submit approved release documentation along with a statement that the dredge and attendant plant can commence dredging within the time required in the specifications. The approved release documentation must be issued by the entity currently utilizing the dredge and attendant plant, and the documentation must clearly indicate the approved release date of the dredge and attendant plant from its current work commitment.

(i) The following timeframes for contract award and Notice to Proceed are the Government's best estimate and will be used during evaluation of the bidder's submitted availability documentation.

The Government does not warrant the accuracy of the below estimated dates, and the Government will not be liable for any delay in award or issuance of Notice to Proceed, regardless of cause. These dates are for informational purposes only and do not create any legal obligation on the part of the Government.

(ii) It is anticipated that contract award will be made within 5 to 7 calendar days after the bid opening date.

(iii) It is anticipated that Notice to Proceed will be issued within 1 to 3 calendar days after receipt of performance and payment bonds from the successful bidder.

If the apparent low bidder fails to furnish the "Cutterhead Dredge and Attendant Plant Data Sheet" or the availability documentation within his/her bid package, the apparent low bidder will have 24 hours after the time of the bid opening to provide the Contracting Officer the documents.

If the apparent low bidder fails to furnish the proper documentation within 24 hours after the time of the bid opening, the respective bidder will be declared non-responsible and the next apparent low bidder will be evaluated as stated in the paragraphs below.

Upon receipt of the apparent low bidder's completed "Cutterhead Dredge and Attendant Plant Data Sheet" for the dredge that will be used to perform work under this solicitation, the "Cutterhead Dredge and Attendant Plant Data Sheet" will be evaluated to ensure that the dredge meets the equipment requirements as stated in Section 35 20 23.23, paragraph entitled "Size and Equipment of Dredge Plant". Upon receipt of the apparent low bidder's

SECTION 00 10 00 Page 10 availability documentation, the availability documentation will be evaluated to ensure that the dredge can commence dredging within the time required in the specifications.

If, after review, the Government determines that the submitted documents satisfy the equipment requirements and the availability requirement, the Government will proceed with award of the contract to the apparent low bidder provided all other requirements for award have been satisfied.

If, after review, the Government determines that the submitted documents do not satisfy the equipment requirements or the availability requirement, the Government will give the apparent low bidder 24 hours to resubmit the documents.

If, after a second review, the Government determines that the submitted documents do not satisfy the equipment requirements or the availability requirement, the Government will declare the apparent low bidder to be non-responsible. The Government will thereafter perform the described pre-award survey on the next apparent low bidder and will do so with each successive apparent low bidder until it is determined that an apparent low bidder has submitted documents that satisfy the equipment requirements and the availability requirement. The apparent low bidder that does satisfy the equipment requirements and the availability requirement will be deemed responsible and eligible for award provided all other requirements for award have been satisfied.

1.8 CONDITIONS OF CONTRACT AWARD

a. Award will be made as a whole to one bidder. The dredge and attendant plant offered in the bidding schedule shall be complete with full operating personnel and in operating status for the contract period. EM 385-1-1, Chapter 19, "Floating Plant and Marine Activities" shall be complied with at all times. NOTE: All work under these specifications shall be performed in accordance with the provisions of EM 385-1-1 "Safety and Occupational Health Requirements", latest edition.

b. The number of hours in the bidding schedule is an estimated quantity. The Government is not bound by the estimated quantities;

however, the Contractor's proposed unit prices are binding.

c. The bidder shall be capable of providing for assignment of the dredge and all attendant plant, complete and in full operating condition in all respects, and to commence dredging no later than 240 hours after issuance of the Notice to Proceed for the initial task order ordering work.

1.9 OTHER BIDDER REQUIREMENTS

a. Bidders shall register in the System for Award Management (SAM) database in accordance with FAR 52.204-7-NOV 2024.

b. Bidders shall use Rapid Vendor Payment. See the following web based instructions for the submission of invoices:

https://www.mvn.usace.army.mil/Business-With-Us/Contracting/Rapid-Vendor -Payment/.

c. Bidders shall provide sufficient documentation for review and approval that its dredge meets the appropriate production rate for the

SECTION 00 10 00 Page 11 dredging region, as listed in the chart in the paragraph entitled "Minimum Production Rate Requirements" located in the Dredging Region Section(s). The Contractor must prove that the proposed dredge has performed at, or above, the listed production rate for a minimum of 30 days on a single contract within three years prior to the bid opening date of this solicitation. Failure to establish the dredge's capability to meet the required production rate will result in a finding of non-responsibility.

1.10 PRE-AWARD INSPECTION OF PLANT

a. The apparent low bidder shall make the dredge and attendant plant available for inspection, to determine compliance with these specifications, as soon as practicable after bids are opened, and prior to contract award. If deficiencies are found during the inspection, the bidder will be notified in writing, which may be transmitted by email. Upon receipt of such notice, the bidder shall correct all deficiencies at least two calendar days in advance of the projected contract award date.

b. Two calendar days before the projected award date, or upon notification by the bidder that the deficiencies have been corrected, a Government representative will re-inspect the dredge and attendant plant. If at that time the dredge and attendant plant do not meet the requirements of these specifications, the bidder will be rejected as non-responsible.

c. The Government may choose to waive the pre-award inspection.

Waiver of the pre-award inspection does not relieve the bidder from the requirement to provide a dredge and attendant plant in full compliance with the specifications. By bidding on this solicitation, the bidder is stating that the provided dredge and attendant plant is in full compliance with the specifications and can perform all requirements as stated in the specifications.

1.11 MINIMUM AND MAXIMUM CONTRACT VALUE AND TASK ORDER VALUE

a. Minimum and Maximum Contract Value: The minimum contract value for all orders issued against this contract shall not be less than $10,000.00. In the event the Government does not order the minimum contract value of $10,000.00, the Contractor is entitled to a reasonable profit on the unordered value up to $10,000.00. The maximum contract value for all orders issued against this contract shall not exceed $40,000,000.00.

b. Minimum and Maximum Task Order Value: The minimum order value for each task order issued shall not be less than $10,000.00. The maximum order value for each task order issued shall not exceed $40,000,000.00.

1.12 DEFINITIONS

a. Consecutive task order = a task order that the Government issues to the Contractor in order to provide continuous operation of the dredge and attendant plant. Consecutive task orders are unilaterally made and do not require mutual agreement. The Contractor must perform consecutive task orders. The Contractor must commence dredging immediately upon completion of previous task order(s).

b. Non-consecutive task order = a task order that the Government

SECTION 00 10 00 Page 12 issues to the Contractor after the Government released the dredge and attendant plant to the Contractor and prior to expiration of the contract period. A non-consecutive task order requires mutual agreement between the Government and the Contractor prior to issuance.

The Contractor must commence dredging no later than the negotiated commencement date.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

SECTION 00 10 00 Page 13

Bid Bond (See Instructions on Page 3)

Date Bond Executed (Must Not Be Later Than Bid Opening Date)

OMB Control Number: 9000-0001 Expiration Date: 1/31/2027

Principal (Legal Name And Business Address) Type Of Organization ("X" One)

State Of Incorporation

Surety(ies) (Name And Business Address)

Percent Of Bid Price

Penal Sum Of Bond Amount Not To Exceed Million(s) Thousand(s) Hundred(s) Cents

Bid Identification Bid Date Invitation Number

Authorized For Local Reproduction Previous Edition Is Not Usable

STANDARD FORM 24 (REV. 10/2023)

Prescribed by GSA - FAR (48 CFR) 53.228(a)

For (Construction, Supplies Or Services)

Obligation:

We, the Principal and Surety(ies) are firmly bound to the United States of America (hereinafter called the Government) in the above penal sum. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. However, where the Sureties are corporations acting as co-sureties, we, the Sureties, bind ourselves in such sum "jointly and severally" as well as "severally" only for the purpose of allowing a joint action or actions against any or all of us. For all other purposes, each Surety binds itself, jointly and severally with the Principal, for the payment of the sum shown opposite the name of the Surety. If no limit of liability is indicated, the limit of liability is the full amount of the penal sum.

Conditions:

The Principal has submitted the bid identified above.

Therefore:

The above obligation is void if the Principal - (a) upon acceptance by the Government of the bid identified above, within the period specified therein for acceptance (sixty (60) days if no period is specified), executes the further contractual documents and gives the bond(s) required by the terms of the bid as accepted within the time specified (ten (10) days if no period is specified) after receipt of the forms by the Principal; or (b) in the event of failure to execute such further contractual documents and give such bonds, pays the Government for any cost of procuring the work which exceeds the amount of the bid.

Each Surety executing this instrument agrees that its obligation is not impaired by any extension(s) of the time for acceptance of the bid that the Principal may grant to the Government. Notice to the Surety(ies) of extension(s) is waived. However, waiver of the notice applies only to extensions aggregating not more than sixty (60) calendar days in addition to the period originally allowed for acceptance of the bid.

Other (Specify) Individual Partnership Joint Venture Corporation

2.

(Seal)2.(Seal)

1.

1.

1.

1. 3.2.

Name(s) (Typed)

Signature(s)

Individual Surety(ies)

Name(s) And Title(s) (Typed)

Corporate Seal

(Seal)

3.

(Seal)

2.

(Seal) Signature(s)

Principal

2.

State Of Incorporation Liability Limit ($)

2.

2.

1.Name(s) And Title(s) (Typed)

Signature(s) 1. 2. Corporate Seal

Corporate Seal

Su re ty C

Name And Address

Signature(s) Name(s) And Title(s) (Typed)

1.

1.

2.

2.

State Of Incorporation Liability Limit ($)

Corporate Seal

Name(s) And Title(s) (Typed)

Su re ty D

Signature(s)

Name And Address

1.

1.

2.

2.

State Of Incorporation Liability Limit ($)

Corporate Seal

Liability Limit ($)State Of Incorporation

1.

1.

Su re ty A

Name And Address

Su re ty B

Name(s) And Title(s) (Typed)

Signature(s)

Name And Address

Corporate Surety(ies)

Witness:

The Principal and Surety(ies) executed this bid bond and affixed their seals on the above date.

STANDARD FORM 24 (REV. 10/2023) PAGE 2

STANDARD FORM 24 (REV. 10/2023) PAGE 3

Corporate Seal

Su re ty F

Name And Address

Signature(s) Name(s) And Title(s) (Typed)

1.

1.

State Of Incorporation

2.

2.

Liability Limit ($)

Corporate Seal

Name(s) And Title(s) (Typed)

Su re ty G

Signature(s)

Name And Address

1.

1.

2.

2.

State Of Incorporation Liability Limit ($)

Corporate Seal

State Of Incorporation Liability Limit ($)

2.

2.

1.

1.

Name And Address

Signature(s) Name(s) And Title(s) (Typed)

Su re ty E

Instructions

1. This form is authorized for use when a bid guaranty is required. Any deviation from this form will require the written approval of the Administrator of General Services.

2. Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved.

3. The bond may express penal sum as a percentage of the bid price. In these cases, the bond may state a maximum dollar limitation (e.g., 20% of the bid price but the amount not to exceed dollars).

4. (a) Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. The value put into the Liability

Limit block is the penal sum (i.e., the face value) of the bond, unless a co-surety arrangement is proposed.

(b) When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "Corporate Surety(ies)." In the space designated

"Surety(ies)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bond, provided that the sum total of their liability equals 100% of the bond penal sum.

(c) When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond. The Government may require the surety to furnish additional substantiating information concerning its financial capability.

5. Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word "Corporate Seal"; and shall affix an adhesive seal if executed in Maine, New

Hampshire, or any other jurisdiction requiring adhesive seals.

6. Type the name and title of each person signing this bond in the space provided.

7. In its application to negotiated contracts, the terms "bid" and "bidder" shall include "proposal" and

"offeror."

STANDARD FORM 24 (REV. 10/2023) PAGE 4

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 USC §

3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0001. We estimate that it will take 1 hour to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: General

Services Administration, Regulatory Secretariat Division (MVCB), 1800 F Street, NW, Washington, DC

20405.

Section 00 21 00 - Instructions

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-7 System for Award Management. 2024-11

52.214-3 Amendments to Invitations for Bids.

2016-12

52.214-4 False Statements in Bids. 1984-04

52.214-5 Submission of Bids. 2016-12

52.214-6 Explanation to Prospective Bidders.

1984-04

52.214-7 Late Submissions, Modifications, and Withdrawals of Bids.

1999-11

52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work.

2014-05

52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements.

2014-05

DFARS Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

W912P826BA0020001

252.204-7024 Notice on the Use of the Supplier Performance Risk System.

2023-03

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.

2023-01

FAR Provisions Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.216-1 Type of Contract. 1984-04

Type of Contract (Apr 1984)

The Government contemplates award of a contract resulting from this firm-fixed price solicitation.

(End of provision)

52.228-1 Bid Guarantee. 1996-09

Bid Guarantee (Sept 1996)

Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening (a) of bids, may be cause for rejection of the bid.

The bidder shall furnish a bid guarantee in the form of a firm commitment, bid bond (b) e.g., supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-

To unsuccessful bidders as soon as practicable after the opening of bids; and(1)

To the successful bidder upon execution of contractual documents and bonds (including any (2) necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

The amount of the bid guarantee shall be percent of the bid price or $(c) twenty (20%) _ , whichever is less._$3,000,000.00___

If the successful bidder, upon acceptance of its bid by the Government within the period (d) specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

In the event the contract is terminated for default, the bidder is liable for any cost of (e) acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of clause)

52.233-2 Service of Protest. 2006-09

Service of Protest (Sept 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed (a) directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from USACE - New Orleans District, Contracting Office, Projects West Branch7400 Leake Avenue, Rm. 172, New Orleans, LA 70118

The copy of any protest shall be received in the office designated above within one day of (b) filing a protest with the GAO.

(End of provision)

52.252-1 Solicitation Provisions Incorporated by Reference.

1998-02

Solicitation Provisions Incorporated by Reference (Feb 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

www.acquistion.gov________[Insert one or more Internet addresses]

(End of provision)

52.252-5 Authorized Deviations in Provisions.

2020-11

Authorized Deviations in Provisions (Nov 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any ____[insert regulation name](48 CFR Chapter____) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 22 00 - Supplementary Instructions

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.217-5 Evaluation of Options. 1990-07

Instructions to Bidders

QUESTION AND ANSWER VIA PROJNET

ALL SUBMITTED QUESTIONS FOR THIS PROJECT AND THE ANSWERS PROVIDED

SHALL BE VIEWED IN BIDDER INQUIRY IN PROJNET AT

(https://www.projnet.org) Technical inquiries and/or questions relating to this solicitation shall be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org). A question period will be set when the bid opening date is established.

To submit or review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. Emailed inquiries and/or questions will not be accepted. A prospective vendor who submits a comment /question will receive an acknowledgment of their comment/question via email.

Another email to the same address will notify the prospective vendor once the reply is available for viewing.

The Bidder Inquiry Key is: RE6C9R-Y7DRI5

Specific Instructions for First Time ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

https://www.projnet.org/

SOLICITATION NUMBER: W912P826BA002

NOTE: BIDDERS MAY SUBMIT BIDS BY ONLY ONE METHOD: A) ELECTRONIC

COMMERCE (EMAIL) OR BY 2) PHYSICAL SUBMISSION. BIDDERS SHALL LIMIT THE BID

SUBMITTAL TO ONE OPTION OR THE OTHER, NOT BOTH.

Electronic Submission of Bids/Proposals (Email):

The New Orleans District utilizes electronic commerce (Email) for receipt of electronic bids under this IFB solicitation. To submit an electronic commerce (Email) bid please follow these steps:

1. Send an email containing your name, email address and bid/proposal to the following emails associated with the IFB (MUST include all emails):

• ANGELA.C.DAY@USACE.ARMY.MIL

• CHRISTOPHER.NUCCIO@USACE.ARMY.MIL

2. ALL BIDS SUBMITTED BY EMAIL MUST CONTAIN THE SOLICITATION NUMBER IN

THE SUBJECT LINE.

3. Once the agency receives your bid/proposal at the above email addresses, you will then receive a confirmation email stating your bid/proposal was received. If a bidder does not receive a reply acknowledging receipt electronically from the New Orleans District, it is incumbent upon the bidder to seek confirmation from the issuing Contracting office by phone.

Note: The size limit for incoming emails is 35MB. Any bid/proposal over this size may not be accepted by the server and will constitute the bid not being received timely. Please note that embedded links, URLs, and other html language included may interfere with the USACE server security, which may cause emails to be removed prior to being received by the contracting office. Bidders are advised to refrain from including external links, embedded links, URLs, and other html language not germane to the proposal/bid. Please note it is a bidder’s responsibility, when transmitting its bid electronically, to ensure the receipt of its bid to the proper designee at the proper time. See FAR 14.304(b)(1)(i) regarding untimely electronic bids. Please note, MVN’s computer system firewall may cause a delay in receipt of emails, so be sure to allow ample time for possible delay. If your email would exceed 35MB you can use one of the following methods as a work-around:

• Use .zip files as attachments. Combine multiple files into a .zip file to compress file size prior to adding as an email attachment.

• Send multiple emails. Label each email with same subject line and indicate number of emails. For example: Smith Construction W912P826BAXXX (1 of 2) Smith Construction W912P826BAXXX (2 of 2).

mailto:KAREN.D.HARGRAVE@USACE.ARMY.MIL

Physical Submission of Bids:

Bidders may submit their bids by hand carrying or express mail to the New Orleans District Contracting Office in Room 172. Bidders are advised to allow adequate time to ensure timely submission of its bid.