Section_C_Div_01_-_Div_51.docx

DOCX document 2 MB Posted

Attached to
Pasture Canyon Dam Construction Federal contract opportunity
Solicitation number
A15PS00794
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

Section C Div 01 - Div 51

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pasture Canyon Dam Modifications

Bureau of Indian Affairs Hopi Indian Reservation - Arizona

DESIGNER

U.S. Department of the Interior FINAL SPECIFICATIONS Bureau of Reclamation Technical Service Center Denver, Colorado FEBRUARY 2015

DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00Mobilization and Preparatory Work
01 11 00Summary of Work
01 14 10Use of Site
01 29 00The HOPI Tribe Business License Application - Construction Projects
01 29 10The HOPI Tribe Employment Rights
01 29 20The HOPI Tribe -Environmental Protection Office - Environmental Protection

Plan

01 32 10Construction Program
01 33 00Submittals
01 35 10Safety Data Sheets
01 35 20Safety and Health
01 35 22First Aid
01 35 30Contractor’s Onsite Safety Personnel
01 42 10Reference Standards
01 46 00Quality Procedures
01 46 20Testing Laboratory Services
01 51 00Temporary Utilities
01 55 00Vehicular Access and Parking
01 55 20Traffic Control
01 56 10Protection of Existing Installations
01 56 15Protection of Existing Utilities
01 56 20Existing Fences
01 56 32Temporary Safety Fence
01 57 20Environmental Controls
01 57 30Water Pollution Control
01 57 50Tree and Plant Protection
01 57 60Protected Species
01 57 90Preservation of Historical and Archeological Data
01 60 00Product Requirements
01 71 20Surveying
01 74 00Cleaning and Waste Management
01 78 30Project Record Documents

DIVISION 02 - EXISTING CONDITIONS

02 21 30Benchmarks
02 41 07Removal and Disposal of Existing Features
02 82 20Removal and Disposal of Asbestos Containing Materials

Table of Contents 00 0110 - 1

DIVISION 03 - CONCRETE

03 11 10Concrete Forming
03 15 12PVC Waterstop
03 15 17Hydrophilic Strip Waterstop
03 20 00Concrete Reinforcement
03 30 00Cast-In-Place Concrete
03 37 52Slush Grout
03 37 55Dental Concrete
03 62 20Nonshrink Grout for Equipment and Metalwork

DIVISION 05 - METALS

05 50 00 Metal Fabrications

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

DIVISION 08 - OPENINGS

08 31 20 Access Hatches

DIVISION 09 - FINISHES

09 96 20Coatings
09 96 23Graffiti Resistant Coatings for Concrete and Masonry

DIVISION 26 - ELECTRICAL

26 05 02Basic Electrical Materials and Methods
26 05 10Conductors and Cables
26 05 20Grounding and Bonding
26 05 30Electrical Conduit
26 35 23Manual Transfer Switch-Generator Power Inlet

DIVISION 31 - EARTHWORK

31 02 10Water for Dust Abatement
31 03 10Diversion and Care of Flows During Construction
31 03 23Cofferdam
31 03 33Removal of Water from Excavation
31 11 00Clearing and Grubbing
31 14 10Stripping
31 23 02Compacting Earth Materials

00 0110 - 2

31 23 11Earthwork for Structures
31 23 18Excavation of Reservoir Sediments
31 23 21Excavation of Existing Embankment and Spillway
31 23 23Excavation from Borrow
31 23 39Disposal of Excavated Materials
31 23 70Controlled Low Strength Material (CLSM)
31 24 10Embankment Construction, General
31 24 11Zone 1, Embankment
31 24 12Zone 2, Fine Filter
31 24 13Zone 3, Coarse Filter
31 24 14Zone 4, Crest and Downstream Face Protection
31 25 10Erosion Control
31 32 32Geotextile
31 37 00Riprap and Bedding

DIVISION 33 - UTILITIES

33 11 13 HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe 33 46 36 Toe Drains

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 21 10Trashracks
35 21 82Steel Pipe
35 22 15Cast-Iron Hydraulic Slide Gate
35 23 12Valves and Equipment

DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS

51 00 00Information Available to Offerors
51 00 10Flood Routing and Hydraulic Issue Evaluation
51 00 20Reservoir Level Data
5102 82Analytic Test Results

DIVISION 52 - DRAWINGS

5200 00 Drawings

DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS

5310 00Geologic Investigation
53 10 15Cone Penetrometer Tests
53 20 00Records of Geologic and Subsurface Investigations

00 0110 - 3

END OF CONTENTS

00 0110 - 4

SECTION 01 10 00

MOBILIZATION AND PREPARATORY WORK

PART 1GENERAL
1.01MEASUREMENT AND PAYMENT
A.Mobilization and Preparatory Work:
1.Payment: Lump sum price offered in schedule A.
a.General. Payment for the Mobilization and Preparatory Work line item of the

schedule will be made as reflected herein. To the extent that this line item exceeds 5.0 percent of the total contract pricing, payment will be made as reflected in B.5.

B.Progress payments for mobilization and preparatory work will be made as follows:
1.The Government will reimburse the Contractor for the total amount of premiums

paid for performance and payment bonds as required by the Performance and Payment Bond Requirements clause of this contract and for any insurance required as payable by the Government under this contract.

2. Except as provided in B.1, progress payments for mobilization and preparatory work shall not be considered a separate division of work for the purposes of progress payments and shall be subject to retainage before payment of the total amount for this contract line item.

3. When progress payments totaling 5 percent of the total original contract amount have been made by the Government for all other work accomplished under the contract, the Government shall pay the Contractor 50 percent of the mobilization and preparatory work contract line item amount or 5.5 percent of the total original contract amount, (whichever is lower), exclusive of any payment already made to the Contractor for performance and payment bond premiums and specified insurance under B.1.

4. When progress payments totaling 10 percent of the total original contract amount have been made by the Government for all other work accomplished under the contract and upon approval of the baseline schedule, the balance of the amount for the mobilization and preparatory work contract line item or 11 percent of the total original contract amount, (whichever is lower), shall be paid to the Contractor.

5. If the contract amount for mobilization and preparatory work exceeds the total of the payments allowed under B.3 and B.4 above, the balance shall be paid when the contract work is substantially complete as determined by the Contracting Officer.

Mobilization and Preparatory Work 01 1000 - 1

C. Termination for default: Should the Contractor be terminated for default as provided by the Default clause of this contract:

1. All facilities, plant, and equipment on the site shall be subject to the Government's right to take possession of and utilize such items for the purpose of completing the work;

2. The Contractor shall provide evidence of encumbrances, liens, or other security interests, to the Contracting Officer; and

3. Any encumbrance, lien, or other security interest on such facilities, plant, or equipment shall be subordinated to the Government's rights under the Default clause of this contract to utilize all facilities, plant, and equipment to complete the work under the contract.

PART 2PRODUCTS
2.01MOBILIZATION AND PREPARATORY WORK OPERATIONS
A.The Contractor shall provide operations including, but not limited to, those necessary for:
1.Movement of personnel, equipment, supplies, and incidentals to the project site;
2.The establishment of offices, buildings, plants and other facilities, at the site,

(excludes temporary buildings - e.g. storage sheds, shops, offices) and utilities listed in the Temporary Utilities section of this contract;

3.Payment of premiums for project bonds and insurance and;
4.Other work and operations to be performed or incidental costs incurred for the

initiation of meaningful work at the site where the contract does not otherwise provide for payment.

5.Approved RSN 01 32 10-1, Baseline Schedule.
B.Facilities and equipment covered by mobilization work:
1.Facilities, plant, and equipment which are established at, or brought to, the site shall

be deemed to be subject to the provisions of this paragraph unless the Contracting Officer specifically provides other written authorization for a particular item or items.

2. The Contractor shall be solely responsible for the adequacy, efficiency, use, protection, maintenance, repair, and preservation of facilities, plant, and equipment on site.

3. Facilities, plant, and equipment covered by this paragraph shall not be dismantled or removed from the site prior to completion of the work under the contract without written authorization of the Contracting Officer.

01 1000 - 2

PART 3 EXECUTION

Not Used.

END OF SECTION

01 1000 - 3

SECTION 01 11 00

SUMMARY OF WORK

PART 1GENERAL
1.1LOCATION
A.Work is located at Pasture Canyon Dam approximately 1.5 miles NE of Tuba City, in

Coconino County, Arizona.

1.2PRINCIPAL COMPONENTS OF WORK
A.Excavation of existing spillway, outlet works, and downstream slope of embankment.
B.Construction of concrete overtopping protection at current spillway location.
C.Removal and disposal of existing outlet works structures.
D.Removal and disposal of existing siphon.
E.Foundation improvement beneath new outlet works structures.
F.Construction of new outlet works structures.
G.Furnishment and installation of Zone 2 fine filter material, Zone 3 coarse filter material

along downstream slope of embankment. Cover filter with Zone 1 embankment.

H. Furnishment and installation of toe drain pipe surrounded by Zone 2 fine filter and Zone 3 coarse filter at downstream toe of embankment, and Zone 2 fine filter material in trench below new toe drain. Cover toe drain with Zone 1 embankment.

I. Replacement of low-voltage electrical distribution equipment associated with the outlet works slide gate hydraulic power unit and gate controls, (HPU), including combination starters, conduit system, grounding system, conductors and cables, and associated electrical equipment.

J.Excavation of reservoir sediment may be awarded.
1.3SPECIFICATIONS REQUIREMENTS
A.Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B.Imperative statements in these specifications are Contractor requirements, unless

otherwise stated.

Summary of Work 01 1100 - 1

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

1.4DEFINITIONS
A.When the specifications use a word or term defined in the Federal Acquisition

Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

1.5ACRONYMS
A.The following acronyms apply to specifications Divisions 1 through 53:
1.CO: Contracting Officer.
2.COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Summary of Work 01 1100 - 2

SECTION 01 14 10

USE OF SITE

PART 1GENERAL
1.1MEASUREMENT AND PAYMENT
A.Cost:
1.Include in prices offered in price schedules A for other items of work.
1.2REFERENCE STANDARDS
A.Bureau of Reclamation (USBR)
1.Cleaning ManualInspection and Cleaning Manual for

Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:

http://www.usbr.gov/mussels/prevention

1.3SUBMITTALS
A.Submit the following in accordance with Section 01 33 00 - Submittals.
B.RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1.For each Contractor use site on Tribal land.
a.Show use location and extent of impact. Uses include but are not limited

to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2)Parking areas, temporary roads, and haul routes.
3)Utilities including air, power, and water lines, fire hydrants, and

compressor station.

4)First-aid and medical facilities.
5)Temporary fences.
b.Describe methods to preserve, protect, and repair if damaged, vegetation,

(such as trees, shrubs, and grass), and other landscape features on or adjacent to the jobsite, which are not to be removed and which do not

Use of Site 01 1410 - 1 interfere with the work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

e. Describe methods for preventing spread of invasive species in the project area during construction.

1) Herbicides, application techniques, and applicator will be approved by the Hopi Environmental Protection Office.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

1.4PROJECT CONDITIONS
A.Tribal land, as shown on drawings, may be used for required construction facilities.
B.When private land is used for construction facilities, or other construction purposes, make

necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of construction facilities on Tribal land will be subject to approval of the COR.

D. Do not interfere with work of other contractors or the Tribe in vicinity, or with reservations made by the Tribe for use of such land.

E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by the COR.

PART 2PRODUCTS
2.01COR FIELD OFFICE
A.Provide temporary field office:
1.Weather tight with lighting, electrical outlets, heating and cooling equipment.
2.No less than 120 square feet of clear floor space.
a.Include locking closet or storage.
3.Heating and Cooling:
a.Minimum temperature: 65 degrees Fahrenheit.
b.Maximum temperature: 75 degrees Fahrenheit.

01 1410 - 2

4. Power: Provide electrical power for lighting, computer operation, fax machine, refrigerator, water cooler, and at least 3 additional duplex outlets.

5.Furnishings:
a.One plan table sized for full size drawings.
b.One, two-drawer filing cabinet.
c.No less than 6 chairs.
6.Approval required by COR prior to ordering.
PART 3EXECUTION
3.1CLEANING
A.Construction Equipment:
1.Before bringing on site, clean construction equipment to remove dirt, vegetation,

and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.

3. COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment onsite.

4. Contractor to obtain approval from COR on removal and prevention plans for possible invasive species within the project area.

3.2RESTORATION
A.Restore Contractor use areas to pre-construction condition.
B.Restore temporary construction roads to original contours and make impassable to

vehicular traffic when no longer required.

C. After completion of work, regrade and scarify Tribal land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

01 1410 - 3

SECTION 01 29 00

THE HOPI TRIBE BUSINESS LICENSE APPLICATION

CONSTRUCTION PROJECTS

PART 1GENERAL
1.1MEASUREMENT AND PAYMENT
A.Cost:
1.Include in prices offered in price schedule A for other items of work.
1.2SUBMITTALS
A.Submit the following in accordance with Section 01 33 00 - Submittals.
B.RSN 01 29 00-1, Copy of Prime Contractors Hopi Business License for Construction

Projects.

C. RSN 01 29 00-2, Copy of All Subcontractors Hopi Business License for Construction Projects.

1.3CONTRACTOR RESPONSIBILITY
A.The Contractor shall be responsible for complying with The Hopi Tribe’s procedure for

obtaining a business license including payment of applicable fees and compliance with applicable Hopi Tribal Employment Rights and Hopi Environmental Protection requirements for the license.

1. Obtain current information regarding applicable fees and contacts from the Hopi Tribe Office of Revenue Commission, P.O. Box 123, Kykotsmovi, AZ 86039, or by telephone: 928-734-3172.

B. The Contractor shall ensure that each Subcontractor obtains appropriate business license in connection with the work.

C. Hopi Tribe Business License applies to work being performed within the boundaries of the Hopi Reservation.

1.4FEE
A.The Hopi Tribe Business License Fee for Construction Projects is based on contract

amount for Prime and Subs. The following table lists the fees as of January 1, 2015.

The Hopi Tribe Business License Application - Construction Projects 01 2900 - 1

Contract AmountFee
Less than $99,999.00$200.00
$100,000.00- $399,999.00$300.00
$400,000.00- $649,999.00$400.00
$650,000.00 and higher$500.00

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

The Hopi Tribe Business License Application - Construction Projects 01 2900 - 2

SECTION 01 29 10

THE HOPI TRIBE EMPLOYMENT RIGHTS

PART 1GENERAL
1.1MEASUREMENT AND PAYMENT
A.Hopi Tribe Employment Rights; (TERO):
1.Payment: Lump sum price offered in price schedule A, B, C, D, and E.
a.Payment for The Hopi Tribe Employment Rights fees will be made at

appropriate percentage of total contract amount shown below.

b. Price shall include only the amount to be paid to the Hopi Tribe for the fee and shall be due prior to commencement of work.

1.2SUBMITTALS
A.Submit the following in accordance with Section 01 33 00 - Submittals.
B.RSN 01 29 10-1, Proof of Payment for Tribal Employment Rights Fees to the Hopi Tribe

Prior to Commencement of Work.

C.RSN 01 29 10-2, Prime Contractor - Tribal Employment Rights Compliance Plan.
D.RSN 01 29 10-3, Subcontractor - Tribal Employment Rights Compliance Plan.
1.3CONTRACTOR COMPLIANCE AND RESPONSIBILITY
A.In addition to the requirements of the clauses entitled “Indian Preference - Department of

the Interior” and “Indian Preference Program - Department of the Interior,” the Contractor shall comply with the Hopi Labor Code.

B. As part of the business licensing process the Contractor is required to submit a compliance plan to the Hopi Tribal Employments Rights Office indicating arrangements to fulfill the requirements of the Hopi Labor Code.

1. Contractor shall be responsible for contacting the Office of Revenue Commission and complying with Hopi Environmental Protection requirements to obtain the license.

2. Contractor shall ensure that each Subcontractor provides an acceptable compliance plan to the Tribe in connection with the work.

3. Contractor shall obtain current information regarding the Hopi Labor Code and licensing contacts from the Hopi Tribal Employment Rights Office, P.O. Box 123, Kykotsmovi, AZ 86039, or by telephone: 928-734-3162.

The Hopi Tribe Employment Rights 01 2910 - 1

C. Contractor shall also be responsible for paying, to the appropriate authorities, all applicable Tribal Employment Rights Ordinance (TERO) fees and taxes.

1. As of January 1, 2015, the employment rights fee was 1/2 of 1 percent, (0.5 percent) of the total contract price, (excluding amounts bid for tribal fees or employment fees).

a. This fee is separate from and in addition to the fees required for The Hopi Tribe Business License Fee for Construction Projects discussed in Section 01 29 00 - The Hopi Tribe Business License Application - Construction Projects.

b. Copies of the Hopi Labor Code and other information on current fees which are applicable to this contract can be obtained from the Hopi Tribal Employment Rights Office, P.O. Box 123, Kykotsmovi, AZ 86039, or by telephone: 928-734-3162.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

The Hopi Tribe Employment Rights 01 2910 - 2

SECTION 01 29 20

THE HOPI TRIBE ENVIRONMENTAL PROTECTION OFFICE -

ENVIRONMENTAL PROTECTION PLAN

PART 1GENERAL
1.1MEASUREMENT AND PAYMENT
A.Cost:
1.Include in prices offered in price schedule A for other items of work.
1.2SUBMITTALS
A.Submit the following in accordance with Section 01 33 00 - Submittals.
B.RSN 01 29 20-1, Environmental Protection Plan for Approval.
C.RSN 01 29 20-2, Amended Environmental Protection Plan for Approval.
1.3CONTRACTOR RESPONSIBILITY
A.Contractor shall develop and submit an Environmental Protection Plan (EPP) to the Hopi

Tribe’s Environmental Protection Office as a condition of obtaining a business license.

B. Contractor shall ensure that each Subcontractor obtains appropriate business license and amends the EPP as necessary in connection with the work.

C. The requirement for a Hopi Tribe Business License process and EPP applies to work being performed within the boundaries of the Hopi Reservation.

D. The Contractor shall obtain current information the Hopi Tribe Environmental Protection Office, P.O. Box 123, Kykotsmovi, AZ 86039, or by telephone: 928-734-3632.

E. The Contractor may obtain a copy of the Environmental Assessment (EA) for the project from Reclamation.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

The Hopi Tribe Environmental Protection Office - Environmental Protection Plan 01 2920 - 1

The Hopi Tribe Environmental Protection Office - Environmental Protection Plan 01 2920 - 2

SECTION 01 32 10

CONSTRUCTION PROGRAM

PART 1GENERAL
1.1MEASUREMENT AND PAYMENT
A.Costs:
1.Developing Baseline Schedule: Include in lump sum price offered in price

schedule A for mobilization and preparatory work.

2. Updating and Using Construction Program: Include as an element of Contractor’s overhead.

1.2REFERENCE STANDARDS
A.Associated General Contractors of America (AGC)
1.AGC ManualConstruction Planning and Scheduling

Manual, 2004

1.3DEFINITIONS
A.Schedule: The Critical Path Method (CPM) of planning and scheduling a construction

project where activities are arranged based on activity relationships and network calculations determine when activities can be performed and the critical path of the project.

B. Project Calendar: Cross reference of numerical work days with calendar days. The project calendar serves as the basis for the day/date conversion and assigns work days and non-workdays.

C. Resources: Equipment, labor or crews, materials, subcontractors, fabricators, manufacturers, and consultants.

D. Out of Sequence Work: An activity that starts before its predecessor activities are completed.

1.4SUBMITTALS
A.Submit the following in accordance with Section 01 33 00 - Submittals.
1.Furnish database files in format compatible with Microsoft Project or Primavera

P6 Project Manager.

2. Furnish schedule and database files on CD-ROM disc.

Construction Program 01 3210 - 1

3. Upon request, provide information and data used to develop and maintain the Construction Program to the CO.

B.RSN 01 32 10-1, Baseline Schedule:
1.Include:
a.Bar chart for project or bar charts for each sub network.
b.Construction Program database with activity and milestone data.
c.Definition of workday calendars.
C.RSN 01 32 10-2, Updated Schedule:
1.Include:
a.Bar chart for project or bar charts for each sub network.
b.Construction Program database with updated activity and milestone data.
c.Definition of workday calendars.
d.Narrative report specifically stating status of project in terms of total float.
1)If negative float exists, cite specific actions and conditions which

caused the "behind schedule" condition and provide proposed course of action to complete the project within the specified delivery time.

2) List of Contractor-initiated changes to current schedule stating reason for action taken and unresolved issues relating to the Construction Program. Government reserves the right to reject Contractor-initiated changes to current schedule which negatively impact Government action which was initiated on the basis of current schedule.

1.5SCHEDULES AND TIME IMPACT ANALYSIS
A.Develop, maintain, and use approved Construction Program to plan, monitor, and

evaluate, and report accomplishment of work.

B. Failure to include any element of the work will not release Contractor from completing all required work under the contract.

C.Construction Program:
1.Prepare detailed activity network for accomplishing required work.
2.Prepare schedule based on required sequence and interdependence of activities.
3.Include work of subcontractors, Government interfaces, and contract milestones.
4.Include contract title, contract number, and Contractors’ name on each sheet.

01 3210 - 2

5. Define construction activities to a level of detail resulting in their durations being no greater than 25 workdays.

6.Adjust Construction Program for seasonal weather conditions.
7.Use durations in units of whole workdays.
D.Baseline Schedule:
1.Represents Contractor’s as-planned approach to accomplishing the work. Do not

include actual start dates, percent completes, or actual finish dates.

2.Include planned start and completion dates for features of work.
E.Updated Schedule:
1.Enter actual progress.
F.If, in the opinion of the CO, the Contractor falls behind the approved schedule,

Contractor shall take steps necessary to improve progress, including those that may be required by the CO.

1. The CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting officer deems necessary to demonstrate how the approved rate of progress will be regained.

2. Costs for actions required to improve progress will be the responsibility of the Contractor.

G.Contract Modification or Delay:
1.Submit a time impact evaluation within 14 days of contract modification or delay,

showing effects of modification or delay on the progress schedule if a time extension is being requested.

2. Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed the contract milestone dates.

H. Float or slack is not for the exclusive use by or benefit of either the Government or Contractor.

1.6FAILURE TO COMPLY
A.Failure to comply with the requirements of this Section shall be grounds for a

determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the specified time.

01 3210 - 3

B. CO may terminate the Contractor’s right to proceed with the work, or separable part of it, in accordance with default terms of this contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 3210 - 4

SECTION 01 33 00

SUBMITTALS

PART 1GENERAL
1.1MEASUREMENT AND PAYMENT
A.Cost:
1.Include in prices offered in price schedules A, B, C, D, and E for other items of

work.

1.2REFERENCE STANDARDS
A.American Society of Mechanical Engineers (ASME)
1.ASME Y14.1-12Decimal-inch Drawing Sheet Size and

Format

B.National Institute of Building Sciences (NIBS)
1.NIBS NCS-11United States National CAD Standards,

Version 5

1.3DEFINITIONS
A.Days: Calendar days.
B.Required Submittal Number (RSN): Identifies items to be submitted together as a

complete submittal.

C.Submittal Types, as listed in Table 01 33 00A - List of Submittals:
1.A - Action:
a.Government will respond as to adequacy of submittal.
b.Action submittals are considered to be “shop drawings” within terms of

clause at FAR 52.236-21, Specifications and Drawings for Construction.

2.I - Informational:
a.Government will acknowledge receipt of these submittals.
b.Government may reject an Informational submittal when the submittal

does not comply with the contract. Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.

Submittals 01 3300 - 1

c. Informational submittals are considered to be “shop drawings” within terms of clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.

1.4SUBMITTAL REQUIREMENTS
A.In case of conflict between requirements of this section and requirements included

elsewhere in these specifications, requirements included elsewhere take precedence.

B.General:
1.Prepare in English.
2.Label with contract number and title, and RSN.
3.Measurement units: US Customary Units.
C.Drawings:
1.Minimum identification in title block:
a.Contract number and title.
b.Contractors’ or suppliers’ title and drawing number.
c.Date.
2.Reserve 3- by 3-inch space next to title block for review stamps.
3.Size: D size (22 inches by 34 inches) as defined by ASME Y14.1.
4.Final Drawings:
a.Computer drafted drawings:
1)In accordance with NIBS NCS.
2)Government will supply electronic AutoCAD format template.
b.Show as-built changes, including revision dates, made during installation.
c.Drawing prepared with drafting equipment, when allowed: Lettering shall

be neat.

D.Product Data:
1.Mark manufacturer's data for commercial products or equipment, such as catalog

cut sheets.

a.Identify manufacturer's name, type, model, size, and characteristics.
b.Illustrate that product or equipment meets requirements of specifications.
c.Mark items to be furnished in a manner that will photocopy (no

highlighter).

d. Strike through items that do not apply.

01 3300 - 2

E.Certifications:
1.Certifications by a registered professional: Signed and sealed by registered

professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

F.Manuals:
1.Copies:
a.Printed copies: Bound and indexed.
b.Electronic copies: Adobe pdf on CD or DVD discs.
1)Bookmark longer files to assist in navigating file.
2.Contents:
a.Parts identification lists, lists of special tools, and accessories.
b.Schematics and wiring diagrams.
c.Detailed instructions for installing, operating, lubricating, and maintaining

equipment.

d. As-built drawings, photographs, and test records or reports if required by the specifications.

G.Samples and Color Selection Submittals:
1.Label with complete manufacturer's product and color identification.
2.Include type and quantity of materials specified in the referenced section in each

“set” of samples.

3.Samples: Representative of product to be installed.
4.Color chips: Sample paint chips. Ink color reproductions are not acceptable.
5.Label each sample, sample kit, set of color chips, or color chart with contract

number and title.

6.The Government will select architectural color and pattern after product approval.
H.Test Reports:
1.Typed, 8 1/2 by 11-inch sheets.
2.Certified.
3.Submit multi-page reports in bound folder or three ring binders.

01 3300 - 3

1.5SUBMITTALS PROCEDURES
A.Submit only checked submittals. Submittals without evidence of Contractor's approval

will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.

D.Include the following information in transmittal letters:
1.Contract number and title.
2.RSN for each attached submittal.
3.Responsible code.
4.Number of sets for each RSN.
5.Identify submittal as initial or resubmittal.
E.Resubmittal of submittals not approved:
1.Mark changes such that they are readily identifiable and show revision date.
2.Describe reasons for significant changes in transmittal letter.
3.Resubmit returned submittals within 28 days after receiving the comments, unless

otherwise directed.

4.Requirements for initial submittals apply to resubmittals.
F.More than one RSN may be submitted under a transmittal letter, provided the responsible

code is the same.

1.6REVIEW OF SUBMITTALS
A.Time Required:
1.Submittal review will require 28 days for review of each submittal or resubmittal,

unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

01 3300 - 4

B.Time in Excess of Specified:
1.CO may extend contract completion date to allow additional time for completing

work affected by excess review time.

a. Time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if Contractor fails to make complete approval submittals in sequence and within time periods specified.

3.Adjustment for delay will be made only to the extent that:
a.Approval was required under the contract, and
b.Requests for approval were properly and timely submitted and were

approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C.Return of Submittals:
1.Action Submittals: One set of submittals required for approval will be returned

either approved, approved subject to identified changes, or not approved.

a.Revise and resubmit for approval submittals not approved.
b.Do not change designs without approval of the CO after approval

drawings, documentation, and technical data have been approved.

2. Informational Submittals: Government will acknowledge Informational submittals.

a. Informational submittals will not be returned when they comply with specifications.

b. Informational submittals that do not comply with specifications may be returned for resubmittal or additional information may be requested.

01 3300 - 5

1.7TRANSMITTAL
A.Addresses for codes listed in Table 01 33 00A - List of Submittals:
1.CO: Bureau of Indian Affairs, Western Region Office, Contracting Officer -

Pasture Canyon Dam Modification, 2600 N. Central Avenue, Phoenix, AZ 85004.

*The Contractor shall provide the Contracting Officer a copy of all correspondence and related documents, pertaining to this contract that is addressed to a representative of the Government. This does not pertain to the Submittal Requirements as they are outlined herein.

2. COR: Bureau of Indian Affairs, Western Region Office, Contracting Officer Representative - Pasture Canyon Dam Modification, 2600 N. Central Avenue, Phoenix, AZ 85004.

B. Send original transmittal letter with appropriate number of sets to COR at office listed, as shown in “Responsible Code” column in Table 01 33 00A - List of Submittals.

C. Submittals required by the specifications, but not listed in Table 01 33 00A - List of Submittals:

1.Submit in accordance with this section.
2.Submit to COR, unless otherwise specified.
D.Electronic Submittals:
1.An internet based electronic submittal and review system will be available for this

project. The use of this system will be organized by the Government at no cost to the Contractor and will be the preferred method for receiving and reviewing submittals.

2. If the Contractor elects to utilize the electronic submittal and review system for a submittal required by the Specifications, the Contractor does not need to perform Sub-Article B of this Section, and will submit set electronically for Article1.05.C.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 3300 - 6

Table 01 33 00A. - List of Submittals

* Submittal types: A - Action, I - Informational ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.

RSN

01 1410-1

01 2900-1

01 2900-2

01 2910-1

01 2910-2

01 2910-3

01 2920-1

01 2920-2

Clause or Section Title

The Hopi Tribe Business License Application- Construction Projects The Hopi Tribe Business License Application- Construction Projects The Hopi Tribe Employment Rights

The Hopi Tribe Employment Rights The Hopi Tribe Employment Rights The Hopi Tribe Environmental Protection Office - Environmental Protection Plan

The Hopi Tribe Environmental Protection Office - Environmental Protection Plan

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Land Use andAt least 28 daysACOR
Landscapebefore use of
Rehabilitation PlanGovernment land
Copy of PrimeAt least 14 daysACOR
Contractors Hopiprior to onsite work

Business License for Construction Projects

Copy of AllAt least 14 daysACOR
Subcontractors Hopiprior to onsite work

Business License for Construction Projects

Proof of Payment forAt least 14 daysACOR
Tribal Employmentprior to onsite work

Rights Fees to the Hopi Tribe Prior to the Commencement of Work

Prime Contractor -At least 14 daysACOR
Tribal Employmentprior to onsite work

Rights Compliance Plan

Subcontractor -At least 14 daysACOR
Tribal Employmentprior to onsite work

Rights Compliance Plan

EnvironmentalAt least 14 daysACOR
Protection Plan forprior to onsite work

Approval

AmendedAt least 14 daysACOR
Environmentalprior to onsite work

Protection Plan for Approval

No. of sets to be sent to: **

CO COR

0 3

0 2

0 2

0 2

0 2

0 2

0 2

0 2

01 3300 - 7

01 32 10-1

01 32 10-2

01 35 10-1

01 35 10-2

01 35 20-1

01 35 20-2

01 35 22-1

01 35 22-2 01 35 30-1

Clause or Section Title Construction Program

Construction Program

Safety Data Sheets

Safety and Health

Safety and Health

First Aid

Contractor’s Onsite Safety Personnel

Respon-

Due date orType
Submittals requiredsible
delivery time*

code Baseline Schedule: Within 21 days after A COR receipt of Notice to

1. Blackline prints Proceed

2. Reports

3. Data on CD or DVD ( 1 copy per submittal set) Updated Schedule: With monthly A COR requests for progress

1. Blackline prints payments

2. Reports

3. Data on CD or DVD (1 copy per submittal set)

Complete LHM andAt least 14 daysICOR
SDSbefore jobsite

delivery of hazardous material

Updated LHM andAt least 14 daysICOR
SDSbefore jobsite

delivery of hazardous material not previously listed Safety Program Submitted and A COR accepted before commencing work.

See section 3 of

RSHS

Weekly AccidentFirst day of eachICO
Summary Reportmonth. See

paragraph 3 of

RSHS

Medical FacilitiesSubmitted andACO
Planapproved before

start of operations

CertificatePrior to employmentACO
ResumePrior to employmentICOR

No. of sets to be sent to: **

CO COR

0 6

0 4

0 3

0 3

0 3

0 3

0 3

04
03

01 3300 - 8

01 35 30-2

01 46 20-1

01 55 20-1

01 57 20-1

01 57 30-1

01 57 30-2

01 57 50-1

01 57 90-1

01 71 20-1

01 71 20-2

01 71 20-3

01 71 20-4 or Section Title Contractor’s Onsite Safety Personnel Testing Laboratory Services

Traffic Control

Environmental Controls

Water Pollution Control Water Pollution Control

Tree and Plant Protection

Preservation of Historical and Archeological Data Surveying

Respon-

Due date orType
Submittals requiredsible
delivery time*

code

Safety InspectionFrequencyICOR
Reportsdetermined prior to

start of construction

Testing LaboratorySubmitted andACOR
Services Planapproved 14 days

before start of operations Traffic Control Plan At least 36 days A COR before affecting public traffic.

Copy of ApplicableAt least 28 daysACOR
Air Quality Permitbefore start of onsite

construction work

Pollution PreventionAt least 28 daysACOR
Planbefore start of onsite

construction work

Spill Prevention,At least 28 daysACOR
Control, andbefore start of onsite
Countermeasureconstruction work

(SPCC) Plan Protection Plan At least 28 days A COR before starting on site construction work

Alternate Use AreaAt least 28 daysACOR
or Borrow Areabefore starting on

site construction work Surveying Plan At least 36 days A COR before beginning survey work Resume At least 36 days A COR before beginning survey work; At Least 36 days before personnel change

Accuracy CheckAt least 14 daysICOR
Resultsbefore beginning

survey work

Completed andAccompanyingACOR
Reduced Surveyprogress payment
Notesrequests

No. of sets to be sent to: **

CO COR

0 3

0 4

0 4

0 3

0 4

0 4

0 4

0 4

0 4

0 4

0 4

0 4

01 3300 - 9

01 7120-5

01 7120-6

01 7120-7

01 7400-1

01 7400-2

01 7400-3

01 7400-4

01 7830-1

02 2130-1

02 4107-1

02 8220-1

02 8220-2 or Section

Cleaning and Waste Management Cleaning and Waste Management Cleaning and Waste Management

Cleaning and Waste Management Project Record Documents Benchmarks

Removal and Disposal of Existing Features Removal and Disposal of Asbestos Containing Materials Removal and Disposal of Asbestos Containing Materials

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Original FieldAccompanyingICOR
Survey Booksprogress payment

requests

Quantity SurveyAccompanyingICOR
Notes andprogress payment
Computationsrequests
Workday’s SurveyAccompanyingICOR
Notesprogress payment

requests

Waste ProductionWithin 7 days ofICOR
and Disposalwaste disposal

Records

Hazardous WastesWithin 7 days ofICOR
Manifesthazardous waste

disposal

EnvironmentalAt least 28 daysICOR
Consultant Resumebefore beginning

environmental assessment

Environmental SiteWithin 14 days ofICOR
Assessmentcompletion of work
Final As-builtWithin 14 days ofICOR
Drawingscompletion of work
Survey Reports andWithin 14 days ofICOR
Drawingscompletion of work
Removal andAt least 28 daysACOR
Disposal of Existingbefore starting
Features Planrelated site

construction work

Asbestos AbatementAt least 28 daysICOR
Contractor andbefore starting
Subcontractorsrelated site
Historyconstruction work
Asbestos Resumes,At least 28 daysACOR
Certificates, andbefore starting
Qualificationsrelated site

construction work

No. of sets to be sent to: **

CO COR

0 4

0 4

0 4

0 3

0 3

0 3

0 3

0 4

0 4

0 4

0 3

0 3

01 3300 - 10

02 8220-3

02 8220-4

03 1512-1

03 1512-2

03 1512-3

03 1512-4

03 1517-1

03 1517-2

03 1517-3

03 2000-1 or Section Title Removal and Disposal of Asbestos Containing Materials Removal and Disposal of Asbestos Containing Materials

PVC

Waterstop

Hydrophilic Strip Waterstop

Hydrophilic Strip Waterstop

Hydrophilic Strip Waterstop

Concrete Reinforcement

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Asbestos HazardAt least 28 daysACOR
Abatement Planbefore starting

related site construction work

Asbestos WasteWithin 7 days ofICOR
Shipment Recorddisposal

and Certificate of Disposal

Purchase Orders At least 28 days A COR before starting related site construction work Samples At least 28 days A COR before starting related site construction work Certifications At least 28 days I COR before starting related site construction work Instructions At least 28 days I COR before starting related site construction work Product Data At least 28 days A COR before starting related site construction work Certification At least 28 days I COR before starting related site construction work Instructions At least 28 days I COR before starting related site construction work

ReinforcementAt least 28 daysACOR
Diagrams and Listsbefore starting

related site construction work

No. of sets to be sent to: **

CO COR

0 3

0 4

0 4

0 2

0 2

0 2

0 4

0 2

0 2

0 6

01 3300 - 11

03 3000-1

03 3000-2

03 3000-3

03 3000-4

03 3752-1

03 3755-1

07 9200-1

07 9200-2

07 9200-3

09 9620-1

09 9620-2

09 9620-3

Clause or Section Title Cast-In-Place Concrete

Slush Grout

Dental

Joint Sealants

Coatings

Coatings

Coatings

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Material ApprovalAt least 28 daysACOR
Databefore starting on

site construction work

Concrete PlacementAt least 28 daysACOR
Drawingsbefore starting on

site construction work

Concrete PlacementAt least 28 daysICOR
Schedulebefore starting on

site construction work Certifications At least 28 days I COR before starting related site construction Mix Design At least 28 days A COR before starting on site construction work Mix Design At least 28 days A COR before starting on site construction work

Approval Data,At least 28 daysACOR
Samples, and Colorbefore starting
Cardrelated construction

work Certification At least 28 days I COR before starting related construction work Instructions At least 28 days I COR before starting related construction work Approval Data At least 28 days A COR prior to application Final Approval Data At least 28 days I COR prior to application Documentation At least 28 days I COR prior to application

No. of sets to be sent to: **

CO COR

0 6

0 6

0 6

0 6

0 6

0 6

0 4

0 4

0 4

0 4

0 4

0 4

01 3300 - 12

09 9623-1

09 9623-2

09 9623-3

26 05 10-1

26 3523-1

31 03 10-1

31 03 23-1

31 03 33-1

31 2318-1

31 2318-2 or Section Title Graffiti Resistant Coatings for Concrete and Masonry Graffiti Resistant Coatings for Concrete and Masonry Graffiti Resistant Coatings for Concrete and Masonry Conductors and Cables Manual Transfer Switch- Generator Power Inlet Diversion and Care of Flows During Construction

Cofferdam

Removal of Water From Excavation

Excavation of Reservoir Sediments

Excavation of Reservoir Sediments

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Approval DataAt least 28 daysACOR

prior to application

Final Approval Data At least 28 days I COR

Documentation At least 28 days I COR

Approval Data Within 60 days after A COR Notice to proceed Approval Data Within 60 days after A COR Notice to proceed

Water Control andAt least 40 daysACOR
Removal Planprior to beginning

any work on the diversion and care of the stream Approval Plans Within 60 days after A COR Notice to proceed

Removal of WaterAt least 28 daysACOR
Planbefore starting on

site construction work

Excavation ofAt least 28 daysACOR
Reservoir Sedimentsbefore starting on
Plansite construction

work

Access forWithin 7 days ofACOR
Subsequentnotice of subsequent
Excavation ofexcavation

Reservoir Sediments #1 Plan

No. of sets to be sent to: **

CO COR

0 4

0 4

0 4

0 6

0 6

0 6

0 6

0 6

0 8

0 8

01 3300 - 13

31 2318-3

31 2318-4

31 2321-1

31 2370-1

31 2410-1

31 2412-1

31 2413-1

31 2414-1

31 2510-1

31 2510-2 or Section Title Excavation of Reservoir Sediments

Excavation of Reservoir Sediments

Excavation of Existing Embankment and Spillway Controlled Low Strength Material

(CLSM)

Embankment Construction, General

Zone 2, Fine Filter

Zone 3, Coarse Filter

Zone 4, Crest and Downstream Face Protection Erosion

Erosion

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Access forWithin 7 days ofACOR
Subsequentnotice of subsequent
Excavation ofexcavation

Reservoir Sediments #2 Plan

Access forWithin 7 days ofACOR
Subsequentnotice of subsequent
Excavation ofexcavation

Reservoir Sediments #3 Plan Excavation Plan At least 28 days A COR before starting on site construction work Approval Data At least 28 days A COR before starting on site construction work

EmbankmentAt least 40 daysACOR
Construction Planprior to beginning

any work on the diversion and care of the stream

Certification andAt least 40 daysACOR
Laboratory Testprior to beginning
Resultsany work on the

embankment

Approval Data andAt least 40 daysACOR
Test Resultsprior to beginning

any work on the embankment

Approval Data andAt least 40 daysACOR
Test Resultsprior to beginning

any work on the embankment

Silt FenceAt least 28 daysACOR
Certificationsbefore starting on

site construction work Straw Certification At least 28 days A COR before starting on site construction work

No. of sets to be sent to: **

CO COR

0 8

0 8

0 6

0 6

0 6

0 6

0 6

0 6

0 4

0 4

01 3300 - 14

313232-1

313232-2

313232-3

313700-1

31 3700-2

33 1113-1

33 1113-2 or Section

Geotextile

Riprap and Bedding

Riprap and Bedding

HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Manufacture’sAt least 28 daysACOR
Certificationbefore starting

related on site construction work Samples At least 28 days I COR before starting related on site construction work Protection Method At least 28 days I COR before starting related on site construction work

Riprap MaterialsAt least 28 daysACOR
Data and Testbefore starting
Resultsrelated construction

work

Bedding MaterialsAt least 28 daysACOR
Databefore starting

related construction work

HDPE Pipe forAt least 28 daysACOR
Outlet Works Shopbefore starting
Drawings, Workrelated on site
Plans, and Fusionconstruction work.

Procedures

HDPE Pipe for AirAt least 28 daysACOR
Vent, Drainage, andbefore starting
Hydraulic Linesrelated on site
Shop Drawings,construction work

Work Plans, and Fusion Procedures

No. of sets to be sent to: **

CO COR

0 4

0 2

0 4

0 4

0 4

0 6

0 6

01 3300 - 15

33 1113-3

33 1113-4

33 1113-5

33 1113-6

33 1113-7 or Section Title HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe HDPE Pipes for Outlet Works, Air Vent, Drainage, Hydraulic Lines, and Irrigation Turnout Pipe

Respon-

Due date orType
Submittals requiredsible
delivery time*code
HDPE Pipe forAt least 28 daysACOR
Irrigation Turnoutbefore starting
Pipe Shop Drawings,related on site
Work Plans, andconstruction work

Fusion Procedures

HDPE Pipe forAt least 28 daysACOR
Outlet Worksbefore starting
Certificationrelated on site

construction work

HDPE Pipe for AirAt least 28 daysACOR
Vent, Drainage, andbefore starting
Hydraulic Linesrelated on site
Certificationconstruction work
HDPE Pipe forAt least 28 daysACOR
Irrigation Turnoutbefore starting
Pipe Certificationrelated on site

construction work

Final InspectionWithin 14 days afterICOR
Videovideo is completed

No. of sets to be sent to: **

CO COR

0 6

0 4

0 4

0 4

0 4

01 3300 - 16

334636-1

334636-2

334636 -3

33 4636-4

33 4636-5

33 4636-6

35 2182-1

35 2182-2

35 2182-3

35 2215-1

35 2215-2

35 2312-1

352312 -2 or Section

Toe Drains

Steel Pipe

Cast-Iron Hydraulic Slide Gate Cast-Iron Hydraulic Slide Gate Valves and Equipment

Valves and Equipment

Respon-

Due date orType
Submittals requiredsible
delivery time*code
Approval DataAt least 28 daysACOR

before starting related on site construction work Certifications At least 28 days A COR before starting related on site construction work Samples At least 28 days A COR before starting related on site construction work Survey Reports Within 14 days after I COR0 construction is completed

PreliminaryWithin 14 days afterACOR