A#1 Wandering Prospector_Special Conditions.pdf

PDF 164 KB Posted

Attached to
PKAA, Wandering Prospector Project
Solicitation number
DQ1 PKAA 2026000476 2
Issued by
Colorado

About this file

This is a Special Conditions Amendment No. 1 document issued by the Colorado Department of Natural Resources, Division of Reclamation, Mining & Safety (DRMS) for the Wandering Prospector Project (DQ1 PKAA 2026*0476). The amendment modifies the original bid documents for mine closure and reclamation work involving multiple features (WP-02 through WP-27) requiring various closure methods. The bid submittal deadline has been extended to Wednesday, July 1, 2026, at 4:00 p.m., with bid opening scheduled for Thursday, July 2, 2026. A pre-bid meeting was held prior to this amendment's issuance. The amendment includes a revised Davis-Bacon wage determination sheet dated May 15, 2026, and a Revised Bid Schedule and Revised Feature Work List that substantially modifies specifications for individual work packages.

Key modifications include changes to closure methods for multiple features (WP-02, WP-07, WP-08, WP-24) utilizing Reinforced Polyurethane Foam (PUF) plugs with pressure-treated posts in quantities ranging from twelve to fifteen cubic yards per feature, removal of rockfill requirements for certain features (WP-12), addition of a second rat gate to WP-16, and increased PUF quantities for WP-11. Additional provisions address tree removal specifications, hantavirus mitigation measures, water availability concerns for WP-19, and specification clarifications for crossbars and grating materials. The amendment notes that fourteen features were not visited during the pre-bid meeting but provides driving directions, distances, travel times, feature access information, photographs, maps, and GIS files through a shared Google Drive folder. All original terms and conditions of the Documented Quote remain in effect except as expressly modified by this amendment, with acknowledgment required through submission of the Revised Bid Schedule.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Physical Address: 1313 Sherman Street, Room 215, Denver, CO 80203 P 303.866.3567 F 303.832.8106 Mailing Address: DRMS Room 215, 1001 E 62nd Ave, Denver, CO 80216 https://drms.colorado.gov

Jared S. Polis, Governor | Dan Gibbs, Executive Director | Michael A. Cunningham, Director

Special Conditions

Wandering Prospector Project

Amendment No. 1 DQ1 PKAA 2026*0476

June 16, 2026

Thank you for attending the Pre-Bid Meeting. The following clarifications and amendments should be noted and incorporated into the bid documents:

1. The Bid Submittal Deadline is changed to Wednesday, July 1, 2026, by 4:00 p.m.

The Bid Opening Date is changed to Thursday, July 2, 2026.

2. A current Davis-Bacon wage determination sheet, dated May 15, 2026, is provided with this amendment.

3. The Bid Schedule and Feature Work List attached to the original bid is replaced with the attached Revised Bid Schedule and Revised Feature Work List attachment named “A#1 Revised Bid Schedule and Revised Feature Work List” and includes the following changes:

4. ITEM 3.0: WP-02

The closure method for this feature is changed to a Reinforced Polyurethane Foam (PUF) Plug. The closure shall be constructed in a similar manner to a Concrete Monolithic Plug (SWS 7) except substituting PUF for concrete. The PUF plug will also be reinforced using pressure treated 4”x4”x12’ posts. Prior to installing PUF, four (4) reinforcing posts shall be placed horizontally roughly three (3) feet above the bottom of the opening. Posts shall be parallel and spaced twenty-four (24) inches apart. Both ends of the reinforcing posts shall be keyed into the sides of the shaft, keeping the posts level with each other. Installed posts should resemble floor joists. Trimming posts may be required for proper fitment. Contractor must ensure that the posts are anchored and don’t “float” as the PUF rises and that both ends are fully encased with foam. PUF must be installed slowly to prevent voids from forming below the reinforcing posts. Once the final lift of PUF has solidified, a one (1) inch uniform layer of fill material shall be shoveled over the surface to protect the PUF from sunlight and vandalism. The PUF plug must cure for a minimum of forty-eight (48) hours before finishing the remainder of the backfill. Minor adjustments to this specification may be required in the field to properly construct the closure.

All personnel working in or around the opening must be harnessed and tied off to a secure point. Twelve (12) cubic yards of PUF and four (4), twelve-foot-long (12’) pressure-treated 4x4-inch posts (4”x4”x12’) are required for this closure.

Rockfill or a drainpipe are not required. A standard monument pipe is required.

5. ITEM 3.0: WP-07

(PUF) Plug. Closure shall be constructed as described above for feature WP-02.

Twelve (12) cubic yards of PUF and four (4), twelve-foot-long (12’) pressure-treated 4x4-inch posts (4”x4”x12’) are required for this closure. Rockfill or a drainpipe are not required. A standard monument pipe is required.

6. ITEM 3.0: WP-08

(PUF) Plug. Closure shall be constructed as described above for feature WP-02.

Fifteen (15) cubic yards of PUF and five (5), twelve-foot-long (12’) pressure-

7. ITEM 3.0: WP-11

The quantity of polyurethane foam (PUF) required for this closure is increased to fifteen (15) cubic yards. Contractor must remove debris to open up and expose all sides of the shaft before installing PUF. Shaft cribbing may have double compartments. The dimensions remain the same, but a second bottom form may be required. All personnel working in or around the opening must be harnessed and tied off to a secure point.

8. ITEM 3.0: WP-12

Rockfill is not required for this closure.

9. ITEM 3.0: WP-16

A second slot “rat gate” is added to this closure. The rat gate shall measure 6”x24” and be framed in 2” angle iron. The opening will be placed in the lower section of the grating in a location determined in the field by the Project Manager.

The debris removal is limited to only the eight (8) used car tires just inside of the portal. All other debris will remain inside of the adit. The entire portal area, inside and out, must still be sprayed with a bleach solution to mitigate for hantavirus before any work may start.

10. ITEM 3.0: WP-19

This feature does not have water available nearby and must be packed in.

11. ITEM 3.0: WP-24

(PUF) Plug. Closure shall be constructed as described above for feature WP-02.

Twelve (12) cubic yards of PUF and four (4), twelve-foot-long (12’) pressure-

12. ITEM: 3.0: WP-27

Crossbars for the bat grate shall be ¾” x 3” flat steel bar.

13. Any trees removed during construction activities shall be bucked to six (6) feet or shorter and scattered.

14. Features WP-02, WP-03, WP-04, WP-14, WP-15, WP-16, WP-17, WP-18, WP-19, WP-20, WP-25, WP-27, were not visited during the prebid. A summary of the driving directions, distances, approximate travel times, and feature access is provided with this amendment. Feature photos, maps, and GIS files are also provided. These items can be accessed here:

https://drive.google.com/drive/folders/1BMiM_QXCsLklQ57sPFVRqIClekQbf66M?u sp=sharing

All terms and conditions of the Documented Quote other than as changed by this amendment remain the same.

Receipt and acceptance of this amendment shall be acknowledged on the revised bid schedule where noted and by submitting the Revised Bid Schedule.