This document outlines operations security requirements for a federal contract to produce explosive and inert demolition charges. The statement of work requires the contractor to establish an operations security program to manage and protect sensitive information. This includes developing an operations security plan within 30 days of award, providing initial and annual training to employees, conducting annual self-assessments, and flowing down the same requirements to any subcontractors. The related solicitation is from the Department of the Army Materiel Command Joint Munitions Command to produce items including the M112, M58A4, M68A2, M59A1, and M69A1 demolition charges.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK: OPERATIONS SECURITY (OPSEC) REQUIREMENTS
(a) As defined in Army Regulation (AR) 530-1, Operations Security (OPSEC), sensitive information is information requiring special protection from disclosure that could cause compromise or threat to our national security, an Army organization, activity, family member, DA civilian or DoD contractor.
Critical Information is defined as information important to the successful achievement of U.S. objectives and missions, or which may be of use to an adversary of the United States. It consists of specific facts about friendly capabilities, activities, limitations (includes vulnerabilities), and intentions needed by adversaries for them to plan and act effectively so as to degrade friendly mission accomplishment. All critical information is sensitive, but not all sensitive information is critical.
(b) The Contractor shall not release sensitive information to the general public without prior written approval from the Contracting Officer. All contractor requests to release sensitive information shall be in writing and clearly explain the necessity for release of the information and consequences if approval is not granted. Contractor employees who are U.S.
citizens shall be provided access to sensitive information on a "need to know" basis required to fulfill the terms and conditions of the contract. Foreign National (FN) employees’ access to information will be limited to non-sensitive information. FN access to sensitive information will be approved in writing by the Contracting Officer on a case-by-case basis, and will be strictly limited to the information that the employee must know in order to fulfill the terms and conditions of the contract.
(c) The Contracting Officer will provide the Contractor with a list of known Critical Information (CI) pertinent to contract requirements as soon as possible after contract award. Critical Information shall be used by the Contractor’s appointed OPSEC Manager to prepare an OPSEC Plan.
(d) The Contractor shall be responsible for establishing and maintaining an OPSEC program to adequately manage, protect and control sensitive information that has been provided or generated under the contract. The Contractor shall prepare and submit a written OPSEC Plan to the Contracting Officer for approval IAW DD 1423/DI-MGMT-80934C within 30 calendar days after receipt of the CI information addressed in Paragraph 3 above. The Contracting Officer will coordinate with the
Government OPSEC Officer and advise the Contractor in writing of the approval, conditional approval or disapproval of the plan within 20 days of receipt.
(e) The Contractor shall conduct annual self-assessments of their OPSEC program and submit annual written assessments to the Contracting Officer in the anniversary month of contract award.
OPSEC Assessment checklists and sample assessment responses will be provided in advance by the Government as tools to aid the Contractor in assessing their OPSEC program.
(f) The Contractor shall provide OPSEC training to all employees regarding the safeguarding of sensitive information prior to employees being allowed access to such information, and annually thereafter.
(g) The Contractor shall destroy all sensitive program material at the completion of the contract so as to ensure the information cannot be accessed or utilized for any purpose and notify the Contracting Officer in writing of its destruction.
(h) These same requirements will flow down to all subcontractors working on or provided any sensitive information related to the contract.
(i) Contractor employees with an area of performance within an Army controlled installation, facility or area. "All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable, and annually thereafter.
The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within XX calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:
https//jkodirect.iten.milL"
(j) Contractor employees with an area of performance within Army controlled installation, facility, or area. "Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes."
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-111} and Terrorist Screening Database (TSDB} (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative),or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations."
k. Contractor employees with an area of performance within an Army controlled installation, facility or area. "The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 90 calendar days after contract award. This is an annual training requirement.”
(l) The Contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified Level II OPSEC coordinator per AR 530-1.
(m) Per AR 530-1, Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
(n) Per AR 381-12, Threat Awareness and Reporting Program (TARP), contractor employees must receive mandatory TARP training within 30 days of employment and annually thereafter. Only TARP training by a CI agent is authorized unless the conditions in paragraph 2-4i apply.