A04_UPDATED_SOW_WRFO_SUPPRESSION_REPAIR_SEEDING_0001.pdf
PDF 1 MB Posted
- Attached to
- BLM-CO WRFO SUPPRESSION REPAIR SEEDING
- Solicitation number
- 140L1726Q0006
About this file
This is a Statement of Work (SOW) for the White River Suppression Repair Seeding project issued by the Bureau of Land Management (BLM) White River Field Office in Meeker, Colorado.
The contractor shall seed 258 total acres across two fire suppression repair projects: 70 acres for the Elk Fire (at 6.5 pounds per acre) and 180 acres for the Lee Fire (at 12 pounds per acre) with pre-mixed seed provided by BLM in 50-pound bags. Work must be completed between March 16, 2026, and April 20, 2026, with an estimated start date of March 2026. The project areas span varied mountainous terrain ranging from 6,250 to 8,800 feet in elevation near Meeker, Colorado in Rio Blanco County, with seeding units located 4 to 27 miles west-southwest of Meeker for the Lee Fire and 5 to 15 miles east of Meeker for the Elk Fire. The contractor must furnish all labor, transportation, fuel, tools, and equipment necessary for performance and must apply seed at 6–12 pounds per acre with no ground disturbance allowed. Seed application equipment must include GPS mapping capability, calibrated distribution mechanisms, and secure lids to prevent seed loss. The contractor must submit shapefiles and GPS-mapped application routes to the Contracting Officer's Representative (COR) within three days of project completion and notify the BLM representative at least 24 hours before commencing operations.
Acceptance is based on 95% of the designated seeded area meeting application specifications under Section C.1.2, with seed distribution uniform within 10 percent above or below the specified pounds per acre. The COR will conduct spot inspections for adequate seed coverage, and any areas with insufficient application documented during inspections require retreatment at no additional cost or result in per-acre payment deductions. Payment is based on actual acres seeded as determined from contractor-provided GPS data converted by BLM into a shapefile, measured on a horizontal plane. Invoices must be submitted through https://www.ipp.gov. Contractors may request remeasurement in writing within 10 calendar days after work completion; if the difference between measurements exceeds 5 percent, payment is based on the second measurement; if the difference is 5 percent or less, the original measurement applies and the contractor bears remeasurement costs. Covered Uncrewed Aerial Systems (UAS) manufactured in or using critical components from adversary countries are prohibited on Department of Interior managed lands.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1726Q0006_Amd_0001.pdf | ||
| A06_Elk_DozerLines_OptOutEdit.zip | ZIP file | |
| A06_Lee_DozerPushes.zip | ZIP file | |
| A04_SOW_WRFO_SUPPRESSION_REPAIR_SEEDING.pdf | ||
| A06_Lee_DozerLines_OptOutEdit.zip | ZIP file | |
| A06_Lee_AerialHaz_Lines_shp.zip | ZIP file | |
| A06_Elk_DozerPushes_OptOutEdit.zip | ZIP file | |
| B03_Service_Contract_Act_WD___2015-5439.pdf | ||
| Sol_140L1726Q0006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES DEPARTMENT OF INTERIOR
BUREAU OF LAND MANAGEMENT
White River Field Office
220 E. Market Street
Meeker, Colorado 81641
Statement of Work
White River Suppression Repair Seeding
SECTION A – SCHEDULE OF ITEMS
Item Description Est. Quantity Unit
Seeding – Elk Fire Suppression
Repair 70 Acres
Seeding – Lee Fire Suppression
Repair 180 Acres
PERFORMANCE TIME: March 16, 2026– April 20, 2026. The area should have at least 1 inch of continual snow cover if possible.
ESTIMATED START WORK DATE: March 2026
PERFORMANCE PERIOD: All work must be completed within the period of performance.
SECTION B - SPECIFICATIONS APPLICABLE TO SEEDING EQUIPMENT
B.1.1 DESCRIPTION OF WORK - The Contractor shall seed 258 acres at 6-12 pounds per acre. No ground disturbance will be allowed. Project area has varied mountainous terrain that ranges from flat valley bottoms to steep slopes and is a mix of public and privately owned land. Utility infrastructure and privately owned structures are near or adjacent to some of the seeding units. BLM will provide the seed in 50 lb. bags.
B.1.2 LOCATION OF PROJECT UNIT – The units for both project areas span a large area near Meeker, Colorado in Rio Blanco County. The Lee fire seeding units range 4 to 27 miles West-Southwest of
Meeker and the Elk fire seeding units range 5 to 15 miles east of Meeker. The Lat/long of the site is
40.90367 X -107.9115 °Maps showing the specific project areas are attached at the end of this document.
B.1.3 SUMMARY OF PROJECT UNITS TO BE TREATED –
Item Est. Acres to be seeded Elevation Est. Lbs Seed
1 70 6250-8300 ft. 455 lbs
2 180 6250-8800 ft. 2,160 lbs
B.1.4 SECURITY OF EQUIPMENT – The Contractor may leave their equipment at the work site however the
Contractor shall be responsible for the equipment if it should be lost, stolen, vandalized or damaged.
B.2.1 CONTRACTOR FURNISHED ITEMS - The Contractor shall provide all labor, transportation, fuel, tools and equipment necessary to perform the requirements of this contract.
B.2.2 SEED APPLICATION EQUIPMENT - The Contractor shall evenly distribute the designated seed at the rates specified. Application equipment shall be equipped for carrying seed with distribution mechanism including release, shutoff, and spreading device which can be calibrated for spreading seed at the prescribed rate in an acceptable manner and uniform pattern. Seed application equipment shall include lids/covers which fasten securely to prevent seed from blowing out.
B2.2a COVERED UAS – Covered Uncrewed Aerial Systems (UAS) will not be operated on Department of
Interior managed lands.
The term “covered UAS” as defined in Executive Order 13981, and adopted for official use by the
Department of Interior, means any UAS that:
i. is manufactured, in whole or in part, by an entity domiciled in an adversary country.
ii. uses critical electronic components installed in flight controllers, ground control system processors, radios, digital transmission devices, cameras, or gimbals manufactured, in whole or in part, in an adversary country (as defined by the Department of Commerce and referenced in OPM-11.)
iii. uses operating software (including a cell phone or tablet applications, but not a cell phone or tablet operating systems) developed, in whole or in part, by an entity domiciled in an adversary country.
iv. uses network connectivity or data storage located outside the United States, or administered by any entity domiciled in an adversary country; or
v. contains hardware and software components used for transmitting photographs, videos, location information, flight paths, or any other data collected by the UAS manufactured by an entity domiciled in an adversary country.
vi. The term “critical electronic component” means any electronic device that stores, manipulates, or transfers digital data. The term critical electronic component does not include, for example, passive electronics such as resistors, and non-data transmitting motors, batteries, and wiring.
B.2.3 GLOBAL POSITIONING SYSTEM - Application equipment furnished by the Contractor shall be capable of electronically mapping application routes to ensure seed is applied evenly and completely and at the specified rates. Within three days of project completion, shapefiles/maps of application routes shall be submitted to the COR (Contracting Officers Representative).
B.2.4 GOVERNMENT-FURNISHED PROPERTY – BLM will provide GPS compatible files that depict the seeding boundaries and work location maps of the project area. BLM will provide the pre-mixed seed in
50 lb. bags
SECTION C - SPECIFICATIONS APPLICABLE TO SEEDING
C.1.1 DISTRIBUTION OF SEED - All seed (government furnished) will be available for pick up from the
White River Field Office at 220 E. Market St., Meeker, CO.
C.1.2 APPLICATION – Apply mixed seed at a uniform rate per horizontal acre, minimizing overspray outside of treatment boundaries. Seed strips shall be distributed in such a manner as to provide uniform seed distribution. Such distribution shall not vary more than 10 percent above or below the specified pounds per acre. Seed application mapping data/mapping from the application equipment shall be provided to the Government following application. Seed application rate per acre is specified below.
Seed Application Rate Per Acre
Item No. Project Name Pounds Per Acre
1 Elk Fire 6.5
2 Lee Fire 12
C.1.3 GOVERNMENT FURNISHED GPS COORDINATES – GPS compatible files that depict project boundaries will be provided. Boundaries will not be marked on the ground.
C.1.4 NOTIFICATION REQUIREMENTS – Notify the BLM representative at least 24 hours prior to commencing seeding operations.
C.1.5 Immediately notify the COR of any application equipment incident.
SECTION D - INSPECTION, ACCEPTANCE, MEASUREMENT, PAYMENT
D.1.1 INSPECTION
D.1.2 The COR or PI will spot inspect seeded areas for sufficient seed coverage.
D.1.3 Where skips or insufficient application are documented during “on the ground inspections” by the COR, retreatment will be required at no extra cost to the Government or a deduction in payment will be calculated.
D.2.0 ACCEPTANCE
D.2.1 Acceptance will be based upon the satisfactory completion of the requirements in Section C.1.2
APPLICATION. The acceptable quality level is 95%. Meaning 95% of the designated seeded area must meet the requirements in C.1.2. If the acceptable quality level is found to be below 95%, per acre deduction will be made for any acres not meeting the specifications.
D.3.0 MEASUREMENT
D.3.1 The determination of the acreage of completed work will be made from contactor provided data and converted by BLM in a shapefile. Area measurements required under this Contract will be measured on a horizontal plane.
D.3.2 Remeasurement of the acreage under this Contract will be made upon the written request of the
Contractor. The request for remeasurement must be made in writing within 10 calendar days after completion of the work. If remeasurement indicates a difference of not more than 5 percent from the original measurement, the Contractor shall pay the actual cost of the remeasurement. Payments will be based on the second measurement where the difference between measurements is more than 5 percent.
Where the difference is less than 5 percent, the results of the first measurement will be used.
D.4.0 PAYMENT
D.4.1 INVOICING – Invoice(s) shall be submitted through the following website:
https://www.ipp.gov
D.4.2 Payment for seeding will be based on the actual number of acres seeded as applied according to the contract specifications within designated project boundaries and in accordance with Section C.1.2
APPLICATION.
D.4.3 If a deduction is determined necessary, it will be based on the awarded per acre price multiplied by the number of acres not meeting the specifications in C.1.2.
SECTION E – ATTACHMENTS
Lee Fire suppression repair Seeding Map
Elk Fire suppression repiar seeding map
File details come from the government source that posted it. Updated .