A1_-_SOW_Red_Rock_Rooftop_AC_-_AI.docx
DOCX document 21 KB Posted
- Attached to
- AC UNIT RELOCATION & RE-INSTALLATION RM
- Solicitation number
- 140A2326Q0153
About this file
This is a Statement of Work (SOW) for the relocation and installation of a rooftop air conditioning unit at Red Rock Day School in Red Valley, Arizona. The project involves moving an existing ground-mounted Fujitsu split-type air conditioner (Model #AOUG12LZAH1) to the building rooftop to provide dedicated cooling for the IT room. The contractor must supply all labor, materials, tools, equipment, and supervision to complete the work, including pre-installation assessment of the existing unit and rooftop structural capacity, decommissioning of the current equipment with proper refrigerant recovery, rigging and crane services for the rooftop relocation, installation of appropriate mounting systems, reconnection of refrigerant piping, electrical and controls integration with the building management system, modification of ductwork for air distribution, and comprehensive system testing and commissioning.
The solicitation, issued by the Bureau of Indian Education under number 140A2326Q0153, requires a firm fixed-price proposal with a quote acceptance period of 120 days past the closing date of July 13, 2026 at 12:00 P.M. Mountain Daylight Time. The period of performance is 30 calendar days. The contractor must obtain all necessary permits and inspections, maintain OSHA compliance, provide as-built documentation and equipment warranties, and conduct operational training for the owner's personnel. Site visits are scheduled for June 22, 2026 at 1:00 p.m., and questions must be submitted to the Contracting Officer no later than June 24, 2026. All costs associated with federal, state, local, and tribal tax obligations, as well as coordination with the Navajo Nation Tax office, must be incorporated into the firm fixed price.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A3_-__-_DIAR_1452_280-2_Supplement.docx | DOCX document | |
| A5_IA_Form_3000_Material_Approval_Submittal.pdf | ||
| A4_-_IA_-_IEE_Representation_Form.pdf | ||
| Sol_140A2326Q0153.pdf | ||
| A6_-__RFP_Questions_and_Answers_Log.xlsx | XLSX spreadsheet | |
| A2_-__WAGE_RATES.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Red Rock Day School Statement of Work Project Title: Relocation and Installation of Rooftop Air Conditioning Unit for IT Room Cooling Project Overview: The project entails moving an existing ground-mounted air conditioning unit to the building rooftop and installing it to provide dedicated cooling for the IT room. The goal is to achieve reliable, efficient, and continuous climate control tailored to IT equipment requirements.
I. Scope of Work:
The contractor shall supply all necessary labor, materials, tools, equipment, and supervision to complete the following tasks:
1.0 Pre-Installation Assessment
1.1 Assess the current air conditioning unit to determine suitability for relocation
1.2 Review rooftop structural integrity to confirm its capacity for supporting the unit
1.3 Evaluate electrical and mechanical systems for compatibility
1.4 Identify relevant code and permitting obligations
2.0 Decommissioning of Existing Unit Make: Fujitsu, Split Type Air Conditioner Model #: AOUG12LZAH1
2.1 Disconnect electrical, refrigerant, and control connections in accordance with safety standards
2.2 Recover refrigerant per environmental regulations
2.3 Prepare equipment for safe lifting and transport
3.0 Rigging and Relocation
3.1 Arrange crane and rigging services for transfer from ground level to rooftop
3.2 Coordinate lift plan, safety protocols, and access restrictions
3.3 Safeguard building structure and adjacent property during lifting operations
4.0 Rooftop Installation
4.1 Install appropriate mounting system (curb, rails, or vibration isolation pads)
4.2 Secure unit per manufacturer specifications and local code compliance
4.3 Ensure proper clearance for airflow and maintenance accessibility
5.0 Mechanical Connections
5.1 Reconnect or install refrigerant piping with insulation
5.2 Conduct pressure testing and evacuating the system
5.3 Charge system with required refrigerant
6.0 Electrical and Controls Work
6.1 Extend or reroute electrical power to rooftop location
6.2 Install disconnects, conduit, and wiring as necessary
6.3 Integrate controls with IT room thermostat or building management system
7.0 Ductwork / Air Distribution
7.1 Modify or install ductwork to deliver cooling to IT room
7.2 Seal and insulate ducts to optimize energy efficiency
8.0 Testing and Commissioning
8.1 Perform system startup and operational tests
8.2 Verify cooling performance meets IT room specifications
8.3 Check for leaks, ensure proper airflow and electrical safety
8.4 Balance system if required
9.0 Documentation and Training
9.1 Provide comprehensive as-built documentation and updated system diagrams
9.2 Submit equipment manuals and warranty information
9.3 Conduct basic operational training for owner’s personnel
II. Deliverables:
1. Fully installed and functional rooftop air conditioning system
2. Inspection and testing reports
3. As-built drawings and documentation
4. Warranty certificates III. Project Schedule:
1. Project Start Date
2. Substantial Completion
3. Final Completion IV. Roles and Responsibilities:
Contractor:
1. Complete all work in compliance with applicable codes and industry standards
2. Obtain necessary permits and inspections
3. Maintain site safety and adhere to OSHA requirements V. Client:
1. Provide access to the site and IT room
2. Approve submittals and schedules promptly
3. Supply any available documentation related to existing systems VI. Assumptions:
1. Existing units are suitable for reuse
2. Rooftop structure is sufficient or will be reinforced by others
3. Work will occur during standard business hours unless otherwise agreed
4. No hazardous materials (e.g., asbestos) are present VII. Exclusions:
1. Structural roof reinforcement (unless expressly included)
2. Major electrical service upgrades
3. Replacement of air conditioning unit (unless deemed defective)
4. Ongoing maintenance post-installation VIII. Acceptance Criteria:
1. System maintains required temperature for IT room operation
2. Installation adheres to all relevant buildings, electrical, and mechanical codes
3. System passes all inspections and commissioning procedures