A04_Statement_of_Work_0001.docx
DOCX document 87 KB Posted
- Attached to
- Asbestos Abatement at Glacier National Park
- Solicitation number
- 140P1424R0011
About this file
This scope of work document outlines a three-part asbestos abatement project at eight buildings across three areas of Glacier National Park. The project includes removing asbestos-containing roofing material from six campground comfort stations, asbestos floor tiles and mastic from an apartment building, and asbestos wall and ceiling materials and floor linoleum from a cabin. Work must be completed by licensed asbestos abatement contractors according to federal, state and local regulations. The National Park Service is the contracting agency and will oversee the work through a contracting officer and contracting officer's representative. The project has three contract line items with work periods ranging from March to August 2024. Contractors must consider logistical challenges such as remote locations, seasonal access issues and protecting natural resources and visitors.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Abate Asbestos Containing Materials Parkwide
SCOPE OF WORK
ABATE ASBESTOS CONTAINING MATERIALS PARKWIDE
GLACIER NATIONAL PARK
UNITED STATES DEPT. OF THE INTERIOR
FINAL – 01/18/2024
0.0 TABLE OF CONTENTS
1.0 Overview & Project Description
2.0 Existing Conditions
3.0 Scope of Work
4.0 Codes & Authorities
5.0 Required Meetings, Submittals, & Closeout
6.0 Special Conditions & Requirements
7.0 Period of Performance
8.0 Attachments
1.0 OVERVIEW & PROJECT DESCRIPTION
This project is a three-part project to abate asbestos-containing materials in eight buildings in the St Mary, and Two Medicine, and Polebridge areas of Glacier National Park.
The Contractor’s scope is limited to abatement and removal services only. Reconstruction will be completed by NPS crews.
There are three Contract Line Item Numbers (CLINs) for this project. Bid prices shall be provided for each CLIN. Each CLIN shall include all preparation, mobilization, facilities, management, supervision, labor, subcontracts, equipment, materials, tools, testing, commissioning, training, permitting, insurance, bonds, taxes, and other costs incurred to complete the requirement as defined under Section 3.0 Scope of Work.
1.1. CLIN #1 Abate Campground Comfort Station Roofing Material
1.1.1. This CLIN will remove suspected asbestos-containing roofing material from six buildings. The buildings included in this CLIN are as follows:
a. B#535 Two Medicine Campground A Loop Comfort Station
b. B#536 Two Medicine Campground A Loop Comfort Station
c. B#1019 St Mary Campground B/C Loop Comfort Station
d. B#1020 St Mary Campground B Loop Comfort Station
e. B#1022 St Mary Campground A Loop Comfort Station
f. B#1133 St Mary Campground C Loop Comfort Station
1.2. CLIN #2 Abate Two Medicine Triplex Flooring Materials
1.2.1. This CLIN will remove asbestos-containing flooring material from an apartment building.
1.3. CLIN #3 Abate Polebridge Cabin Wall and Floor Material
1.3.1. This CLIN will remove asbestos-containing drywall joint material and mastic material from a one-room cabin.
Refer to Section 2.0 Existing Conditions for a description of the existing conditions for each CLIN. Refer to Section 8.0 Attachments for a list of materials and data provided by NPS.
Important points of contact for this project are as follows:
Contracting Officer’s Representative (COR) Kirby Granite Project Manager/Civil Engineer kirby_granite@nps.gov
(406) 890-5893
Contracting Officer To be determined
Glacier National Park Dispatch
(406) 888-7801
2.0 EXISTING CONDITIONS
2.1. CLIN #1 Abate Campground Comfort Station Roofing Material
2.1.1. Campground comfort stations have men’s and women’s restrooms, a utility sink room, and mechanical room. The six structures included in this project were built in the 1950s and 1960s in three separate projects.
2.1.2. Asbestos-containing materials have been positively identified in the roofing system of several of these buildings, according to the attached hazmat reports; however, it is believed that the roofing system of all six buildings contains asbestos. The work under this CLIN shall be performed under the assumption that the roofing system of all six buildings contain asbestos.
2.1.3. Refer to the available as-built drawings for the comfort stations. All comfort stations have a similar roofing system, described as follows:
a. Roof area, approximate:
1) Two Medicine B#535 and B#536: 594 square feet
2) St Mary B#1019, B#1020, B#1022: 492 square feet
3) St Mary B#1133: 631 square feet
b. Roof perimeter of lumber fascia boards and metal drip edge, approximate:
1) Two Medicine B#535 and B#536: 97 linear feet
2) St Mary B#1019, B#1020, B#1022: 91 linear feet
3) St Mary B#1133: 100 linear feet
c. 1:12 roof slope with high point at center
d. Approximate 8’ roof height above grade
e. Roof structure typically consisting of the following, from bottom to top (the roof structure may vary some from building to building):
1) Bottom layer of lumber tongue-and-groove board roof deck, under
2) Approximately 1” thick fiberboard panels (typically bonded to the roof deck with cap nails), under
3) Gravel layer bonded by asbestos-containing black tar, under
4) Approximately 3” thick foam boards, under
5) Top layer polymer-like layer that provides a singular, waterproof roof membrane, bonded to metal drip edge.
f. One plumbing vent penetration through the roof
g. Three of four buildings in the St Mary Campground (all but B#1133) are served by overhead electric lines with a roof penetration for the electrical connection.
h. At least one building (Two Medicine B#536) is NOT accessible by trailer. This building can only be accessed by narrow foot paths. Trailer access to other buildings may be difficult.
2.2. CLIN #2 Abate Two Medicine Triplex Flooring Material
2.2.1. B#1085 Two Medicine Triplex is a three-unit apartment building located off of the Two Medicine Campground Road, just past the Two Medicine Ranger Station. This building was constructed in 1966.
2.2.2. Each of the three apartments has a kitchen area, living space, bathroom, three closets, and a bedroom. As-built plans (dated 1966) are included in the attachments.
2.2.3. A laundry, storage, and mechanical room is located in the rear of the building.
2.2.4. 1/8” thick, 9” square, brown-colored vinyl-asbestos tiles are glued to a finished concrete surface. The glue tested negative for any hazardous materials. In 2002, this vinyl-asbestos tile was covered in vinyl or laminate flooring with a wood-grained appearance. This makes up the entire floor surface of the following units:
a. Apartment 1: approximately 475 square feet
b. Apartment 2: approximately 475 square feet
c. Apartment 3: approximately 486 square feet
d. Laundry, storage, and mechanical room: approximately 105 square feet
2.2.5. Furniture, cabinets, toilets, and other appliances will be removed by NPS prior to the start of abatement work.
2.3. CLIN #3 Abate Polebridge Cabin Wall and Floor Material
2.3.1. B#353 Polebridge Cabin is a one room building located in the Polebridge housing area in the Park. It was built in 1935 and has served several purposes, but is currently used as storage. Refer to the attached building plans.
2.3.2. Asbestos has been identified in the wall and ceiling joint material in the building. Refer to the hazmat history attachment.
2.3.3. Asbestos has been identified in the black mastic under the sheet linoleum that covers the entire floor surface. The building’s subfloor is constructed of lumber.
2.3.4. Its interior dimensions are approximately 12’ in width by 18’ in length by 8.33’ in height. It has four windows (approximately 2’ by 3’ each) and one door (approximately 3’ by 6.5’). A quantity estimate is provided below:
a. West (front door) wall: 118 sf
b. Side walls: 94 sf each x 2
c. East wall: 150 sf
d. Ceiling and floor: 216 sf
2.3.5. The building’s ceiling and walls are insulated.
2.3.6. All furniture will be removed by NPS prior to the start of abatement work.
3.0 SCOPE OF WORK
3.1. The following in this section does not dictate the sequence of the work to be performed. The Contractor shall determine the appropriate means and methods to accomplish the project objectives. Inspect all existing conditions and understand the full scope of related tasks. Bring any questions or unforeseen conditions to the attention of the CO.
3.2. Removal, handling, and disposal of asbestos containing material shall be completed by a Montana licensed professional abatement contractor in strict compliance with requirements of Federal, State, and local authorities having jurisdiction. The Contractor shall adhere to the most recent versions of all applicable codes. Applicable codes include, but are not limited to, those listed in Section 4.0 Codes & Authorities.
3.3. Provide a hazardous waste manifest to prove that the asbestos-containing and asbestos contaminated material has been disposed of properly.
3.4. Fully contain all and immediately collect all debris throughout the removals process. Use tarps or plastic sheets (as appropriate) to prevent any material and debris from leaving the project area and polluting the natural environment.
3.5. Secure each jobsite to prevent asbestos hazards to NPS and visitors.
3.6. All reconstruction and repair work will be completed by NPS. The contractor’s scope is limited to abatement and removal services only.
3.7. The following shall be completed under CLIN#1 Abate Campground Comfort Station Roofing Material:
3.7.1. Safely remove, handle, and dispose of all roofing material (including any debris resulting from the removals process) down to the tongue-and-groove roof deck. Remove metal drip edge. The roof deck is to remain. Damaged or deteriorated roof deck boards will be replaced by NPS. All debris is to be immediately collected and contained. Prevent any debris from leaving the project area and polluting the natural environment.
3.8. The following shall be completed under CLIN #2 Abate Two Medicine Triplex Flooring Material:
3.8.1. Please note that work will occur in the early spring, so water supplies will not be available in the Two Medicine Valley. The Contractor shall provide water supplies to complete the job.
3.8.2. Prepare the work area, construct the enclosure, and establish negative air pressure within the enclosure.
3.8.3. Safely remove, handle, and dispose of all vinyl-asbestos tiles, including any debris resulting from the removals process. Remove all mastic from the concrete surface. The mastic tested negative for hazardous materials.
3.8.4. Prevent water damage to any features that are to remain.
3.8.5. An independent third-party firm will complete air quality monitoring and provide a final clearance to confirm that all asbestos containing material is removed from the work area. This test will be scheduled and paid for by NPS. The Contractor is responsible for additional costs incurred from failed clearance tests.
3.9. The following shall be completed under CLIN #3 Abate Polebridge Cabin Wall Material:
3.9.1. Please note that water supplies will not be available in Polebridge during the period of performance for CLIN #3. The Contractor shall bring adequate water supplies to complete the job.
3.9.2. Safely remove, handle, and dispose of asbestos-containing wall and ceiling materials.
3.9.3. Safely remove, handle, and dispose of asbestos-contaminated sheet linoleum flooring and asbestos-containing black mastic.
3.9.4. Remove insulation from walls and ceilings.
3.9.5. Remove trim around the floor, windows, and doors.
3.9.6. Prevent any water damage to features that are to remain.
3.9.7. An independent third-party firm will complete air quality monitoring and provide a final clearance to confirm that all asbestos containing material is removed from the work area. This test will be scheduled and paid for by NPS. The Contractor is responsible for additional costs incurred from failed clearance tests.
4.0 CODES & AUTHORITIES
4.1. All work shall be performed in accordance with the following codes:
4.1.1. 29 CFR 1910 – Occupational Safety and Health Standards
4.1.2. 29 CFR 1926 – Safety and Health Regulations for Construction
4.1.3. 40 CFR 61 – NESHAP (National Emission Standards for Hazardous Air Pollutants)
4.1.4. 40 CFR 763 – Toxic Substances Control Act
4.1.5. Administrative Rules of Montana ARM 17.74 Subchapter 3 – Asbestos Control
4.1.6. Montana Code Annotated (MCA), Title 75, Part 5 – Asbestos Control
5.0 REQUIRED MEETINGS, SUBMITTALS, PAYMENTS, & CLOSEOUT
5.1. Pre-Construction Meeting
5.1.1. A pre-construction meeting will be held online with the Contractor, CO, COR, and NPS to cover basic procedures and regulations. This meeting will include, at minimum: discussions on Park rules and regulations, wildlife management, correspondence procedures, progress meetings, lines of authority, roles and responsibilities, coordination of subcontractors, submittal procedures, construction schedule, progress payments, acceptance and rejection of work, liquidated damages, labor standards, payroll reports, contract modifications, accident prevention, quality control, waste management and recycling, emergency procedures, road and site constraints, environmental considerations, and value engineering.
5.1.2. Meeting notes will be recorded and distributed by the COR.
5.2. Progress Meetings
5.2.1. Regular progress meetings may be required at the discretion of the CO. Progress meetings shall include, at minimum: submittal status, RFIs, contract modifications, work progress, schedule updates, and status of project record drawings or operation and maintenance manuals.
5.2.2. Meeting notes will be recorded and distributed by the COR.
5.3. Submittals
5.3.1. Submittals will be reviewed by the COR and CO. Submit at least 14 days prior to needed approval.
5.3.2. Submit the following items within 10 days of contract award. Once approved, the CO will issue the Notice to Proceed.
a. Performance Bonds
b. Certificate of Insurance
c. SF1413 forms for all Contractors and Subcontractors
5.3.3. Submit the following items after contract award but before the start of work using the provided NPS CM-16 form. Submittals shall be specific to the project.
a. Material technical data sheets for all proposed materials
b. Letter of Site Superintendent Designation
c. List of all Subcontractors (shall match that given in the Contractor’s proposal)
d. Final Construction Schedule
e. Schedule of Values (see Section 5.4)
f. Waste Management and Recycling Plan (see Section 6.9)
g. Quality Control Plan (see Section 6.10)
h. Safety and Accident Prevention Plan (see Section 6.11), including:
1) Hazardous spill plan
2) Visitor and traffic management plan
5.3.4. Submit the following items during work or prior to requesting a final inspection using the provided NPS CM-16 form:
a. Contractor Daily Reports
b. Digital Photos
5.4. Payments
5.4.1. The Contractor shall submit progress payments (for approval by the COR) based on the actual percentage of work completed by items listed in the approved Schedule of Values or by Contract Line Item.
a. The Schedule of Values shall include a breakdown of work items within each CLIN into discrete work elements or deliverables for which payments may be requested. Include mobilization, general conditions, overhead, and profit within each item rather than as separate items.
b. The CO may request data to verify the accuracy progress payments.
5.4.2. The Contractor shall provide all field notes, invoices and payroll reports, and other records relating to the basis of payment to the CO. The CO shall use these items as necessary to determine the final amount of progress payments.
5.5. Project Closeout
5.5.1. Submittals
a. Submit all deliverables listed in Section 5.3 Submittals and make any corrections required by the CO’s review.
5.5.2. Final Cleaning
a. The Contractor shall perform a final cleaning of the project area, including removal of all tools, equipment, materials, waste, and any grease, stains, labels, or other foreign materials. The project area shall be clean and ready for use by NPS and the public.
5.5.3. Substantial Completion, Final Inspection, and Acceptance
a. Submit written certification that the project, or designated portion of the project, is substantially complete and ready for final inspection. After final inspections, the CO will issue a punch list for any deficiencies noted. The CO will issue a Letter of Substantial Completion.
b. All deficiencies shall be corrected within 30 days, weather permitting. The CO will issue a Letter of Acceptance when all deficiencies are corrected. If the Contractor fails to complete the work within 30 days of issuance of the punch list, weather permitting. The CO may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs.
6.0 SPECIAL CONDITIONS & REQUIREMENTS
6.1. Wildlife Protection
6.1.1. Wildlife protections is of utmost importance. All Contractors and Subcontractors shall receive a briefing on working around wildlife, including bears, prior to the start of work. Notify the CO at least 14 days prior to the start of work to schedule this briefing. All construction personnel are required to fully understand and abide by all Park requirements, which will be strictly enforced at all times. Failure to comply may result in a citation and fine. A copy of Bear, Wildlife, and Sanitation Requirements While Working in Glacier National Park will be provided to the Contractor. Key points of this document include:
a. Food handling and storage
1) When not in use, food, beverages, containers, and utensils shall be kept inside of buildings, enclosed vehicles or trailers, storage sheds, or bear-proof coolers.
b. Material handling and storage
1) Mortar bags are known to attract goats, sheep, and deer. These materials should be kept under tarps to deter wildlife.
c. Petroleum product, antifreeze, and chemical handling and storage
1) Petroleum products, antifreeze, and other chemicals are known to attract and kill wildlife. When not in use, these materials shall be kept in bear-resistant containers.
d. Equipment use, maintenance, and refueling
1) Leaky equipment should be repaired immediately.
2) Refueling and servicing shall not occur within 100 feet of a water body.
e. Sanitation requirements, including site cleanliness, trash handling and disposal, and portable toilet requirements
1) Portable toilets must be lockable and be firmly staked into the ground to resist the force of 70 mph winds, or that of a curious grizzly bear.
2) Construction debris and trash must be disposed of in bear-proof bins or dumpsters, unless kept inside of buildings, enclosed vehicles or trailers, storage sheds, or bear-proof containers.
3) Construction debris and food waste shall not be mixed.
4) Immediately collect and contain scraps and waste.
f. Wildlife safety and potential wildlife interactions
1) All personnel should have bear spray readily available.
2) Activities shall be suspended if a bear, wolf, mountain lion, or other aggressive, conditioned, or habituated animal comes near the construction area and creates a potential human-wildlife conflict. Notify Park Rangers immediately for resolution of the potential conflict.
3) Report wildlife sightings to the CO and COR.
6.1.2. Protect natural habitats, including nests, and ecological systems at or near the project site.
6.1.3. Protect any unknown or undiscovered threatened, endangered, or special status species. Immediately stop work and contact the CO and COR if these species are found at the site.
6.2. Natural Resource Protection
6.2.1. Air, Water, and Soil Pollution
a. Employ construction practices that minimize dust production and combustion byproducts.
b. Avoid materials that can leach toxic chemicals into the groundwater. Do not allow toxic chemicals to enter sewers or storm drains. Apply Best Management Practices, including vehicle wash-down areas, equipment storage and maintenance areas protection, and roadway sweeping related to hauling activities.
c. Air quality impacts are expected to be temporary and localized. To reduce tailpipe emissions, vehicles and equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.
d. Volatile wastes shall be stored according to best industry practices and in covered containers.
e. Repair leaky equipment immediately.
1) Do not use equipment that is leaking.
2) Keep a supply of acceptable absorbent materials at the job site in the event of spills.
3) Acceptable absorbent materials are those manufactured specifically for containment and clean-up of hazardous materials.
f. Protect against erosion, contamination, and topsoil depletion.
6.2.2. Invasive Species
a. To prevent the introduction of noxious weeds to the Park, the Contractor shall thoroughly pressure wash all earth-moving and off-road vehicles and equipment with minimum 122°F water at 2,900 psi prior to entering the Park. All equipment must be free of soils, plant matter, and other debris, as determined the COR. Coordinate inspections with the COR at least two business days prior to bringing equipment to the Park. Failed inspections must be corrected at the Contractor’s expense. Vehicles and equipment that are reentering the Park does not have to be cleaned again, provided that it has not operated on a different jobsite. Coordinate with the COR.
b. To prevent the introduction of aquatic invasive species into the Park, all water pumps, hoses, and tanks must be chlorinated with a 200 ppm chlorine solution. Use a powder calcium hypochlorite or liquid bleach sodium hypochlorite. Allow the solution to stand for at least 12 hours and test to verify that a minimum 150 ppm is present. Chlorinated water shall be disposed of outside of the Park. Vehicles and equipment that is reentering the Park does not have to be chlorinated again, provided that it has not operated on a different jobsite. Coordinate with the COR.
c. All imported rocks, gravel, fill, or topsoil must be sourced from a NPS approved weed-free source.
6.2.3. Soundscapes
a. Minimize noise generated during construction.
6.3. Archeological Resource Protection
6.3.1. The discovery of archeological resources is not anticipated during this project. Work shall be immediately stopped and the Contractor shall notify the CO and COR if archeological resources are discovered during construction. The archeology and cultural resources team will document the location of the findings and, if necessary, develop an appropriate mitigation plan. The Contractor may be required stop work at the location of the findings and move elsewhere until given clearance from the CO.
6.4. Visitor Management
6.4.1. Incorporate visitor management and traffic control precautions and procedures into the Safety and Accident Prevention Plan as outlined in Section 6.11 Safety and Accident Prevention.
a. B#353 Polebridge Cabin and B#1085 Two Medicine Triplex are in areas not typically accessed by the public, but the potential remains. These buildings are in areas used by NPS employees, however.
b. The St Mary and Two Medicine comfort stations are in heavily used campground and the structures are in close proximity to campsites.
6.4.2. The Contractor is responsible for jobsite safety and security. The Contractor shall secure the jobsite to prevent any potential hazards to visitors and NPS, inside and outside of working hours.
6.4.3. Minimize disturbance to and interference with NPS operations, visitors, and traffic near the project area. Coordinate with NPS.
6.5. Contractor Access to the Park and Facilities
6.5.1. The Park does not provide lodging or campsites to Contractors. The Contractor shall not set up camp at (or near) the project site. The Contractor is responsible for finding accommodations on their own.
6.5.2. Coordinate with the COR for Park entry passes. Entry passes are required to be displayed on the dashboard of all Contractor vehicles and shown to NPS personnel at the Entrance Station. Entry passes are of no cost to the Contractor.
6.5.3. Coordinate with the COR for access to gates and buildings. The Contractor shall be responsible for safekeeping any loaned keys. The Contractor shall pay to replace lost or damaged keys.
6.6. Contractor Use of Utilities
6.6.1. There is no internet or cell service available in the Two Medicine Valley or Polebridge. Cell service is limited in St Mary during the summer months. Plan accordingly.
6.6.2. Water service will not be available in Two Medicine Valley or Polebridge areas during the period of performance of CLIN #2 and CLIN #3.
a. While the local water system is operational, NPS will provide potable water to the Contractor at no expense. The Contractor is responsible for installing and removing all temporary connections to the NPS water system. All temporary connections shall be approved by the NPS and shall include backflow prevention.
6.6.3. Vault toilets or comfort stations are available in each project area. Please make effort to keep these facilities clean for visitor use. Trash and debris shall not be disposed of in these facilities. These facilities shall not be used for cleaning tools or materials.
6.6.4. The contractor shall fully remove all temporary facilities prior to the final inspection.
6.6.5. The Contractor shall provide and maintain any needed heating or cooling facilities.
6.6.6. Keep utility service disruptions to a minimum. If disrupting NPS owned utilities, coordinate with the CO, COR, and NPS at least two weeks in advance of any utility disruptions. Coordinate with other utility providers and follow the utility provider’s procedures if other utilities will be disrupted.
6.6.7. Accidental utility disruptions shall immediately be remedied at no cost to NPS.
6.7. Contractor Use of Site
6.7.1. The Contractor shall keep the site neat and orderly at all times. Schedule regular “housekeeping” to ensure this. The site must always be free of wildlife attractants and potential hazards to NPS and visitors.
6.7.2. The Contractor shall be responsible for any damage caused by the Contractor that is outside of the scope of this project.
6.7.3. The Contractor shall minimize the footprint of the site and its staging areas.
6.7.4. The Contractor shall confine operations to within the immediate vicinity of the sites.
a. The Contractor shall use construction fencing or barriers, or other methods as explained in the approved Safety and Accident Prevention Plan (see Section 6.11), to define a construction zone and deter non-construction personnel from entering the site. The Contractor shall not conduct activities outside of the construction zone.
6.7.5. The Contractor shall prevent undue damage to the site’s natural surroundings.
a. Provide temporary barriers to protect existing trees, plants, and root zones that are to remain in place. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with the CO. Remove agreed-upon roots and branches that interfere with construction. Do not fasten ropes, cables, or guys to existing trees. Carefully supervise excavation, grading, backfilling, and other construction operations near trees and plants to prevent damage.
b. The Contractor shall restore damaged areas outside of the limits of disturbance, including but not limited to, vegetation restoration and tree repair or replacement.
6.7.6. The Contractor shall allow for NPS occupation or visitation of the site and always keep driveways and entrances serving premises clear and available to NPS and emergency vehicles.
6.7.7. The Contractor shall maintain existing buildings in a weathertight condition and protect its occupants.
6.8. Vehicles, Equipment, Parking & Staging Areas
6.8.1. The Contractor shall clean vehicles and equipment to prevent the introduction of invasive species or noxious weeds into the Park, as described in Section 6.2. Natural Resource Protection above.
6.8.2. Comply with all local, state, and federal loading and hauling restrictions.
a. Vehicles or vehicle assemblies longer than 21’, taller than 10’, or wider than 10’ are not allowed on Going to the Sun Road between the Avalanche Campground and the Rising Sun Campground. The alternate route is US-2 to US-89 through Browning, MT.
b. Vehicles or vehicle assemblies longer than 21’ are not allowed on MT-49 between the Two Medicine Road and US-89. Approach Two Medicine from East Glacier, MT.
c. The railroad overpass bridge at the intersection of US-2 and Going to the Sun Road in West Glacier has as clearance of approximately 13’-6”. Verify clearance and vehicle height before taking this route. The alternate route is to take the North Fork Road to Camas Road into the Park.
6.8.3. Parking and staging areas shall not obstruct emergency traffic, visitor traffic, or prevent NPS occupation or visitation of the site.
6.8.4. Parking, staging, and storage is at the risk of the Contractor.
6.8.5. Parking and storage of materials is permitted on-site and limited to hard surfaces, such as gravel or asphalt unless otherwise noted. Trailers may be brought on pervious surfaces, but take care not to damage vegetation or the ground surface.
a. CLIN #1 – each St Mary comfort station has two to three parking spaces that may be used by the contractor during work hours. In the Two Medicine Campground, park and stage vehicles along the roadway. Please note that there is no trailer access to at least one building (B#536) – this building can only be accessed by narrow foot paths. Trailer access to other buildings may be difficult.
b. CLIN #2 – there are asphalt parking areas in the front and rear of B#1085.
c. CLIN #3 – there is a defined gravel/dirt pathway in front of B#353 that can be accessed by trailers and used for parking.
6.9. Material Handling & Waste
6.9.1. The Contractor shall handle and store materials and waste as described in Section 6.1. Wildlife Protection above.
6.9.2. Materials shall be used efficiently. Select materials and use construction practices that achieve the most efficient use of resources and materials. Minimize waste generation due to over-packaging, poor planning, breakage, mishandling, contamination, error, or other factors. Reuse, recycle, or salvage as much of the waste generated as is economically feasible. Minimize waste disposal in landfills.
6.9.3. Materials shall be recycled to the maximum practical extent. Recyclable materials include carboard, paper, packaging, wood, containers, concrete, metals, drywall, paint, glass, and plastics.
6.9.4. All waste shall be disposed of outside of the Park in accordance with local, state, and federal requirements.
6.10. Quality Control
6.10.1. Quality Control Program
a. A site-specific Quality Control Program (QCP) shall be developed by the Contractor. The plan shall include, at minimum:
1) A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
2) A copy of a letter of direction to the Contractor's Quality Control Supervisor (QCS) that will carry out and oversee the QCP. The QCS (and alternate QCS, if applicable) shall be qualified and competent to perform these duties.
3) Names, qualifications, and descriptions of laboratories to perform sampling and testing and samples of proposed report forms
4) Methods of performing, documenting, and enforcing quality control of all work
5) Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws
b. The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance follows applicable specifications and drawings. Quality Control Daily Reports shall be completed by the QCS. Daily Test Reports shall be completed by the person performing the test.
6.10.2. Testing and Reporting
a. All work shall be tested, as applicable, to ensure that the quality of materials, workmanship, construction, finish, and functional performance is within the contract documents.
b. The Contractor shall employ certified independent laboratories to perform sampling and testing. The testing laboratory organization shall be certified for the type of testing work to be done.
c. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NBS requirements. Upon request, measuring and testing devices shall be made available for use by NPS for verification tests.
6.10.3. Enforcement
a. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the QCS or the CO.
6.11. Safety and Accident Prevention
6.11.1. Quality Assurance
a. A site-specific Safety and Accident Prevention Plan (SAPP) shall be developed by the Contractor to identify, assess, and mitigate potential hazards associated with the project through all phases of work. The SAPP should encompass detailed safety protocols, emergency response procedures, and protective measures aimed at ensuring the well-being of all contractor and subcontractor personnel, NPS employees, and visitors on or around the site.
b. A qualified and competent supervisor (and alternate supervisor, if applicable) shall be named to oversee and carry out the SAPP.
c. The Contractor shall that all employees are physically qualified to perform their assigned duties safely. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals, and operating instructions and be capable of operating such equipment.
6.11.2. Hazardous Spills
a. The Contractor shall incorporate preventative measures to prevent hazardous spills into their SAPP. Hazardous spills shall be reported to Glacier Dispatch and CO immediately.
6.11.3. Visitor and Traffic Management
a. The Contractor shall incorporate preventative measure to prevent hazards to NPS and visitors at or near the jobsites.
6.11.4. Safety Measures
a. The following shall be provided by the Contactor:
1) First Aid supplies
2) PPE that meets NIOSH and MSHA standards
3) Emergency instructions, including phone numbers and reporting instructions for Glacier Dispatch and emergency medical care.
4) Adequate egress at all times, following Life Safety Code NFPA 241
5) Hard hats for all employees and visitors
6) Posted signs in all designated hard hat areas
7) Hazardous spill clean-up kit
8) Fire prevention and protection equipment, as outlined in Section 6.13. Fire Prevention and Protection
b. Training
1) Provide training for first aid and hazardous material handling and storage.
2) On-site safety meetings with all personnel shall be conducted at least once per week.
c. Enforcement
1) The Contractor shall stop work on any item or feature pending satisfactory correction of any safety issue noted by any of the Contractor's staff, the subcontractor's staff, COR, or the CO.
d. Accident Reporting
1) Reportable accidents, defined as death, occupational disease, traumatic injury to Contractor's personnel, NPS employees or the public, property damage of any accident more than $100 and fires, must be reported immediately. Complete an Accident/Property Damage Report using the NPS standard Form CM-22 and forward to the CO within seven days.
6.12. Fire Prevention and Protection
6.12.1. Fire Safety
a. Observe and enforce standards of fire prevention. No open fires shall be allowed.
b. Capable and qualified person shall be in change for fire protection and prevention. Their responsibilities include locating and maintaining fire protection equipment and establishing and maintaining safe torch cutting and welding procedures.
6.12.2. Vehicles and Equipment
a. Provide one fire extinguisher on each vehicle or piece of equipment. A minimum of one fire extinguisher shall be readily available in all work areas. Extinguishers shall have a minimum UL rating of 2-A:10-B:C.
6.12.3. Hazard Control
a. Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in enclosed areas. Provide adequate ventilation during use of volatile or noxious substances.
6.12.4. Spark Arrestors
a. Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U. S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by CO. Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Shut down equipment before refueling.
6.12.5. Smoking
a. Smoking inside of structures near potentially combustible materials is prohibited. Cigarette butts shall be discarded in non-combustible containers and disposed of properly.
6.12.6. Welding and Grinding
a. Cutting by torch or grinding shall only be performed when adequate fire protection is provided and readily available.
6.12.7. Stage 2 Fire Restrictions
a. Should the Park enter Stage 2 Fire Restrictions during the period of performance, the Contractor may be required to obtain a Stage 2 Fire Restriction Exemption Permit from the GLAC Fire Management Office. Additional firefighting tools may be required to be readily available during work.
b. Stage 2 Fire Restrictions prohibit the following activities, without an exemption permit:
1) Building, maintaining, attending, or using a campfire
2) Smoking, outside of an enclosed vehicle or area clear of flammable materials
3) The following acts are prohibited outside between 1:00 pm and 1:00 am:
1. Operation of an internal combustion engine, except for use of generators with an approved spark arrestor in an enclosed vehicle or building or area cleared of any flammable materials within three feet of the generator.
2. Welding or use of a torch with an open flame
3. Use of explosives
4) Operation of motorized vehicles off designated roads or trails.
7.0 PERIOD OF PERFORMANCE
7.1. Work shall be performed in the following timeframes:
7.1.1. CLIN #1 #1 Abate Campground Comfort Station Roofing Material
a. May 20, 2024 to June 14, 2024 – completion of all work at B#535 and B#536 in the Two Medicine Campground. The Two Medicine Campground is scheduled to open on June 14, 2024.
b. July 1, 2024, to July 26, 2024 – completion of all work at B#1020 and B#1133 in the St Mary Campground.
c. August 1, 2024 to August 31, 2024 – completion of all work at B#1019 and B#1022 in the St Mary Campground.
d. NPS crews will make repairs and replace the roof structure immediately after the completion of abatement services. Coordinate with NPS at least two weeks prior to the start of abatement work.
e. Comfort stations will be closed to visitor use during abatement services. Minimize disturbance to the public.
7.1.2. CLIN #2 Abate Two Medicine Triplex Flooring Material
a. April 8, 2024 to April 30, 2024 – complete all work at B#1085.
b. NPS snow plowing crews typically being plowing operations on April 1 and will reach the end of the Two Medicine Road within a few days. Abatement work should begin shortly after the site becomes accessible. NPS crews plan to renovate the units to have available for the summer season.
c. NPS crews will remove furniture, appliances, cabinets, and plumbing prior to abatement work. Provide NPS at least a two week notice prior to the start of abatement work.
7.1.3. CLIN #3 Abate Polebridge Cabin Wall Material
a. March 18, 2024 to June 28, 2024 – complete all work at B#353.
b. The site is accessible year-round.
c. NPS crews will remove all furniture, trim and accessories prior to the start of work. Provide NPS at least a two week notice prior to the start of abatement work.
7.2. Work may generally be performed from 8 am to 6 pm, Monday to Friday. Weekends and holidays may be worked if approved at least two business days in advance by the COR and CO.
8.0 ATTACHMENTS
1.1 Scope of Work
1.2 Site Photos
1.3 As-Built Building Plans
1.4 Hazmat B#353 Polebridge
1.5 Hazmat B#535 Two Medicine (note – assume the same results for B#536 Two Medicine)
1.4 Hazmat B#1019 St Mary
1.4 Hazmat B#1020 St Mary
1.4 Hazmat B#1022 St Mary
1.4 Hazmat B#1085 Two Medicine
1.4 Hazmat B#1133 St Mary