A2. Statement of Work for the ESR D2 Dipole Magnets.pdf

PDF 318 KB Posted

Attached to
Electron Storage Ring D2 Dipole Magnets
Solicitation number
462499
Issued by

About this file

This is a Statement of Work (SOW) for the procurement of Electron Storage Ring (ESR) D2 Dipole Magnets for the Electron-Ion Collider (EIC) at Brookhaven National Laboratory (BNL), managed by Brookhaven Science Associates (BSA). The document is controlled under U.S. Department of Commerce Export Administration Regulations as EAR99 Technology.

The Contractor shall design, manufacture, inspect, test, and deliver one first article magnet and 194 production magnets across five configurations. Magnet quantities include: 176 units of the D2 Magnet Assembly (2104M0025), 8 units of 13-turn configuration (2104M0052), 8 units of 11-turn configuration (2104M0055), 1 unit of 5-to-1 turn configuration (2104M0061), and 1 unit of 21-to-5 turn configuration (2104M0084). The Contractor must procure all 730 tons of steel in a single procurement from preferably one heat to enable lamination shuffling for minimal magnetic field variation, with material certifications supplied to BSA prior to delivery. The design must comply with technical specifications EIC-MSG-SPC-009 and EIC-MSG-SPC-010, ASME Y14.100 drawing standards, and ISO-9001 quality management requirements. Key milestones include Preliminary Design Review at week 5, Final Design Review at week 10, first article delivery at week 44, Manufacturing Readiness Review approval at week 54, and production magnet delivery at week 104. The Contractor is responsible for all tooling, fixtures, and test equipment; shall maintain special tooling for three years post-completion; must conduct bi-weekly progress meetings with BSA; and shall provide monthly performance reports. BSA reserves witness point rights with ten working days' notice and conducts final acceptance testing and magnetic measurement at no cost to the Contractor. All documentation, including design analyses, Manufacturing/Inspection/Test Plans, and End-Item documentation packages, must be provided in English with electronic copies in native ANSYS format or equivalent.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Electron-Ion Collider, Brookhaven National Laboratory

Doc No. EIC-MSG-SOW-018 Author: George Mahler Effective Date: July 28, 2026 Review Frequency: N/A

SOW: Statement of Work for the ESR D2 Dipole Magnets Revision: 03

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

Parts 730-774 as EAR99 Technology

STATEMENT OF WORK

for the

Electron Storage Ring D2 Dipole Magnets

Quality Classification: A-3

Prepared By:

_____________________________________________ Date: __________________

George Mahler, Group Leader – Normal Conducting Magnets

Reviewed By:

Sara Notaro, Technical Representative

Joseph Zipper, Quality Representative

Chuck Schaefer, ESH Manager

Marcel Romero, Procurement Liaison Engineer

Joseph Tuozzolo, Technical Systems Division Director

Sergei Nagaitsev, Technical Director

Approved By:

Christoph Montag, Electron Storage Ring L2 Manager

Doc No. EIC-MSG-SOW-018 Author: George Mahler Effective Date: July 28.2026 Review Frequency: N/A

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

REVISION HISTORY

Revision # Effective Date Summary of Change

00 9/27/2024 Initial Release

01 1/30/2025 Changes made per RFI and FDR feedback

02 2/4/2026 Changes made to the procurement strategy

03 7/28/2026 Revisions to drawing numbers and configuration quantities

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

Table of Contents

LIST OF ACRONYMS

1 SCOPE

1.1 Background

2 APPLICABLE DOCUMENTS

3 REQUIREMENTS

3.1 Contractor and BSA Responsibilities

3.1.1 First Article Magnet

3.1.2 Production Magnets

3.1.3 Technical Performance

3.1.4 Tooling/Fixtures/Test Equipment

3.1.5 Special Tools

3.2 Engineering Design and Manufacturing Requirements

3.2.1 Detailed Design Requirements

3.2.2 Detailed Analysis Requirements

3.3 Project Communication and Management

3.3.1 Progress Communications

3.3.2 Program Plan

3.3.3 Performance Reporting

3.3.4 “Witness” Points

3.3.5 Manufacturing/Inspection/Test Plan

3.4 Design Reviews and Production Review

3.4.1 Preliminary Design Review (PDR)

3.4.2 Final Design Review (FDR)

3.4.3 Manufacturing Readiness Review (MRR)

3.5 Documentation and Data Management

3.5.1 Report/Documentation Format

3.5.2 Engineering Drawing Practices

3.5.3 End Item Documentation Package

3.5.4 Records

3.6 Environment, Safety and Health (ESH)

4 QUALITY ASSURANCE

4.1 Quality System and Facility Access

4.2 Configuration Management

4.3 Responsibility for Subcontractor

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

4.4 Responsibility for Conformance

4.5 Measuring and Test Equipment (M&TE) Calibration

4.6 Inspections and Test Requirements

4.6.1 Test and Inspection

4.6.1.1 Steel Testing Requirements

4.6.1.2 Magnet Testing Requirements

4.6.2 First Article Acceptance

4.7 Repairs

4.8 Failure Reporting, Analysis and Corrective Action

5 DELIVERABLES

6 SCHEDULE

7 VALUE ENGINEERING

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

LIST OF ACRONYMS

ASME American Society of Mechanical Engineers

BNL Brookhaven National Laboratory

BSA Brookhaven Science Associates

DOE Department of Energy

EIC Electron-Ion Collider

ESH Environment, Safety and Health

ESR Electron Storage Ring

FDR Final Design Review

MRP Material Requirements Planning

MRR Manufacturing Readiness Review

M&TE Measuring and Test Equipment

NIST National Institute of Standards and Technology

PDR Preliminary Design Review

QA Quality Assurance

RHIC Relativistic Heavy Ion Collider

SI International System of Units

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

Statement of Work for the ESR D2 Dipole Magnets

1 SCOPE

This Statement of Work (SOW) will be the basis for the procurement of Electron Storage Ring

(ESR) D2 Dipole Magnets to be used at the Electron-Ion Collider (EIC) at Brookhaven National

Laboratory (BNL) managed by Brookhaven Science Associates (BSA). This document outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.

1.1 Background

The Electron-Ion Collider (EIC) is a Nuclear Physics facility being built at the United States (U.S.)

Department of Energy’s (DOE) Brookhaven National Laboratory (BNL). The EIC will create intense beams of relativistic energy electrons and ions in opposing particle storage rings that will be brought into collision in a large experimental detector. This will provide insight into the internal structure of protons and neutrons and the gluelike force that holds them together.

Conventional beam line accelerator magnets will be used to bend and focus high energy and high intensity electron beams in the EIC Electron Storage Ring. The ESR “ring” will be located in the existing Relativistic Heavy Ion Collider (RHIC) tunnel. The ESR will have a beamline circumference of 3,830 meters (2.4 miles).

The ESR will store the polarized electron beam for the EIC particle collisions for hours at various energies, depending on the science program, from 5 GeV to 18 GeV. Therefore, the ESR dipoles will operate at constant field/current. The magnets shall be fabricated with high-quality laminated steel to provide high field quality. For production, there will be a requirement to shuffle the laminations from different heats to provide minimal differences in magnetic field strength from magnet to magnet because they are powered in a single series string.

2 APPLICABLE DOCUMENTS

In the event of a conflict between the Technical Documentation and this SOW, the Contractor shall immediately notify the BSA contract representative who shall in each instance determine which document takes precedence and advise the Contractor accordingly. Failure to notify BSA contract representative of a document conflict shall not relieve the Contractor’s responsibility to ensure full compliance to all requirements.

The following documents and drawings are an integral part of the SOW; the applicable revision level will be the latest that is in effect at the time of award:

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

Document Number Document Title

ASME Y14.100 Engineering Drawing Practices

BNL-QA-101 Brookhaven National Laboratory Supplier Quality Assurance Requirements

EIC-MSG-SPC-009 Technical Specification for the ESR D2 Dipole Magnet

EIC-MSG-SPC-010 Technical Specification for the EIC D1/ D3 and D2 Dipole Magnet Steel

2104M0025 D2 Magnet Assembly with Required Interfaces (STEP Model and

Specification Control Drawing)

2104M0039 12 Turn Coil, Top

2104M0041 D2 Magnet Lamination Specification Control Drawing

2104M0047 12 Turn Coil, Bottom

2104M0050 D2 Trim Coil Specification Control Drawing

2104M0052 D2 Magnet Assembly Interface, 13 Turn

2104M0053 13 Turn Coil, Bottom

2104M0054 13 Turn Coil, Top

2104M0055 D2 Magnet Assembly Interface, 11 Turn

2104M0056 11 Turn Coil, Top

2104M0057 11 Turn Coil, Bottom

2104M0058 D2 Magnet Assembly Interface, 11 to 2 Turn

2104M0059 11 to 2 Turn Coil, Top

2104M0060 11 to 2 Turn Coil, Bottom

2104M0061 D2 Magnet Assembly Interface, 5 to 1 Turn

2104M0062 5 to 1 Turn Coil, Top

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

2104M0063 5 to 1 Turn Coil, Bottom

2104M0084 D2 Magnet Assembly Interface, 21 to 5 Turn

2104M0085 21 to 5 Turn Coil, Top

2104M0086 21 to 5 Turn Coil, Bottom

3 REQUIREMENTS

In accordance with the technical specification, referenced drawings (drawing references includes the model file), and instructions as defined in this SOW, the Contractor shall be responsible for designing, manufacturing, inspecting, testing, and delivering the ESR D2 Dipole Magnets.

The vendor will purchase all steel for D2 magnets totaling 730 tons in one single procurement to allow for proper shuffling of the laminations from different heats, ensuring minimal differences in magnetic field strength from magnet to magnet because they are powered in a single series string.

The steel shall be procured from one heat where possible and be traceable via material certifications that shall be supplied to BSA prior to delivery. BSA shall be notified of intent to use multiple heats prior to purchase of the steel. The steel will be stored under required conditions identified in Technical Specification EIC-MSG-SPC-010.

3.1 Contractor and BSA Responsibilities

The BSA/EIC Engineering group is responsible for the magnetic analysis and core and coil design of the D2 dipole magnet to meet the ESR performance requirements and interfaces. The referenced specification control drawings and technical specification are the result of the magnetic design effort. The Contractor is responsible for the detailed magnet engineering design in accordance with the technical specification and drawings. The Contractor’s magnet design shall be reviewed and approved by the BSA technical representative in accordance with this SOW before proceeding with production of the first article production magnet.

3.1.1 First Article Magnet

The Contractor is responsible for fabricating and assembling one (1) first article magnet (Drawing

2104M0025) that will verify the magnet’s conformance to this SOW, the technical specification, the referenced control drawings, the quality of the Contractor’s design and fabrication methods, and the conformance of the BSA/EIC magnetic design to the ESR performance requirements. The

Contractor shall procure all materials and fabricate a first article magnet that shall be inspected and tested by the Contractor prior to shipping. The steel for the first article needs to be from the same batch and/or ONE heat as outlined per EIC-MSG-SPC-010. BSA shall be notified of intent to use multiple heats prior to purchase of the steel. BSA will inspect, test, and magnetically measure the first article magnet at no cost to the Contractor again, after receiving. After review of

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR passing inspection, test, and measurement results, and approval of the Manufacturing Readiness

Review (MRR) the magnets will be approved for production in writing by the BSA technical representative.

3.1.2 Production Magnets

The Contractor shall fabricate and assemble one hundred ninety-four (194) production magnets that will be inspected and tested by the Contractor prior to shipping. BSA will inspect, test, and magnetically measure the production magnets to verify the quality of each magnet at no cost to the

Contractor again, after receiving. After review of passing inspection, test, and measurement results the magnets will be accepted for installation by the BSA technical representative. The magnets will be installed by BSA. See the table below for the number of magnets per configuration.

Document

Number

Document Title Number of

Magnets

2104M0025 D2 Magnet Assembly with Required Interfaces (STEP Model and Specification Control Drawing) Qty: 176

2104M0052 D2 Magnet Assembly Interface, 13 Turn Qty: 8

2104M0055 D2 Magnet Assembly Interface, 11 Turn Qty: 8

2104M0061 D2 Magnet Assembly Interface, 5 to 1 Turn Qty: 1

2104M0084 D2 Magnet Assembly Interface, 21 to 5 Turn Qty: 1

3.1.3 Technical Performance

In accordance with this SOW, the technical specification, and the drawings, the Contractor shall furnish all equipment, materials, facilities, and labor to perform the work necessary to design, manufacture, test, and ship the ESR Dipole Magnets. The Contractor shall ensure that the resultant design and finished product meets the performance parameters and criteria in the technical specification and drawings.

3.1.4 Tooling/Fixtures/Test Equipment

The Contractor shall be responsible for the design and fabrication of all tools, jigs, fixtures, and test equipment required to meet the requirements of this SOW, the technical specification and the drawings.

3.1.5 Special Tools

After completion of the magnet order, all special tooling developed specifically for the manufacturing, assembly, and/or testing of the magnets shall be carefully stored and maintained for a minimum of three (3) years after contract completion. The BSA technical representative shall be notified in writing prior to disposing of any tooling or equipment required to manufacture, assemble or test the magnet.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

3.2 Engineering Design and Manufacturing Requirements

The Contractor shall provide a complete design package, including but not limited to mechanical drawings for components, assemblies, and fixtures required for manufacturing and assembling the magnets, magnet assembly drawings, design analyses and reports, test plans and reports, inspection plans and report, and quality assurance documentation.

3.2.1 Detailed Design Requirements

The Contractor’s detailed design effort shall include but is not limited to the following considerations:

1. Magnet core structural design to ensure that the laminated magnet cores have proper rigidity to meet the magnet interface drawing tolerance and specification requirements.

2. The magnet core design shall interface with the magnet core supports that securely hold the magnet to the support frame. The magnet core shall meet the tolerance requirements when secured by the support points defined by drawing 2104M0025.

3. The magnet design shall meet the lifting requirements in the technical specification. The

Contractor shall design the lifting frame in accordance with the specification for both the first article and production magnets. A lifting frame shall be provided with the first article and production magnets.

4. The design of the coil support system that supports the coils without stress or deformation and the high voltage isolation requirements shall be in accordance with the magnet specification.

3.2.2 Detailed Analysis Requirements

The Contractor shall perform analyses to ensure the ESR dipole magnets meet the requirements of the specification. Models and results shall be provided electronically in their native ANSYS, which refers to the name of the software or equivalent standard format, as well as in hard copy form to the BSA technical representative. The analyses shall include, but is not limited to:

1. Structural analysis of the magnet assembly, the coil support, cable termination assembly, etc.

with interface to the girder assembly and the lifting requirements.

2. Electromagnetic analysis to determine forces for the magnet design and for proper coil support.

3. Thermal analysis for the coil support.

3.3 Project Communication and Management

3.3.1 Progress Communications

Within two (2) weeks after award of contract, program technical and progress communications

(via Zoom or MS Teams) between the Contractor and BSA shall be held at a mutually scheduled time on a bi-weekly basis. The discussions shall include the Contractor’s progress, technical and

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR contractual questions, presentations of analysis or testing results, in process design reviews, value engineering, troubleshooting, material status, tooling status, resources, and manufacturing issues.

3.3.2 Program Plan

Within three (3) weeks after award of contract, the Contractor shall deliver a detailed program plan which includes a milestone schedule for the first article magnet program. It shall include the magnet design effort, the design validation through design reviews as defined in this SOW, material procurement, fabrication of tooling, fixtures, and magnet components, parts inspection and testing, magnet assembly, inspection, testing and delivery. The program plan shall be sufficient in detail to allow progress monitoring.

3.3.3 Performance Reporting

Throughout the life of the contract, the Contractor shall supply a written report by the fifth of every month to the BSA technical representative clearly detailing progress through the prior month with respect to the program. This shall include milestone charts, detailed progress, open items, problems, recommended solutions, and risk mitigation.

3.3.4 “Witness” Points

BSA reserves the right, after review of the Contractor Manufacturing Plan, to designate selected manufacturing, inspection, and/or test operations as “witness” points. The contractor shall provide the BSA technical representative with ten (10) working days’ notice in advance of such witness points during the manufacturing and test cycle.

3.3.5 Manufacturing/Inspection/Test Plan

The Contractor shall develop a Manufacturing/Inspection/Test Plan which identifies the manufacturing processes required to complete individual magnet assemblies. The plan shall include manufacturing, inspection, and test steps including identification of critical manufacturing operations for parts and subassemblies showing integrated flow into a complete ESR dipole magnet assembly. The Manufacturing/Inspection/Test Plan shall address shop loading (by work center). It shall include a schedule for manufacturing all components, inspection and testing components, assembling the magnets, final acceptance testing, and shipping.

The plan shall address Material Requirements Planning (MRP). The plan shall provide details for purchasing all raw materials, hardware, and other commercial off-the-shelf components. The contractor shall preform all inspections and tests required to assure that the magnets meet the requirements of the technical specification and associated documents. The plan shall provide for material, procured component, and manufactured parts inspection and traveler acceptance documentation which will be part of a completed magnet Quality Assurance (QA) documentation.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

The Manufacturing/Inspection/Test Plan shall include acceptance tests in the technical specification as well as the “Magnet Assembly Inspection Data Sheet” and the “Coil Inspection

Data Sheet”. The plan is required for the first article and production magnets fabrication efforts.

3.4 Design Reviews and Production Review

In addition to the bi-weekly progress communication the Contractor is responsible for holding formal preliminary and final design reviews as defined in this SOW. The reviews shall be at the

Contractor’s site, and the BSA technical representative shall have option to attend in person and/or via Zoom or MS Teams. The reviews provide for formal communication on design progress and design approval. Approval of Contractor designs and processes by the BSA technical representative does not relieve the Contractor’s responsibility to meet the requirements of this

SOW, technical specification, or drawings unless a contract modification is approved by BSA.

3.4.1 Preliminary Design Review (PDR)

The PDR shall be held in accordance with the schedule set forth in section 6 herein, to ensure compliance with this SOW, applicable specifications, and interface control drawings. The PDR meeting and associated PDR report shall include at a minimum the following items to be addressed in detail and supported by preliminary calculations that shall be presented at the PDR for review and approval.

• General information and outline of magnet design progress.

• Detailed design information, including drawings, parts lists, engineering analyses.

• Design concerns, documented requests for deviations from the requirements in this SOW, the technical specification, and the associated drawings.

• Design verification plan and report

• Preliminary Manufacturing/Inspection/Test Plan

• Program Plan and Schedule Update for Completion of Design and Fabrication of the First

Article Magnet.

3.4.1.1 Preliminary Design Review (PDR) Report

The Contractor shall provide, no later than ten (10) working days prior to the scheduled PDR meeting, a draft PDR Report. The contents of this report shall be reviewed at the PDR. The

Contractor PDR report shall reflect the state of the developed design.

3.4.1.2 Preliminary Design Review Meeting

The Contractor shall be responsible for maintaining and submitting the minutes of the PDR and shall also incorporate any agreed-to changes into the final comprehensive PDR Report. The final report shall be submitted within ten (10) working days of the PDR meeting. The PDR report shall be reviewed and approved by the BSA technical representative.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

3.4.2 Final Design Review (FDR)

The FDR shall be held in accordance with the schedule set forth in section 6 herein. The FDR shall ensure compliance with this SOW, applicable specifications, and interface control drawings. The

FDR meeting and associated FDR report shall include at a minimum the items listed on 3.4.2.1 to be addressed in detail and supported by preliminary calculations that shall be presented at the FDR for review and approval.

3.4.2.1 Final Design Review Report

The Contractor shall provide an FDR report that reflects the state of the developed design as it evolved from the PDR. The Contractor shall be responsible to develop the overall design of the

ESR dipole magnets in accordance with the applicable specifications and supporting documents.

The Contractor shall perform the tasks listed below, with the results to be included in the Final

Design Review Report for review and approval in writing by the BSA technical representative.

• General information and outline of magnet design effort.

• Summary of significant design changes since the PDR.

• Detailed design information, including models, drawings, parts lists, and engineering analyses.

• First Article Magnet Production Program plan with schedule through to testing and shipping.

• Production Magnet Manufacturing plan with production rate and schedule.

• Manufacturing/Inspection/Test Plan final for First Article and Production Magnets.

• Program Plan and Schedule Update for Completion of Design and Fabrication of the First

Article Magnet.

3.4.2.2 Final Design Review Meeting

The FDR meeting shall be held in accordance with the schedule set forth in section 6 herein, to ensure compliance with this SOW, technical specification, interface control drawings (and model), and to obtain approval from the BSA technical representative to proceed to the production phase.

The Contractor shall provide, no later than ten (10) working days prior to the scheduled meeting, a draft FDR Report that shall consist of the requirements set forth herein. The findings of the FDR

Report shall be reviewed at the FDR meeting and shall cover all pertinent issues relating to the final detailed design of the ESR D2 dipole magnets.

The Contractor shall be responsible for maintaining and submitting minutes of the FDR meeting and shall also incorporate any agreed-to changes into the final comprehensive FDR Report, both of which are to be submitted to the BSA technical representative within ten (10) working days of the FDR for subsequent review and approval. After written approval of the FDR report by the BSA technical representative, the Contractor shall promptly begin manufacturing the ESR dipole magnets. Upon written approval of the FDR report the design is to be considered “frozen” and no changes are permitted to the design, materials, processes, methods, and tooling, or component-level substitutions, without written approval by BSA technical representative.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

3.4.2.3 Approval to Proceed with First Article Fabrication

The BSA technical representative must approve in writing the Final Design Review Report, including any modifications introduced at the Final Design Review, before the Contractor proceeds with ordering of material and components. The BSA technical representative may approve in writing ordering of long-lead-time materials and components prior to the approval of the Final

Design Review Report to expedite schedule.

3.4.3 Manufacturing Readiness Review (MRR)

After the first article testing by the Contractor and testing and magnetic measurement by BSA, the

Contractor shall hold a manufacturing readiness review for the production quantities. The

Contractor shall provide, no later than ten (10) working days prior to the scheduled meeting, a draft of the final Production Magnet Manufacturing Plan and the Manufacturing/Inspection/Test

Plan for review. The MRR shall include:

• Discussion of lessons learned from manufacturing by the Contractor and opportunities for value engineering improvements or cost savings.

• Inspection, test, and magnetic measurements results provided by BSA.

• Any modifications that may be needed and negotiated to improve the magnet design.

• Updates to the Production Magnet Manufacturing Plan with production rate and schedule.

• Update to the Manufacturing/Inspection/Test Plan final for production Magnets.

3.4.3.1 Manufacturing Readiness Review Report

The Contractor shall be responsible for maintaining and submitting minutes for the MRR meeting and shall also incorporate any agreed-to changes into the final comprehensive MRR Report, both of which are to be submitted to BSA within ten (10) working days after the MRR for subsequent review and approval. After review of passing inspection, test, and measurement results, and approval of the Manufacturing Readiness Review (MRR) the magnets will be approved for production in writing by the BSA technical representative and the Contractor shall promptly begin the process for manufacturing the ESR dipole magnets.

3.5 Documentation and Data Management

3.5.1 Report/Documentation Format

• All reports submitted shall include an introduction, body of the documents, and a conclusion. Large documents shall include a table of contents. For calculations, equations shall be shown with values defined for each variable so the analysis can be reviewed.

Diagrams shall be included for clarity, and labels shall be consistent with design drawings for specific items.

• All documentation provided by the Contractor shall be in English.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

• The Contractor shall provide an electronic copy of all documentation required by this

SOW. Contractor manufacturing drawing Computer-Aided Design files of all components and assemblies shall be in a mutually agreed format.

3.5.2 Engineering Drawing Practices

All Contractor-generated engineering drawings shall be in accordance with ASME Y14.100, Engineering Drawing Practices. All dimensions and tolerances shall be U.S. Customary units with metric (SI) units as a secondary notation.

3.5.3 End Item Documentation Package

The Contractor shall provide the end item documentation package in electronic form for each magnet shipped. The End Item documentation package shall consist of all documentation identified in this SOW and include the following:

• Manufacturing Travelers in accordance with the Manufacturing/Inspection/Test Plan.

• Final Inspection and Test Reports in accordance with the Manufacturing/Inspection/Test

Plan.

• For a complete list of documents required for the End-Item Documentation Package, reference BNL-QA-101 Clause 4.10.

3.5.4 Records

The Contractor shall retain objective evidence, including records, of the inspections and tests performed in the course of manufacturing, testing, inspecting, preserving, packaging, and preparation for shipment of the magnets. These records shall be made available to BSA for review upon request. These records shall be maintained for a minimum of three (3) years, unless otherwise specified in the procurement documentation, after the completion of the Contract.

3.6 Environment, Safety and Health (ESH)

The Contractor shall design and build the ESR D2 dipole magnets in accordance with ESH requirements in the specification, codes, standards, and other documents listed in Section 2 of the technical specification.

4 QUALITY ASSURANCE

4.1 Quality System and Facility Access

The Contractor shall maintain and apply an effective and documented quality assurance system for the design, manufacture, and testing of the dipole magnets. The system shall meet the requirements of the ISO-9001 Standard, “Quality Management Systems Requirements”, and shall provide the processes to ensure that each component produced for acceptance conforms to the

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR requirements of this document and the applicable technical documentation. The Contractor shall supply the necessary documentation to demonstrate this compliance. Post-award surveys may be required and shall be supported by the Contractor. In addition, BSA representatives shall have access to the Contractor’s facility during agreed-upon fabrication, inspection and testing processes.

The Contractor shall provide ten (10) working days’ notice in advance of the agreed-upon witness points.

As set forth in BSA Form BNL-QA-101, “Brookhaven National Laboratory Supplier Quality

Assurance Requirements,” as amended herein, forms a part of this SOW. Specifically, this includes the following sections: 1, 2, 3, 3.1, 3.1.2, 3.1.4, 3.2 to 3.8, 3.11, 3.21, 3.22, 4.0, 4.1, 4.2, 4.3, 4.4, 4.4.1, 4.4.2, 4.4.3, 4.5, 4.6, 4.7, 4.7.1, 4.7.3, 4.10, 4.10.1, 4.10.2, 4.10.3, 4.10.4, 4.11, 4.13, 4.14, 4.16, 4.18, 4.18.2, 4.18.3, 4.19, 4.21, 4.34 and 4.39. With each Component delivered, the

Contractor shall supply BSA a Certificate of Conformance, in accordance with section 4.16 of

BNL-QA-101.

BNL-QA-101 Section 2.0 Definitions use the terms Buyer and Seller. In the context of this SOW

Buyer is referred to as “BSA” and Seller is referred to as “Contractor”.

BNL-QA-101 Clause 4.5 “Witness Points” is amended to require the Contractor to provide BSA with ten (10) working days’ notice in advance of reaching such witness points during the manufacturing and test cycle of each item.

4.2 Configuration Management

The Contractor shall establish and maintain a configuration control system to ensure that all magnets are of the proper configuration, and that all approved configuration changes are incorporated at the specified effectivity points. Records verifying the configuration of each item shall be maintained for a minimum of three (3) years from the date of acceptance of the dipole magnets by BSA. The Contractor shall immediately notify the BSA technical representative of any significant changes (those that may affect form, fit, function, reliability, safety, or interchangeability) in design, fabrication methods, material or processing. For changes in configuration, a request for change approval shall be submitted to the BSA technical representative for consideration. Changes in configuration may be made by the Contractor only with the written approval of the BSA technical and representative and a contract modification.

4.3 Responsibility for Subcontractor

It is the responsibility of the Contractor to flow down and impose applicable technical and quality assurance requirements upon their contractors and subcontractors. BSA reserves the right to disapprove, in writing, any contractor or subcontractor.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

4.4 Responsibility for Conformance

The Contractor is responsible to provide magnets which conform to the requirements of the

Contract regardless of any assessments, surveillances, inspections and/or tests by BSA or its representatives at either the Contractor’s or BSA’s facility. The Contractor is responsible for notifying the BSA technical representative of any recalls or alerts associated with this Contract this notification is in addition to the notifications required in the BNL-QA-101.

4.5 Measuring and Test Equipment (M&TE) Calibration

The Contractor shall calibrate any M&TE used in the fulfillment of the Contract requirements against certified standards that are traceable to national standards such as the National Institute of

Standards and Technology (NIST), or an international standard, or a physical constant. The

Contractor shall notify the BSA technical representative of any condition found during the calibration, servicing or repair of measuring and test equipment that can affect the end item requirements.

4.6 Inspections and Test Requirements

Unless otherwise specified in the Contract, the Contractor shall be responsible for the performance of all inspections and tests required in the technical specification. Except as otherwise specified in the Contract, the Contractor shall utilize facilities suitable for the performance of the inspection and test requirements, specified herein, which are acceptable to BSA. BSA reserves the right to re-perform any of the inspections and/or tests set forth in this document or technical specification when deemed necessary to assure that the ESR D2 dipole magnets conform to prescribed requirements at no cost to the Contractor. The BSA technical representative shall have the option to witness all tests defined in this SOW or the technical specification.

4.6.1 Test and Inspection

4.6.1.1 Steel Testing Requirements

The steel, supplied by the Contractor, will be sample tested by BSA. The Contractor shall supply a sample set for each steel heat. The dimensions of the sample pieces, quantity required, and other requirements are provided in specification EIC-MSG-SPC-010. Samples of material distributed throughout each heat of material shall be provided to BSA for magnetic property testing.

One week prior to each shipment, the Contractor shall notify the BSA technical representative and supply all records of inspection, test results and specimens for the tests as required in specification

EIC-MSG-SPC-010. The BSA technical representative will communicate to the Contractor the disposition of the supplied steel coil delivery. Steel shall not be used for production until testing is completed and approved by the BSA technical representative. Contractor shall supply material certification prior to shipment, indicating contract and identification of the specification to which the material conforms. Contractor shall be responsible for certification validity.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

4.6.1.2 Magnet Testing Requirements

The magnets shall be inspected and tested by the Contractor at the Contractor’s facility or the

Contractor’s subcontractor’s facility prior to shipment using the Manufacturing/Inspection/Test

Plan defined in this SOW. The BSA technical representative retains the right to witness all inspections and tests. Final acceptance of the magnets shall take place following the successful completion of final testing and magnetic measurement at BNL. The time period for the final testing at BNL shall be within 90 days after receipt of the magnets at BNL.

4.6.2 First Article Acceptance

BSA’s acceptance of the first article magnets is required prior to the production run. The first article shall be identified as such, including the contract, part number, and part name.

After BSA technical representative acceptance of first article magnets, all remaining magnets required by the Contract shall be produced by the Contractor and the Contractor’s suppliers using the same design, materials, processes, methods, and tooling that were used to manufacture the approved first article. Any changes must have prior written approval from the BSA technical representative.

4.7 Repairs

If failures occur or repairs are required to a magnet assembly or any component during manufacturing or testing that affects form, fit, function, reliability, safety, or interchangeability the process shall stop and the BSA technical representative shall be immediately notified. The BSA technical representative at their discretion may ask for retesting, additional review and evaluation to determine root causes, analyses of failure modes(s) or proposals for repair. Proposals for repair shall include adequate information for evaluating the repair, testing the effectiveness of the repair, and methods to prevent damage to the existing work. No proposed repair shall be initiated without approval of the BSA technical representative. No repair shall be considered successfully accomplished without inspection and written approval by the BSA technical representative. All repairs shall be at the expense of the Contractor. In addition, the Contractor shall not use nonconforming materials via use-as-is disposition without written approval from the BSA technical representative.

4.8 Failure Reporting, Analysis and Corrective Action

The Contractor shall maintain a failure reporting, analysis, and corrective action system which shall, as a minimum, evaluate, analyze, and correct failures occurring during end-item acceptance testing and inspection. The results of all failure evaluations and analyses shall be documented and available for review by the BSA technical representative.

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

5 DELIVERABLES

The Contractor shall supply the following:

Item Deliverable Due

BSA

Approval

1 Technical and Progress Reporting 2 weeks after award of contract/ Bi-weekly thereafter No

2 Program Plan 3 weeks after award of contract Yes

3 Performance reports 5th of each month after contract award No

Draft Production Magnet Manufacturing

Plan 10 working days prior to MRR Yes

5 Draft Manufacturing/Inspection/Test Plan 10 working days prior to MRR Yes

6 Draft Preliminary Design Review Report 10 working days prior to PDR Yes

7 Final Preliminary Design Review Report 10 working days after PDR Yes

8 Manufacturing/Inspection/Test Plan 10 working days prior to FDR Yes

9 Draft Final Design Review Report 10 working days prior to FDR Yes

10 Final Design Review Report 10 working days after FDR Yes

Steel Sample Set w/ associated documentation

1 week prior to each steel coil shipment Yes

1st Article Magnet w/associated documentation As set forth in contract Yes

13 Manufacturing Readiness Review Report 10 working days after MRR Yes

Delivery of ESR dipole Magnet w/associated documentation

Quantities and Delivery Dates as set forth in contract Yes

6 SCHEDULE

The following schedule is for planning purposes only. Schedule requirements set forth in the contract will take precedence.

Milestone Calendar weeks after award

Preliminary Design Review 5

Final Design Review 10

Delivery BNL: 1st Article Magnet w/associate documentation 44

Approval for production/Manufacturing Readiness Review 54

Delivery of ESR production dipole magnets to BNL 104

This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR

7 VALUE ENGINEERING

The Contractor is encouraged to make recommendations for changes that might lead to improvements in performance, reliability, quality, safety, or reduction in cost. Simplicity in design and manufacture and an improvement in the performance and reliability beyond the requirements of this SOW and the technical specification are objectives which shall be considered in the dipole magnet design. Where it appears a substantial improvement in simplicity of design, performance, reliability will result from the use of materials, parts, and processes other than those specified, it is desirable that their use be investigated. When investigations point to advantages that may be realized, the recommendation for change shall be presented to the BSA technical representative for review.

LIST OF ACRONYMS
1 SCOPE
1.1 Background
2 APPLICABLE DOCUMENTS
3 REQUIREMENTS
3.1 Contractor and BSA Responsibilities
3.1.1 First Article Magnet
3.1.2 Production Magnets
3.1.3 Technical Performance
3.1.4 Tooling/Fixtures/Test Equipment
3.1.5 Special Tools
3.2 Engineering Design and Manufacturing Requirements
3.2.1 Detailed Design Requirements
3.2.2 Detailed Analysis Requirements
3.3 Project Communication and Management
3.3.1 Progress Communications
3.3.2 Program Plan
3.3.3 Performance Reporting
3.3.4 “Witness” Points
3.3.5 Manufacturing/Inspection/Test Plan
3.4 Design Reviews and Production Review
3.4.1 Preliminary Design Review (PDR)
3.4.1.1 Preliminary Design Review (PDR) Report
3.4.1.2 Preliminary Design Review Meeting
3.4.2 Final Design Review (FDR)
3.4.2.1 Final Design Review Report
3.4.2.2 Final Design Review Meeting
3.4.2.3 Approval to Proceed with First Article Fabrication
3.4.3 Manufacturing Readiness Review (MRR)
3.4.3.1 Manufacturing Readiness Review Report
3.5 Documentation and Data Management
3.5.1 Report/Documentation Format
3.5.2 Engineering Drawing Practices
3.5.3 End Item Documentation Package
3.5.4 Records

3.6 Environment, Safety and Health (ESH)

4 QUALITY ASSURANCE
4.1 Quality System and Facility Access
4.2 Configuration Management
4.3 Responsibility for Subcontractor
4.4 Responsibility for Conformance
4.5 Measuring and Test Equipment (M&TE) Calibration
4.6 Inspections and Test Requirements
4.6.1 Test and Inspection
4.6.1.1 Steel Testing Requirements
4.6.1.2 Magnet Testing Requirements

4.6.2 First Article Acceptance

4.7 Repairs
4.8 Failure Reporting, Analysis and Corrective Action
5 DELIVERABLES
6 SCHEDULE
7 VALUE ENGINEERING

File details come from the government source that posted it. Updated .