A06_Trail_Specifications.doc

DOC document 136 KB Posted

Attached to
GAOA WATER CANYON TRAIL BRIDGE REPLACEMENT Federal contract opportunity
Solicitation number
140L3923R0024
Issued by
Department of the Interior Bureau of Land Management Nevada Region

About this file

This document provides standard specifications for the construction of a water canyon trail bridge. The specifications cover requirements for various aspects of the project such as clearing limits, excavation and embankment, borrow material, surfacing, turnouts and passing areas. Key details include specifications for trail construction including trailbed preparation, drainage features, and retaining structures. Requirements are also provided for clearing vegetation and removing rocks, roots, and hazard trees from the work site. Procedures are outlined for borrow pits and disposal of excess materials. Performance standards address compaction and finish requirements for different elements of the project. Related details involve measurement and payment methods according to itemized work units.

View the file

Other files for this federal contract opportunity

Other files attached to GAOA WATER CANYON TRAIL BRIDGE REPLACEMENT, newest first.
File Type Posted
B09_Q_and_A_0001.docx DOCX document
Sol_140L3923R0024_Amd_0001.pdf PDF
A06__Drawing_Book_Water_Canyon_Trail_Bridges_100_percent.pdf PDF
Sol_140L3923R0024.pdf PDF
B03_DBA_Wages_NV20220005.pdf PDF
A04_100__Statement_of_work_TrailsPortion.docx DOCX document
A06_Water_Canyon_Trail_Bridges_SCR_s.docx DOCX document
A06_Chapter_10__Outdoor_Developed_Areas.pdf PDF
A04_100__Statement_of_work_PedestrianBridges.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STANDARD SPECIFICATIONS FOR CONSTRUCTION OF WATER CANYON TRAIL BRIDGE TRAIL

U.S. Customary Units

Table of Contents

Section 900.

General Requirements

901.

Terms, Format, Abbreviations, and Definitions 902.

Intent of Contract 903.

Control of Work 904.

Control of Materials 905.

Quality Assurance and Quantity of Measurement 906.

Measurement and Payment

907.

Mobilization

908.

Construction Survey, Staking, Flagging and Cleanup

Construction Specifications

910.

Trailway 912.00.

Clearing Limits 912.10.

Clearing and Grubbing

912.20.

Brush Cutting

912.30.

Logging Out

912.40.

Hazard Tree Removal

912.50.

Loose Rock Removal

912.60.

Rock and Root Removal

913.00.

Surfacing

913.80.

Surface Maintenance

916.00.

Turnout and Passing Section 916.10.

Turnout and Passing Section 922.00.

Waterbars

922.30.

Belted Waterbar Section 900

General Specifications

Section 901—Terms, Format, Abbreviations and Definitions

901.01 Meaning of Terms. These specifications are generally written in the imperative mood. In sentences using the imperative mood, the subject “the Contractor,” is implied. Also implied in this language is “shall,” “shall be,” or similar words or phrases. In material specifications, the subject may also be the supplier, fabricator, or manufacturer supplying material, products, or equipment for use on the project.

Wherever “directed,” “required,” “prescribed,” or similar words are used, the “direction,” “requirement,” or “order” of the Contracting Officer is intended. Similarly, wherever “approved,” “acceptable,” suitable,” “satisfactory,” or similar words are used, they mean “approved by,” “acceptable to,” or “satisfactory to” the Contracting Officer.

The word “will” generally pertains to decisions or actions of the Contracting Officer.

Whenever in these specifications, or in other contract documents, the following terms (or pronouns in place of them) are used, the intent and meaning shall be interpreted as follows: reference to a specific standard, test, testing method, or specification shall mean the latest published edition or amendment that is in effect at the solicitation issue date for the public works contracts.

901.02 Specification Format These specifications are divided into Sections.

Sections 900 through 906, 908 and 909 consist of general contract requirements for which no direct payment is made. The requirements contained in Sections 900 through 906 are applicable to all contracts.

Sections 907, 908, 909 and 910 through 989 consist of construction contract requirements for specific items of work. Work under these Sections is paid for directly or indirectly according to Subsection 906.04 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.

Sections 990 through 999 contain the material requirements for Sections 910 through 989. No direct payment is made in Sections 990 through 999. Payment for material is included as part of the work required in Sections 910 through 989.

The first three digits of the pay item number identify the Section under which the work is performed.

901.03 Abbreviations. Whenever these abbreviations are used in the specifications, they represent the following:

(a) Acronyms

AASHTO
American Association Of State Highway And Transportation Officials
ABS
Acrylonitrile-Butadiene-Styrene
AITC
American Institute of Timber Construction
ANSI
American National Standards Institute
AQ
Actual Quantities
APA
American Plywood Association
ASTM
American Society For Testing And Material
AWPA
American Wood Protection Association
CO
Contracting Officer
C.F.
Cubic Feet
C.Y.
Cubic Yard
DQ
Design Quantities
EA
Each
FAR
Federal Acquisition Regulation
g
Grams
HDPE
High-Density Polyethylene
hr
Hour
kg
Kilogram
kN
Kilonewtons
lb
Pound
L.F.
Linear Feet
LS
Lump Sum
LSQ
Lump Sum Quantities
m
Meter
m2
Square Meter
m3
Cubic Meter
mi
Mile
mm
Millimeter
MPa
Megapascals
MSE
Mechanically Stabilized Earth
N
Newton
NBS
National Bureau Of Standards
NCMA
National Concrete Masonry Association
OSHA
Occupational Safety & Health Administration
Pa
Pascal
PE
Polyethylene
PS
Product Standard Issued By The U.S. Department Of Commerce
psi
Pounds Per Square Inch
PVC
Polyvinyl Chloride
S.F.
Square Feet
SQ
Staked Quantities
S.Y.
Square Yard
WCLIB
West Coast Lumber Inspection Bureau
WWPA
Western Wood Products Association
WWPI
Western Wood Preservers Institute

Additional abbreviations may be found in Section 101.03 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03).

(b) Slope notation (vertical: horizontal). For slopes flatter than 1:1, express the slope as the ratio of one unit vertical to a number of units horizontal. For slopes steeper than 1:1, express the slope as the ratio of a number of units vertical to one unit horizontal.

901.04 Definitions The following terms, or pronouns in place of them, are used in these specifications or in other contract documents, the intent and meaning are as follows:

Barriers. A fence or other obstacle that prevents movement or access.

Base Course. The layer or layers of specified material of designed thickness placed on a trailbed to support surfacing.

Batter. A backward and upward slope of the face of a wall.

Berm. The ridge of material formed on the outer edge of the trail that projects higher than the tread.

Borrow. Suitable materials taken from approved sources designated on the plans or on the ground, to be used for embankments and backfilling.

Bridge. A trail structure, including supports, erected over a depression or obstruction such as a body of water, a road, a trail, or a railroad that provides a continuous pathway and that has a deck for carrying traffic or other loads.

Cap Rock. Rock placed in the top or uppermost layer in a constructed rock structure, such as a talus or rubble rock section or rock retaining wall.

Catch Point. The outer limits of a trailway where the excavation and/or embankment intersect with the ground line.

Clearing Limit. The area over and beside the trail that is cleared of trees, limbs, and other obstructions.

Climbing Turn. A reverse in direction of trail grade without a level landing used to change elevation on a steep slope.

Compacted. Consolidation that is obtained by tamping or rolling suitable material until no noticeable displacement of material is observed.

Contracting Officer (CO). An official of the Government with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the CO acting within the limits of their authority as delegated by the CO.

Culvert. Any structure with a bottom, regardless of the fill depth, the depth of invert, or the presence of a horizontal driving surface, or any bottomless (natural channel) structure with footings that does not have wheel loads in direct contact with the top of the structure.

Curb. A border defining the edge of the trail or trail bridge.

Cushion Material. Native or imported material generally placed over rocky section of unsurfaced trail to provide a usable and maintained traveled way.

Designated on the Ground. The location of materials, work areas, and construction items, including lines and grades, marked on the ground with stakes, flagging, tags, or paint.

Drawings. Design sheets or fabrication, erection, or construction details submitted to the Government by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Duff. Organic material overlying rock or mineral soil.

Embankment. A structure of suitable material placed on the prepared ground surface and constructed to the trailbed elevation.

Excess Excavation. Material in the trailway in excess of that needed for construction of designed trailways.

Falsework. Temporary construction work on which a main work is wholly or partly built and supported until the main work is strong enough to support itself.

Ford. A water-level stream crossing constructed to provide a level surface for safe traffic passage.

Full Bench. Trailbed constructed entirely on undisturbed material.

Gabion Basket. Rectangular wire baskets filled with rock used as pervious, semiflexible building blocks for slope and foundation stabilization.

Grade. The vertical distance of ascent or descent of the trail expressed as a percentage of the horizontal distance.

Hazard Tree. An unstable tree that is likely to fall across the trail.

Header Rock. Rock laid with the narrow end towards the face of the wall.

Inslope. Where the trails tread is sloped downward toward the backslope.

Leave Tree. Trees designated to be left or to remain undisturbed after trail construction.

Mineral Soil. Soil or aggregate that is free from organic substances and contains no particles larger than 2 inches at their greatest dimension.

Outslope. Where the trail tread is sloped downward toward the embankment or daylight side of the trailway.

Plans. The contract plans furnished by the Government showing the location, type, dimensions, and details of work.

Retainers. Embedded border of wood or rock used to retain fill and/or surface material.

Sideslope. The natural slope of the ground, usually expressed as a percentage.

Slough. That material from the backslope or the area of the backslope that has raveled onto the trailbed.

Slump. Where the trailbed material has moved downward, causing a dip in the trail grade.

Special Contract Requirements. Specifications that detail the conditions and requirements peculiar to an individual project, including additions and revisions to the standard specifications.

Standard Plans. Detailed plans approved for repetitive use and included as part of the plans.

Standard Specifications. The Standard Specifications for Construction of Trails on Federal Projects approved for general application and repetitive use.

Surfacing. Material placed on top of the trailbed or base course that provides the desired tread.

Suitable Material. Rock that can be accommodated in the trail structure, and soil free of duff with a recognizable granular texture.

Switchback. A reverse in direction of trail grade with a level landing used to change elevation on a steep slope, usually involving special treatment of the approaches, barriers, and drainages.

Trailbed. The finished surface on which base course or surfacing may be constructed. For trails without surfacing the trailbed is the tread.

Trailway. The portion of the trail within the limits of the excavation and embankment.

Tread. The surface portion of the trail upon which traffic moves.

Turnout. A short section of extra trail width to provide for passage of trail users.

Waterbar. A structure used for turning water off the trail, usually made of logs or stones.

Water Courses. Any natural or constructed channel where water naturally flows or will collect and flow during spring runoff, rainstorms, etc.

Additional definitions may be found in Section 101.03 of the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03).

Section 902—Intent of Contract

902.01 Intent of Contract. The intent of the contract is to provide for the construction and completion of the work described. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

Section 904—Control of Materials

904.01 Handling Materials. Transport and handle all materials to preserve their quality and fitness for the work. Stockpile, load, and transport aggregates in a manner that will preserve specified gradation and avoid contamination.

Store materials to assure the preservation of their quality and fitness for the work. Locate stored materials to facilitate their prompt inspection. Sites on Government-administered land that are not already designated may be used for storage purposes and for placing of equipment only when approved in advance by the CO. Restore all storage sites in accordance with requirements SHOWN ON THE PLANS or as otherwise specified. Arrangements for storage on other than designated sites are the responsibility of the contractor.

904.02 Material Sources

(a) Designated Sources. Sources for materials such as, but not limited to, soil, rock, or logs that are not available from trailway excavation or clearing operations will be designated. Sources of local materials designated in the SPECIAL CONTRACT REQUIREMENTS or SHOWN ON THE PLANS are guaranteed by the Government for the quality and quantity of material in the source.

Use all needed suitable material from the source. The designation of a source includes the right to use areas SHOWN ON THE PLANS for the purposes designated (such as plant sites, stockpiles, and haul roads). Operations are restricted to the confines of the area(s) designated.

Comply with the requirements of 30 CFR 56, subparts B and H. When required, re-establish vegetation in disturbed areas according to section 981.

(b) Contractor-Furnished Sources. Furnish material that produces an end product equivalent in performance to that specified.

904.03 Restoration. Shape and grade borrow areas on Government-administered land to make them stable and to minimize future erosion. Dispose of debris resulting from development of material sources by scattering, unless otherwise specified. Do not scatter debris within the clearing limits of trails or within roadsides. Cut off stumps to less than 12 inches above the ground as measured on the uphill side of the stump.

Section 905—Quality Assurance and Quantity Measurement

Description

905.01 This work consists of providing certification that the quality and quantity of construction conform to the plans, specifications, and requirements of the contract.

Construction

905.02 Certification and Measurements

(a) Offsite-Produced Materials. Furnish signed certificates executed by the manufacturer, supplier, or vendor, stipulating that all offsite-produced materials incorporated in the work meet applicable requirements SHOWN ON THE PLANS or stated in the specifications. Furnish a certificate for each commodity or invoice.

(b) Quantity Measurements. Submit quantities to the CO for periodic progress payments, and the CO will compute payments. Quantities are subject to verification.

905.03 Records. Maintain a set of contract plans depicting as-built conditions resulting from approved changes. Maintain the plans in a current condition and indicate changes from the original contract plans in red. Give the plans to the CO upon the completion of the contract work.

Measurement

905.04 Method. There will be no separate measurement for this item.

Payment

905.05 Payment will be considered incidental to other pay items in this contract.

Section 906—Measurement and Payment

906.01 General. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered incidental and included in the payment of the PAY ITEMS in the SCHEDULE OF ITEMS.

When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any PAY ITEM, suffixes will be added to the item number to differentiate between the items.

906.02 Determination of Quantities. The following measurements and calculations are to be used to determine contract quantities for payment:

Make measurements for seeding, geotextiles, and erosion control blankets along slope lines.

For retaining walls, measure by the square foot of front wall face.

Measure structures according to neat lines SHOWN ON THE PLANS or as altered by the CO in writing to fit field conditions. Make measurements along the centerline and parallel to the specified grade or foundation or as SHOWN ON THE PLANS.

Deduct lengths for stairways, turnpike, puncheon, retaining walls, wire baskets, switchbacks, bridges, and bridge approaches from the measurement of excavation in Section 911 unless these items are specified as incidental to excavation in Section 911.

For standard manufactured items, such as fence, wire, plates, rolled shapes, and pipe conduits identified by gage, weight, section dimensions, and the like, such identification shall be considered the nominal weights or dimensions. Manufacturer’s tolerances will be accepted unless controlled by tolerances in the cited specifications.

906.03 Units of Measurement. Payment will be made by units defined and determined according to U.S. Customary measure and by the following:

(a) Cubic Yard. A measurement computed by one of the following methods:

(1) Excavation, embankment, or borrow. The measurement computed by the average-end-area method from measurements made longitudinally along a centerline or other reference line.

(2) Material in place or stockpiled. The measurement computed with the dimensions of the in-place material using average-end-area method or prismodial formula.

(3) Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water-level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

(b) Each (EA). One complete unit, which may consist of one or more parts.

(c) Lump Sum (LS). The quantities that denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

906.04 Methods of Measurement. One of the following methods of measurement for determining final payment is DESIGNATED ON THE SCHEDULE OF ITEMS for each PAY ITEM:

(a) Designed Quantities. These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, and plans. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under the following conditions:

(1) As a result of changes in the work approved by the CO.

(2) As a result of the CO determining that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

(3) As a result of the contractor submitting to the CO a written request showing evidence of errors in the original design that cause a PAY ITEM quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, plans, or other data that show how the designed quantity is believed to be in error.

(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to the construction.

(c) Actual Quantities (AQ). These quantities are determined from measurement of completed work.

(d) Vehicle Quantities. These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

Section 907—Mobilization

Description

907.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the costs associated with obtaining permits, insurance, and bonds. Mobilization is not intended to pay for the costs of materials before they are used on the project site.

Payment

907.02 The accepted quantity, measured as provided in Subsection 906.02, will be paid at the contract price per unit of measurement for the Section 907 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section.

Progress payments for mobilization lump sum will be paid as follows:

(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment. Reimburse for bond premiums before issuing the Notice to Proceed if evidence of payment is received.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance. Pay any unpaid amount for mobilization upon final acceptance of all work items.

Section 908—Construction Staking, Flagging, and Cleanup

Description

908.01 This work consists of establishing any control points needed in addition to existing staking, and removing and disposing of all construction stakes, tags, flagging, and plastic ribbon from the project area.

Construction

908.02 General. The Government will set initial construction stakes or flagging, and control points, and furnish the contractor with all necessary information relating to lines, slopes, and grades. These stakes and flagging constitute the field control.

Furnish and maintain additional stakes, flagging, templates, batter boards, and other materials and supplies necessary for marking and maintaining points and lines established. Do not perform work in the absence of control points. If any construction control points are destroyed, displaced, or erroneous, notify the CO. Uniformly contour alignment and construct grade from control point to control point.

Remove all construction stakes, tags, flagging, and plastic ribbon from the project area within 7 days after the final inspection of all other work on the project. Dispose of all stakes, tags, flagging, and plastic ribbon off Government-administered lands unless otherwise designated.

Measurement

908.03 There will be no separate measurement for this item.

Payment

908.04 Trail staking, flagging, and cleanup will be considered incidental to other pay items in this contract, and additional payment will not be made.

Section 910—Trailways

Section 911 - Trail and Prism

Description

911.00.01 This work consists of constructing trails, restoration of existing trails or obliteration of abandoned trails. The earthwork and associated trail tread and prism work may be covered by one or more of the following subsections:

911.10.

Excavation and Embankment

911.20.

Borrow

911.30.

Existing Trail Restoration

911.40.

Slide Maintenance

911.50.

Slough and Berm Removal

911.60.

Obliteration of Abandoned Trails 911.70.

Retainers Measurement

911.00.02 Measure the section 911 items listed in the bid schedule according to subsection 906.

Payment

911.00.03 The accepted quantities will be paid at the contract price per unit of measurement for the section 911 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 906.04.

911.10 - Excavation and Embankment

Description

911.10.01 This work consists of the excavation and placement of excavated material, regardless of its nature, from within the trailway or from other sources, except for material included under other pay items SHOWN IN THE SCHEDULE OF ITEMS.

Includes excavation, embankment, and backfill construction required to shape and finish the trailbed, ditches, backslopes, fill slopes, drainage dips, trail passing sections, and turnouts. Also includes excavation and embankment work required to construct culverts, trail bridges, shallow stream fords and gully crossings, talus and rubble rock sections, and climbing turns.

Construction

911.10.03 Use and Disposal of Excavated Material. Conserve and use all suitable material for specified work. Conserve excess excavated rock suitable for specified project work and use in place of materials from designated sources.

Remove all duff and debris from within trailway limits and uniformly spread outside the clearing limits, not more than 4 inches in depth (unless otherwise SHOWN ON THE PLANS). Do not obstruct drainage or create piles, berms, or windrows of debris.

Place excess and unsuitable excavation beyond the downslope edge of the trailbed Do not obstruct drainage and spread to a depth not exceeding 4 inches. This includes any material removed in the grubbing operation and deposited in the same area.

Place rocks over 4 inches in greatest dimension not used in construction beyond the hinge point on the downslope side. Place rocks so that the tops are at least 6 inches lower than the trailbed surface. Ensure that no blockage of drainage or creation of a windrow effect occurs.

911.10.04 Trailway Excavation and Embankment. Minor deviations of ± 12 inches in vertical alignment and 36 inches in horizontal alignment with smooth transitions of at least 30 feet on each side of the deviation are acceptable unless otherwise SHOWN ON THE PLANS.

Construct embankments with suitable compacted material. Compact all disturbed soil within the trailbed area.

Remove any rock within or above the backslopes that is unstable. Use or dispose of rock in accordance with Subsection 912.03.

Leave the finished slope in a uniform and roughened condition.

Make necessary adjustments of horizontal or vertical alignment, within the tolerances specified in this subsection, to produce the designed trailway section and balance earthwork. Such adjustments shall not be considered as changes.

911.10.05 Trailbed Finish. Fill holes with suitable material, compact, and cut high points to provide a uniform trailbed finish.

911.10.07 Ditches. Construct ditches to be free of loose rocks, roots, sticks, and other obstructions.

911.20 - Borrow

Description

911.20.01 This work consists of placing select borrow material on the trailbed.

Materials

911.20.02 Requirements. Obtain borrow materials from locations SHOWN ON THE PLANS or DESIGNATED ON THE GROUND. Obtain CO's approval before using borrow from other locations. Suitable material from slough and berm removal may also be used as borrow material. Use suitable borrow material and aggregate under 2 inches in the greatest dimension.

Construction

911.20.03 General. On sideslopes where water can drain away from the trailbed, provide a sufficient depth of borrow material to obtain the outslope as SHOWN ON THE PLANS.

Across meadows and on turnpike sections, provide a sufficient depth of borrow material to produce a crowned trailbed as SHOWN ON THE PLANS.

Compact all material placed. Compact borrow material placed on the approaches of bridges and puncheon to provide a smooth surface and a smooth transition from the structure to the adjoining trail tread surface.

Cover any culvert surfaces that have become exposed with a minimum depth of 6 inches of suitable material over the full length of the exposed culvert and of sufficient length along the trail to present a uniform trail grade.

Provide free-draining borrow sites and backslopes no steeper than 1 1/3:1.

Section 912 - Clearing Limits

Description

912.00.01 This work consists of clearing, grubbing, trimming, removing, and treating trees, logs, limbs, branches, brush, plants, and other vegetation along with removal of rocks, undermined roots and hazard trees within the clearing limits. Clearing and removal of trees, vegetation and rocks may be covered by one or more of the following subsections:

912.10.

Clearing and Grubbing

912.20.

Brush Cutting

912.30.

Logging Out

912.40.

Hazard Tree Removal

912.50.

Loose Rock Removal

912.60.

Rock and Root Removal

Measurement

912.00.02 Measure the section 912 items listed in the bid schedule according to subsection 906.

Payment

912.00.03 The accepted quantities will be paid at the contract price per unit of measurement for the section 911 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 906.04.

912.10 - Clearing and Grubbing

Description

912.10.01 This work consists of clearing, grubbing, trimming, removing, and treating trees, logs, limbs, branches, brush, plants, and other vegetation within the clearing limits. Work includes the felling and treatment of designated trees outside the clearing limits. Also, included are the protection from injury or defacement of trees and other objects not designated for removal and treatment of damaged trees.

Construction

912.10.02 Clearing Limits. Clear to the dimensions SHOWN ON THE PLANS or 12 inches beyond the fill and backslope catch points, whichever is greater.

912.10.03 Material to Be Cleared. Remove and dispose of trees, logs, limbs, branches, brush, herbaceous plants, and other vegetation within the clearing limits, except for the following:

a) Live, sound, and firmly rooted trees of the size SHOWN ON THE PLANS.

b) Live brush, herbaceous plants, and trees between the trailway and the clearing limits that are less than 12 inches in height and less than ½ inch in diameter at ground line.

Except as provided above, cut all limbs and branches more than ½ inch in diameter that extend into the clearing limits. Cut limbs flush with the tree trunks or stems or cut at the ground surface as SHOWN ON THE PLANS.

Fall and limb designated trees.

912.10.04 Damaged Trees. When felling, cutting, or trimming, do not cause bark damage to standing timber. If damage does occur to standing trees, treat the injured trees as SHOWN ON THE PLANS. Remove and dispose of trees with major roots exposed by construction that are rendered unstable.

912.10.05 Removal of Stumps. Remove all stumps within the trailbed. Remove stumps located between the edge of the trailbed and the edge of the trailway that cannot be cut flush with the finished slope or that are not tightly rooted.

912.20 - Brush Cutting

Description

912.20.01 This work consists of removing brush, trees less than 4 inches in diameter, and shrubs within the clearing limits.

Construction

912.20.02 General. Remove all limbs of shrubs and trees that extend across or into the clearing limits as SHOWN ON THE PLANS. Saw or cut limbs flush with the tree trunk. Make cuts in a manner that will not tear or strip bark from the trees.

Cut and remove from the clearing limits all woody plants exceeding ½ inch in stem diameter or 12 inches in height. The maximum size material to be cut under this specification is 4 inches in diameter when measured at a height of 6 inches above the ground on the uphill side of the stump.

Cut all brush and small, woody plants as near flush to the ground surface as possible. When impractical to cut plants flush, the maximum stem length shall be 2 inches.

Remove all woody material for a minimum of 3 inches below the trail tread surface. Fill holes in the trail tread caused by removing woody material with suitable material.

Scatter the clearing debris removed from the clearing limits outside and below the clearing limits. Do not place materials in stream channels, drainage ways, ditches, culvert inlets, or other locations where they would prevent the free flow of water away from the trailbed.

912.30 - Logging Out

Description

912.30.01 This work consists of removing brush, logs, and down trees from the clearing limits.

Construction

912.30.02 Clearing Out. Mark trees slated for removal and confirm with the project inspector before removing. Cut and remove all logs that extend across or into the clearing limits. The portions of cut logs that remain on the upper side of the trail shall be either firmly anchored to prevent sliding or rolling onto the trailway or moved across the trail to the lower side and scattered outside the clearing limits.

Fell all trees over 4 inches in diameter that are leaning into the clearing limits and that are within 10 feet above the trailbed. Stump height of leaning trees that are cut outside the clearing limits shall not exceed 12 inches as measured on the uphill side of the stump. Disposal and payment for the leaning trees described above will be the same as for down logs and trees.

Remove roots and stumps from trees within the trailway that have been uprooted.

Rerouting the trail around windfalls, uprooted trees, and other obstacles will not be permitted. Ramp or reroute sections of the trail tread that have been damaged by uprooted stumps as necessary to provide safe passage on the trail. Payment for such work will be incidental to the specified work item, and no extra payment will be made.

Remove sticks or wood chunks exceeding 2 inches in diameter and 12 inches in length that have fallen onto the trailbed.

Scatter the down trees on the lower side of the trailway outside the clearing limits. Do not place such materials in stream channels, drainage ways, ditches, culvert catch basins or other locations where they would prevent the free flow of water away from the trailbed.

912.40 - Hazard Tree Removal

Description

912.40.01 This work consists of felling, bucking, and limbing trees and scattering slash.

912.50 - Loose Rock Removal

Description

912.50.01 This work consists of removal and disposal of loose rock from the trail tread.

Construction

912.50.02 General. Remove loose rocks that are larger than 2 inches at their greatest dimension from the trailbed. Remove any loose rock in drainage dips or ditches that may impede water flow off the trail. Loose rocks are rocks that are not firmly embedded in the trail and can be removed by hand. Where the trailbed consists predominantly of rock with little or no soil present, remove all loose rock larger than 3 inches.

Fill any holes remaining from rock removal with suitable material and compact. If the rock removed is not needed for other items of maintenance work, scatter the rock by side-casting to the lower side of trailway beyond the clearing limits, and distribute rock to ensure that no blockage of drainage or creation of a windrow occurs. Do not dispose of waste materials in water courses.

912.60 - Rock and Root Removal

Description

912.60.01 This work consists of removal and disposal of rocks and roots from the tread.

Construction

912.60.02 Rock Removal. Remove surface rocks that are larger than 2 inches at their greatest dimension, and rocks that project more than 2 inches above the surface of the trail tread, when removal can be accomplished by hand or when rocks can be pried out with a pick mattock, shovel, pry bar, or similar tool. Where the trailbed consists predominantly of rock with little or no soil present, remove loose rock in excess of 3 inches.

Shatter any protruding rocks in trail tread that are too large to be pried out with a pick and bar by using either a rock sledge or explosives. Remove the protrusion down to the level of the tread surface. Fill any resulting depressions with suitable material and compact by tamping. If rock removed is not needed for other items of maintenance work, scatter the rock by side-casting to the lower side of the trailway and beyond the clearing limits and distribute rock to ensure that no blockage of drainage or creation of windrow occurs. Do not dispose any waste material in water courses.

912.60.03 Root Removal. Remove exposed tree roots on or in the trail tread that are greater than 1 inch in diameter. Cut embedded roots that project more than 2 inches above the trail tread flush with the trail tread. Scatter removed roots on the lower side of the trailway beyond the clearing limits and outside of water courses.

Fill holes caused by rock and root removal with suitable material and compact to form a smooth trail tread.

Maintain trail tread to the width as SHOWN ON THE PLANS or DESIGNATED ON THE GROUND.

Section 913 – Surfacing

Description

913.00.01 This work consists of furnishing, hauling, watering, placing, and compacting surfacing and other associated work. Trail surfacing may be covered by one or more of the following subsections:

913.90.

Surface Maintenance

Measurement

913.00.04 Measure the section 913 items listed in the bid schedule according to subsection 906.

Payment

913.00.05 The accepted quantities will be paid at the contract price per unit of measurement for the section 913 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 906.04.

913.90 – Surface Maintenance

Description

913.90.01 This work consists of maintenance of surfacing, including excavation, furnishing, hauling, and placing rock, aggregate and other surfacing, compacting surfacing, and associated barriers, ditches, and retaining walls to bring surface up to good condition.

Maintenance

913.90.02 Perform maintenance of surfacing as required under the construction section of 914.00. and/or as SHOWN ON THE PLANS.

916.10 - Turnout and Passing Area

Description

916.10.01 This work consists of construction of turnout and passing sections, including furnishing, hauling, and placing rock and aggregate, and compacting aggregate surfacing and through talus or rubble rock sections of trail.

Construction

916.10.02 Construct turnout and passing sections as required by ABA requirements for every 1000 feet of trail distance.

916.20 - Turnout and Passing Area Maintenance

Description

05/01/2023