This Performance Work Statement (PWS) details a remediation support project for the Bureau of Indian Affairs (BIA) in the Village of Eek, Alaska for 2025. The project focuses on conducting a preliminary investigation and site assessment of soil and groundwater contamination at an old school site (Hazard ID: 25493), with the primary objectives of characterizing petroleum contamination, evaluating environmental and public health risks, and developing a potential remediation plan.

The scope of work includes three primary tasks: (1) Planning and Project Management, involving project kick-off meetings, developing work plans, and preparing safety documentation; (2) Field Work, which involves a thorough site inspection, collecting up to 16 soil samples and 12 water samples for laboratory analysis, and documenting site conditions; and (3) Reporting, requiring a draft report within 45 days of field work completion, followed by review and finalization. The project is scheduled to be completed in spring 2025, with specific milestones tied to the contract award date, and all work must adhere to Alaska Department of Environmental Conservation (DEC), federal, and tribal regulations.

View the file

Other files

File Type Posted
Sol_140A0525Q0009_Amd_0002.pdf PDF
Sol_140A0525Q0009_Amd_0001.pdf PDF
B08_-_RFQ_Attachment_2_-_IEE_Rep_Form.pdf PDF
Sol_140A0525Q0009.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement Eek Remediation Support – Alaska Region 2025

Introduction

This RFQ is for a preliminary investigation/ site assessment of soil and groundwater contamination within the Village of Eek. The purpose of this contract is to conduct a preliminary investigation/ site assessment and remediation at the old school site (Haz ID: 25493) within the Village of Eek to characterize the contamination and design a remediation plan.

The work to be performed includes research of historic documents, site reconnaissance, identification of contamination, geotechnical investigation, risk evaluation, permitting, field work, sampling, analysis, data evaluation and additional activities to determine the quantity and quality of any contaminants present at the site. The scope of the investigation shall provide information sufficient to identify potential liability and risk associated with environmental and public health considerations concerning the property. In addition, the site characterization will allow managers to plan further investigations, if required, to determine cleanup requirements and design a cleanup action in accordance with the Alaska Department of Environmental Conservation (DEC), federal and tribal laws and regulations.

Background

Eek is located on the south bank of the Eenrayak River, 35 miles south of Bethel and 420 miles southeast of Anchorage, Alaska. The old school is located approximately 125 feet south of the Eenrayak River. The geographic description for the old Eek school is: Seward Meridian, Township 2 North, Range 73W, Section 31, of the United States Geological Survey. Fieldwork in 2024 determined petroleum contamination is present at various locations across the site.

Several samples found concentrations at levels greater than the DEC Maximum Allowable Concentration for DRO and RRO in soil. The contamination appears to mostly impact the area in the vicinity of the former BIA School and adjacent to the former tank farm, although the extent of contamination is not known.

The Environmental program ensures BIA’s compliance with environmental laws and regulations related to Native Allotments, Trust properties and BIA-funded projects. Among the support provided are contaminated site characterizations, remediation, groundwater sampling and laboratory analysis.

The intent of the project is to characterize to horizontal and vertical extent of soil contamination at the site and determine if impacts could pose a threat to the environment and/or human health, as well as if existing conditions may violate environmental regulations.

Work to be Performed

Conduct a contaminated site characterization/ site assessment within the Village of Eek. The Contractor(s) shall furnish the necessary personnel, material, equipment, services and facilities to perform the work for successful completion of the following project objectives for the investigation:

1. Planning and Project Management: Conduct project kick-off meeting and a planning meeting with BIA; develop work plan, schedule for the tasks and interim milestones.

2. Field Work: Obtain direct, in situ data that delineates the area of soil contamination above regulatory cleanup levels and conduct groundwater monitoring. Up to 16 soil samples will be collected for laboratory analysis. In addition, up to 12 water samples will be collected for laboratory analysis from the existing groundwater monitoring wells or using no flow grab sampling if a significant portion of the wells are dry. All fieldwork will follow DEC methods and meet DEC standards.

3. Report: The report must identify the environmental professional and others whom conducted fieldwork listed above, support findings and ensuing opinions with documentation, and use enough detail to allow another party to reconstruct the work that was performed and come to the same conclusions.

Task 1: Planning and Project Management

The contractor(s) will lead a project kick-off meeting with BIA within two weeks of the contract award to introduce the Contractor's Project Manager and key BIA personnel (Project Manager, Contracting Officer). Within one month after the award, a planning meeting will occur where the work plan, including schedule for the task elements will be identified, and interim milestones will be agreed upon and accepted by DEC. Key Contactor personnel/subcontractors will participate in the planning meeting. The Contractor will prepare materials and minutes for these two meetings. Minutes are due one week from the date of the meeting for review and comments and finalized 10-days after meeting dates. The Contractor should plan for one additional meeting during the period of performance following submittal of the draft final report.

In preparation for the planning meeting, the Contractor shall:

Collect and review existing data and files located on the DEC’s Contaminated Sites website Prepare a draft work plan, including sampling plan, and submit to BIA and DEC for review and approval Prepare a draft health and safety plan (HASP) in accordance with 29 CFR 1910.120 to ensure worker protection Prepare a draft notice to Native Corporation/Village advising them of the proposed site visit and sampling

Task 2: Field Work

The Contractor will plan field work with BIA personnel to document current site conditions, inspect known and potential sources of contaminants of potential concern (COPC) and delineate the area contaminated above regulatory cleanup levels. The field work will be coordinated with local tribal governments to ensure adherence to any restrictions.

A thorough inspection of the site is usually conducted first to familiarize the assessor with the physical parameters of the property and the surrounding properties. During this inspection, the assessor inspects the property and adjacent properties at the property line for signs of obvious contamination such as discolored soil, dead vegetation, underground tank appurtenances, leaking drums or other containers, transformers and evidence of asbestos or lead paint. The assessor also takes note of all current property users and any relevant activity that may have impacted the property being assessed. These observations are documented with photographs and GPS coordinates for the final report. If contamination is identified or suspected, soil and ground- water samples (as appropriate) will be collected and analyzed as necessary to delineate the contaminated area. Site visitation and sampling event will be dependent on weather conditions.

Task 3: Reporting

Based on the site inspection, field work, historic records and public agency file review; a report is prepared that summarizes the findings and presents recommendations for further field and laboratory work, if required.

A draft report will be submitted for review by BIA and DEC within 45 days following completion of the field work. The contractor shall schedule a joint work session to review the draft report and note comments for incorporation into the 90% submittal to expedite the review process. Following the final review and approval of the draft documentation by BIA and DEC, the contractor shall prepare the final report at 100% completion. This should include an electronic *.pdf version and three hard copies;

contractor will provide all electronic files in an editable format to include, Word, Excel, photos, etc.

Period of Performance, Schedule and Delivery

Schedule for delivery of contract-required deliverables:

Activity Timeframe

Contract Award

Task 1. Project Management and Planning Documents Initial Meeting Award Date + 28 days Draft Meeting Minutes Award Date + 35 days Final Meeting Minutes Award Date + 42 days Collaborative Workplan Meeting Award Date + 49 days Draft Workplan Award Date + 56 days Final Workplan Award Date + 64 days

Task 2. Field Work Spring (conditional on-site accessibility) Task 3.

Reporting Prepare Draft Report Field Work + 45 days BIA & ADEC Review of Draft Report Field Work + 60 days Submit Final Report Field Work + 75 days

The Contractor will obtain all necessary permits and access permission. Contractor shall adhere to all applicable federal, state and tribal laws and regulations. The Contractor is responsible for any utilities that are damaged during performance and shall repair them immediately at no cost to the Government.

Barring any complications in site access or other site-specific factors, the project shall be completed by the period of performance end date. As data is developed and regulatory agencies provide direction and guidance, Contractor shall be expected to provide timely and quality response to issues raised by the regulator(s). All contact between the public, private or regulatory community shall be made through the BIA, Alaska Regional Office. No information may be released without the written consent of the

BIA, ARO.

The government assumes no responsibility for any conclusions or interpretations made by the contractor based on the information made available by the government. Nor does the government assume any responsibility for any understanding reached or representation made concerning conditions, which can affect the work, by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this solicit

Introduction
Background
Work to be Performed
Task 1: Planning and Project Management
Task 2: Field Work
Task 3: Reporting
Period of Performance, Schedule and Delivery