This Statement of Work (SOW) details a project for road rehabilitation in the Concow area of Plumas National Forest, severely impacted by wildfires in 2018 and 2020. The United States Department of Agriculture (USDA) Forest Service requires a contractor to furnish, haul, and spread 12,300 cubic yards of ¾" Forest Service Class D aggregate base rock across four specific forest service roads: FS Road 23N02 (3,600 cubic yards), FS Road 23N06 (1,500 cubic yards), FS Road 23N22Y (3,800 cubic yards), and FS Road 22N04 (3,400 cubic yards).

The project's technical requirements specify that the aggregate must consist of crushed rock with flat and elongated particles, with no more than 10% larger than a 1:3 ratio. The contractor must provide delivery vehicles capable of operating on narrow, steep, mountainous roads and have an on-site representative to coordinate delivery and spread the aggregate. The road maintenance will be completed by a Forest Service crew that will water, grade, and roll the aggregate after spreading. The entire project must be completed within 60 days after the Notice to Proceed (NTP), and the solicitation is set aside 100% for small business entities under NAICS code 212321 (Construction Sand and Gravel Mining).

View the file

Other files for this federal contract opportunity

Other files attached to Plumas NF Concow Disaster Aggregate Base, newest first.
File Type Posted
A11_QAmemo1-127EAS25R0003_17Jul2025.pdf PDF
A10_127EAS25R0003-Att4-SCAWD2015-5605.pdf PDF
A10_127EAS25R0003-Att5-ExperienceQuestionnaire.docx DOCX document
A10_127EAS25R0003-Att3-LocationsMap.pdf PDF
A10_0-RFP-127EAS25R0003.pdf PDF
A10_127EAS25R0003-Att1-FillableSOI.xlsx XLSX spreadsheet
A10_127EAS25R0003-Att6-KTRKeyPersonnel.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

7.0 Contractor’s Key Personnel

Tables…………………………………………………………………………………………………………………………………….4

Project FRRD Concow Resiliency Aggregate Haul and Supply

General Information

1.0 Scope of Work

Furnish, supply, haul and spread 12,300 CUYD of ¾” Forest Service Class D aggregate base to Concow, CA on Forest Service Roads 22N04, 23N06, 23N02 and 23N22Y

2.0 Background

The Concow area was almost mostly destroyed in the 2018 Camp Fire, and some parts were then reburned in the 2020 North Fire Complex. The roads in this area are experiencing a great deal of erosion and surface material loss during winter storms. The goal of this project is to repair the Forest Roads in the area and create erosion resilient road system in this burned area.

Contractor Requirements

3.0 Technical Requirements / Tasks

The contractor shall furnish all equipment, labor, supervision, and incidentals necessary to furnish, haul, deliver and spread 12,300 cubic yards of ¾” crushed aggregate base rock.

• ¾” Crushed Aggregate – Flat and Elongated particles with no more than 10% larger than a 1:3 ratio.

• See Specification table attached for Forest Service Class D Aggregate Rock.

• The delivery vehicle must be able to operate on narrow, steep, winding mountainous aggregate surface roads and dump/spread their loads under their own power without being pushed, pulled, or towed by US Forest Service vehicles or equipment.

• The contractor must have an on-site representative to coordinate the delivery/spreading of the aggregate base and collect haul tags to be turned in at the end of each day.

• FS Road 23N02 – Deliver/spread 3,600 Cubic yards of Aggregate base.

• FS Road 23N06 – Deliver/spread 1,500 Cubic yards of Aggregate base.

• FS Road 23N22Y – Deliver/spread 3,800 Cubic yards of Aggregate base.

• FS Road 22N04 – Deliver/spread 3,400 Cubic yards of Aggregate base.

Period of Performance: ALL TASKS MUST BE COMPLETED WITHIN 60 DAYS AFTER NOTICE TO PROCEED (NTP)

4.0 Government Furnished

The US Forest Service will have a road maintenance crew at each of the road delivery sites that will be watering, grading and rolling the aggregate once it has been spread on the road surface by the contractor.

7.0 Contractor’s Key Personnel

The contractor must have an on-site representative to coordinate the delivery/spreading of the aggregate base and collect haul tags to be turned in at the end of each day to government representative.

Delete Table 703-2 and replace with the following:

T ab le

-2

T ar ge t V al ue R an ge s f or

S ub ba se a nd

B as e G ra da tio n

Pe rc en t b y M as s P as si ng D es ig na te d Si ev e

(A A

SH

T

O T an d

T

G ra di ng

D es ig na tio n

E (B as e)

(6

(6

(4

4.

7.

(3

T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n

) f ro m th e ta rg et v al ue s..

D (B

(6

(6

(6

(4

4.

7.

(3

C (B

(6

(6

4.

–7 .0

(3

B (S ub ba se

(8

4.

.0 (4

A (S ub ba se

(7

(6

(4

4.

8.

(3

Si ev e Si ze

2½ in ch

1½

3/

1/

3/

N o.

N o.

N o.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
7.0 Contractor’s Key Personnel