B09_Q_and_A_0001.docx

DOCX document 16 KB Posted

Attached to
GAOA WATER CANYON TRAIL BRIDGE REPLACEMENT Federal contract opportunity
Solicitation number
140L3923R0024
Issued by
Department of the Interior Bureau of Land Management Nevada Region

About this file

This document contains questions and answers regarding Solicitation 140L3923R0024 from the Bureau of Land Management for the replacement of two trail bridges over Water Canyon. The solicitation is primarily for construction services to replace the bridges according to the provided design documents. The contractor will be responsible for submitting proposals for construction methods such as precast abutments for approval. The bridges must be accessible by crane, which the contractor must assess for each site located within 100 yards of the main access road. Construction must take place in the fall or winter due to environmental restrictions, though delays in bridge manufacturing may extend work into the following season.

View the file

Other files for this federal contract opportunity

Other files attached to GAOA WATER CANYON TRAIL BRIDGE REPLACEMENT, newest first.
File Type Posted
Sol_140L3923R0024_Amd_0001.pdf PDF
A06__Drawing_Book_Water_Canyon_Trail_Bridges_100_percent.pdf PDF
B03_DBA_Wages_NV20220005.pdf PDF
A04_100__Statement_of_work_TrailsPortion.docx DOCX document
A06_Water_Canyon_Trail_Bridges_SCR_s.docx DOCX document
A06_Chapter_10__Outdoor_Developed_Areas.pdf PDF
A04_100__Statement_of_work_PedestrianBridges.docx DOCX document
A06_Trail_Specifications.doc DOC document
Sol_140L3923R0024.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers: Solicitation: 140L3923R0024 GAOA WATER CANYON TRAIL BRIDGE REPLACEMENT

“Does the solicitation require any design work?”

“The solicitation in nature is primarily a construction project. It is not primarily a design or a design-build project.”

1- The major suppliers of trail bridges are taking about 3-4 months after shop drawings are approved. This will takes it well past the governments current deadline. Can work be completed in the winter or will the project be extended to next spring/summer?

Construction must take place in the fall or winter time per NEPA. Water Canyon may be inaccessible due to winter snowfall. "The Government understands that the bridge manufacturing process may take longer than the time frame allotted, in this case the contractor should provide their best achievable period of performance date. The Governments preference would be for this fall/ winter season, but dates that go past the originally estimated period of performance will still be considered."

2-Can the contractor supply a precast abutment?

“The contractor will be responsible for submitting their proposal to the COR for approval.

Construction methods are the responsibility of the contractor. The abutments must meet design criteria provided in the design documents. Precast abutments that meet the design criteria would be acceptable.”

3- Is there crane access available at both sites?

“It is up to the contractor to determine the suitability of the two sites for crane access.

It is thought that crane access on the north side of the creek should be obtainable.

Trees greater than 6" diameter should be protected.”

“I was reviewing all the documents for said project in subject line. In the SOW I did not see any Hydro excavation of potholing needed. Can you confirm?”

“The main general contractor will be responsible for determining if utilities are present and the means and methods they will use to verify that. For clarification, this contract is not primarily a hydrovac excavation contract.”

“Is the fabrication and erection of the pre-manufactured steel pedestrian bridges to comply with FP-14 Section 555 Steel Structures including the requirement for an AISC Certified Steel Erector (555.18 Erection)?”

“The erection certifications for 555.18 may be waived.

The FP-14 specifications are for the site work and fabrication of the bridge. The welding certification must be maintained.”

“Construction Period” In fall or winter per NEPA. Water Canyon may be inaccessible due to winter snowfall. "The Government understands that the bridge manufacturing process may take longer than the time frame allotted, in this case the contractor should provide their best achievable period of performance date. The Governments preference would be for this fall/ winter season, but dates that go past the originally estimated period of performance will still be considered."

“Crane Accessibility” “Contractor to make own assessment of the site.”

”Are these like a 1000 feet up a canyon or pretty remote inside the canyon” “Each of the bridge locations are within approximately 100 yards of the main access road. The contractor will be responsible for evaluating access.”