A06_Site_Photos_29_pages_0001.pdf
PDF 15 MB Posted
- Attached to
- Asbestos Abatement at Glacier National Park
- Solicitation number
- 140P1424R0011
About this file
This document provides details on a federal contract opportunity for asbestos abatement work at Glacier National Park. The solicitation number is 140P1424R0011 and seeks bids for a three-part project to abate asbestos-containing materials in eight buildings located in the St Mary, Two Medicine, and Polebridge areas of the park. The work includes abating asbestos in various forms from the listed structures. The contracting agency is the Department of the Interior National Park Service Intermountain Region. The opportunity type is a solicitation and the document attached appears to be site photos relevant to the abatement work sites.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASBESTOS ABATEMENT
PARKWIDE
SITE PHOTOS
Location – St Mary Campground
CLIN #1 - St Mary Campground Area
B#1133 St Mary CG Comfort Station Loop C
B#1019 St Mary CG Comfort Station Loop B-C
B#1020 St Mary CG Comfort Station Loop B
B#1022 St Mary CG Comfort Station Loop A
Loop A
Loop B
Loop C
Location – Two Medicine and Polebridge
CLIN #1 and #2 Two Medicine Campground Area CLIN #3 Polebridge Ranger Area
B#535 Two Medicine CG Comfort Station Loop A
B#536 Two Medicine CG Comfort Station Loop A
B#1085 Two Medicine Triplex
B#353 Polebridge Cabin
Polebridge Ranger Station
Two Medicine Ranger Station
Two Medicine Camp Store
Two Medicine Lake
Pray Lake
CLIN #1 ABATE CAMPGROUND
COMFORT STATION ROOFING
MATERIAL
NOVEMBER 2023
Two Medicine B#535 and B#536
Roof framing plan (see attachments) Approximately 594 sf Typical appearance
Two Medicine B#535 and B#536
Typical roof layout Typical appearance
St Mary B#1019, B#1020, & B#1022
Approximately 492 sf Typical appearance
Typical appearance. Three of these buildings are served by an overhead electrical line connecting to the roof.
Typical appearance
Typical appearance. Three of the four St Mary buildings are served by an overhead electrical line connecting to the roof.
Rotten tongue and groove boards to be replaced by NPS after abatement
Typical drip edge, fascia boards, and roofing material Typical fascia boards and drip edge
St Mary B#1133
B#1133 appearance and parking area
Approximately 631 sf
St Mary B#1133
Appearance and roofing material Tongue and groove board roof deck
Typical photos from past project
Typical roof system, showing removed foam layer over asbestos-containing tar and gravel over fiberboards
Typical roof system showing top coating layer and drip edge
Roofing material removal in progress Roofing material removal in progress
Foam boards and asbestos-tar and gravel removed to reveal fiberboards
Foam boards partially removed to reveal asbestos-tar and gravel and fiberboards
Removals completed to tongue and groove roof deckRemovals completed to tongue and groove roof deck
CLIN #2 ABATE TWO MEDICINE
TRIPLEX FLOORING MATERIAL
SPRING 2015
Two Medicine B#1085
Google Maps view
FRONT PARKING
AND STAGING AREA
B#1085
REAR PARKING AND
STAGING AREA
Two Medicine Ranger Station
Floor plan (see attachments)
Unit A 475 sf
Unit B 475 sf
Unit C 486 sf
Laundry & Storage
105 sf
B#1085 Units B and C Typical entrance
Typical living room Typical living room
Typical living room Typical living room and kitchen
Typical living room, closets, and bathroom Typical kitchen
Typical bedroom and closets Typical bedroom
CLIN #3 ABATE POLEBRIDGE
WALL AND FLOOR MATERIAL
NOVEMBER 2023
Original cabin plans. Coal storage and shed have since been removed. Four windows were added.
B#353 Polebridge Cabin
Cabin interior. All drywall and flooring to be abated.
West/front elevation and access to cabin South elevation
East elevation North elevation
| ASBESTOS ABATEMENT PARKWIDE |
| Location – St Mary Campground |
| Location – Two Medicine and Polebridge |
| CLIN #1 ABATE CAMPGROUND COMFORT STATION ROOFING MATERIAL |
| Two Medicine B#535 and B#536 |
| Two Medicine B#535 and B#536 |
| St Mary B#1019, B#1020, & B#1022 |
| St Mary B#1019, B#1020, & B#1022 |
| St Mary B#1019, B#1020, & B#1022 |
| St Mary B#1019, B#1020, & B#1022 |
| St Mary B#1133 |
| St Mary B#1133 |
| Typical photos from past project |
| Typical photos from past project |
| Typical photos from past project |
| Typical photos from past project |
| CLIN #2 ABATE TWO MEDICINE TRIPLEX FLOORING MATERIAL |
| Two Medicine B#1085 |
| Two Medicine B#1085 |
| Two Medicine B#1085 |
| Two Medicine B#1085 |
| Two Medicine B#1085 |
| Two Medicine B#1085 |
| Two Medicine B#1085 |
| CLIN #3 ABATE POLEBRIDGE WALL AND FLOOR MATERIAL |
| B#353 Polebridge Cabin |
| B#353 Polebridge Cabin |
| B#353 Polebridge Cabin |
| B#353 Polebridge Cabin |