STATEMENT OF WORK
SUNSET CRATER NATIONAL MONUMENT FLAGSTAFF, ARIZONA
June 20, 2020
SOLICITATION ########
REHABILITATE ELEVATED WATER TANK
PMIS NO: 247591
PROJECT SCOPE
NATIONAL PARK SERVICE INTERMOUNTAIN REGION
Table of Contents
| PROJECT INTRODUCTION | 3 |
| Scope | 3 |
| Location | 3 |
| Background | 4 |
| Description | 4 |
| Schedule | 4 |
| Information | 5 |
| Data and Materials to be provided by the NPS | 5 |
| PROJECT REQUIREMENTS | 6 |
| General Requirements | 6 |
| Scope of Work and Project Summary/Requirements | 6 |
| Definition of Contract Line Items | 7 |
| Progress Payments | 7 |
| Project Meetings | 7 |
| Construction Requirements | 8 |
| Environmental and Sustainability Requirements | 8 |
| Construction Support | 10 |
| Submittals During Construction | 11 |
| Quality Control | 15 |
| Working Hour Restrictions | 16 |
| Temporary Services | 16 |
| Access | 17 |
| Preservation of Adjacent Features | 17 |
| Existing Utilities | 17 |
| Hauling Restrictions | 17 |
| Accident Prevention | 18 |
| Temporary Controls | 19 |
| Project Close-out | 19 |
| Substantial Completion and Final Inspection | 20 |
| Forms | 21 |
| PERFORMANCE REQUIREMENTS | 23 |
| 3.2 Facility Performance | 23 |
| 3.3 Elements and Products | 23 |
| 4.0 TECHNICAL REQUIREMENTS | 24 |
| 5.0 ATTACHMENTS | 25 |
1.1 PROJECT INTRODUCTION
Park Alpha and PMIS Number: SUCR 247591
Project Title: REHABALITATE WATER TANK
1.2 Scope
In accordance with the terms and conditions of the Contract, the Contractor shall perform the work for the National Park Service (NPS) as described below.
In addition, there is an “Information” section (http://www.nps.gov/dscw/information.htm) which provides design requirements and criteria that shall be used for completing the work of this contract. The “Information” section provides links to the following:
· Forms/Templates/Samples/Guidelines (http://www.nps.gov/dscw/publicforms.htm): A listing of forms/templates/samples/guidelines used for a typical project.
· Laws/Regulations/Policies/Guidance (http://www.nps.gov/dscw/laws-policies.htm): A listing of sources for retrieving laws/regulations/policies/guidance applicable to NPS projects.
1.3 Location
This project is located in and directly adjacent to the developed Visitor Center and Housing Area at Sunset Crater National Monument (SUCR) in Coconino County, Arizona. The SUCR Visitor Center area is located at 6082 Sunset Crater Rd, Flagstaff, AZ, 86004. The Visitor Center Area is located appx. 5 miles East on FS 545 (Wupatki Loop Road) from the intersection of FS 545 and US Highway 89. The intersection of US Highway 89 and FS 545 is appx 18 miles north of Flagstaff, AZ. The elevated water storage tank has good accessibility for vehicles and equipment.
A pre- award site visit is greatly encouraged to determine site conditions and site limitations to conventional equipment. The contractor shall make every effort to minimize impact to the site and the natural surroundings by limiting off road travel. The date and time of the site visit will be noted in the solicitation sent to the Contractors.
1.4 Background
The elevated water storage tank was constructed in 1966 and has been properly maintained since. This has left the tank in good condition but requires minor rehabilitation to reach the full design life. In an effort to reduce impact on the surrounding resources all considerations will be made to use minimal impact. Contractor will be responsible for proper disposal of all materials. The water tank provides services to a visitor center (2 restrooms, a water fountain, and other points of service), a maintenance facility, 2 residential housing units, a 2-unit apartment building, 4 trailer pads, and a seasonal campground with 2000 GPD used on average, and various points of service (yard hydrants, spigots, fire hydrants).
1.5 Description
The park seeks to:
Rehabilitate the existing elevated water tank at SUCR to comply with OSHA, AWWA regulations. A temporary water supply in compliance with all ADEQ guidelines must be provided while existing tank is out of commission. All water quality testing stipulated by ADEQ must be preformed prior to rehabilitated tank being brought back into service. All applicable ADEQ paper work will be provided to park.
1.6 Schedule
The work in this RFP shall be completed in accordance with the following schedule:
Construction:
Construction shall not begin until the Contracting Officer (CO) has issued the Notice to Proceed.
Construction shall be completed no later than 180 calendar days after award of the contract.
1.7 Information
NPS Points of Contact:
Contractual:
Contracting Officer (CO): Deborah Cimmer, 928-638-7434, Deborah_cimmer@nps.gov
Technical:
Project Manager/Contracting Officer’s Representative (PM/COR): Eric Rowe, 781-718-7333, Eric_rowe@nps.gov
| Contracting Office Address: | Work Location Address | ||
| National Park Service – Intermountain Region | Sunset Crater NM Arizona Major Acquisition Buying Office | 6082 Wupatki Loop (AZ-MABO) | Flagstaff, AZ 86004 |
1824 S. Thompson St. Suite 200 Flagstaff, AZ, 86001
1.8 Data and Materials to be provided by the NPS
The following data and materials will be provided to the DBC and are included in Section 5 of this RFP:
· Project Program/Description
· Existing Drawings
· Existing Site Map and Underground Utilities
· Most recent tank inspection reports
· NPS Transmittal Form CM-16 for submittals
2.1 PROJECT REQUIREMENTS
2.2 General Requirements
2.2.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS
This proposal is for the rehabilitation of the 100’ 50,000 gallon elevated water storage tank. The water tank serves the Visitor Center, 2 Public restrooms, 8 residential service connections, and a seasonal campground using 2000 GPD average.
The rehabilitation of the water tanks consists of the following:
· Temporary water storage and distribution: A temporary water supply system must be provided to maintain potable water supply to the Sunset Crater water system. System must comply with all ADEQ water quality testing and other requirements for a temporary potable water supply.
· Tank Foundation rehab: Clearing any dirt, debris and other loose gravel away from the tank foundation, down to a minimum 6” below top of concrete foundations. The top of the concrete piers shall be 6” above the finished grade. Repair any cracks and spalling in the concrete with a commercial non-shrinking grout. Re-seal the foundations with a sealant. Clean the area around the anchor bolts, tightening the anchor bolt nuts to approved specifications and welding around the circumference of the bolt-to-nut and nut-to-base plate connections to reinforce.
· Drain Valve Splash Pad: Install a concrete splash pad to direct drained water away from foundation.
· Manway rehab and replacement: Install a “Confined Space Entry” sign on all Manways and install maintenance free galvanized steel bolts. Replace one 24” manways with 30” manways to meet OSHA AWWA guidelines.
· Overflow Pipe System rehab: Install a flapper valve and screen on discharge end of overflow pipe.
· Ladder rehab: Install a new OSHA compliant tower access ladder complete with standoffs every 10' on center, a new OSHA approved cable type ladder safety device, and reinstall the existing lockable ladder guard.
· Handrail and Walkway System rehab: Install an intermediate rail on the existing 42” handrail as required by OSHA 29 CFR 1910.23(e)(1). Drill additional weep holes in the balcony floor to prevent ponding of water.
· Liquid level Indicator rehab: Repair the existing liquid level indicator, replacing damaged parts as needed, calibrate the unit and repaint the target board.
· Shell/Roof Access Ladder rehab: Replace existing ladder with OSHA approved anti-skid rung equipped shell ladder complete with standoffs every 10' on center and a OSHA approved cable type ladder safety device.
· Tank Roof rehab: Extend the 42” high handrail system around the circumference of the tank roof, complete with toeboard and intermediate rail to comply with OSHA standards.
· Tank Interior rehab: Recoat tank interior with an AWWA/NSF approved coating. Install OSHA approved cable type ladder safety devices at the primary and secondary shell manway ladders.
The project shall consist of rehabilitating the elevated water storage tank of the Sunset Crater water system.
The project shall include, but not be limited to, the following:
· Provide schedule of construction work
· Secure work area and provide for continued access to the facility
· Construct project
· Create and provide operations and maintenance manual
2.2.2 Definition of Contract Line Items
The intent of this section is to explain, in general, what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include the costs in a related line item.
CONTRACT LINE ITEM NO. 1 – Tank #1: These items consist of all the work required on Tank #1.
CONTRACT LINE ITEM NO. 2 – Tank #2: These items consist of all the work required on Tank #2.
This item shall consist of lines needed to properly construct all items in Design part No. 1.
2.2.3 Progress Payments
Construction Phase - Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the percent complete shall be initiated by the Contractor under the direction of a representative of the Contracting Officer (CO), unless the CO waives this requirement in a specific instance.
The Contractor shall make the computations for payment based on the government’s verification of work completed and in place for any periods for which progress payments are requested.
The Contractor shall furnish the originals of all field notes and all other records relating to the basis for payment, to the CO, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the CO.
2.2.4 Project Meetings
Preconstruction Meeting
The following deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting.
· Letter designating your Project Superintendent
· Project Schedule
· Accident Prevention Program
· List of subcontractors (must be same as in the proposal)
· Written statements from subcontractors certifying compliance with applicable labor standard clauses
· Evidence of liability insurance coverage and workmen’s compensation for the contractor and all subcontractors
· Storm Water Pollution Prevention Plan Submittal process
· Contractor’s Commissioning Plan (CCxP)
Progress Meetings
The Contractor shall participate in weekly, or as appropriate, telephone conference calls with the Contracting Officer (CO), and other project team members to update them on the following meeting agenda items:
· Approval of minutes of previous meetings
· Submittal status
· Review of off-site fabrication and delivery
· Requests for Information (RFI’s) and issues
· Modifications
· Work in progress and projected
· Schedule update
· Other business relating to work
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Contact for the Arizona Department of Environmental Quality is Brian Jones (602) 771-2333.
Refer to part 3, Performance Requirements, of this document and the NPS Project Sustainability Checklist. The following are general requirements:
· Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.
Toxic Chemicals: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water. Refer to NPS Project Sustainability Checklist for additional requirements.
· Soil Erosion: Protect against erosion and topsoil depletion in accordance with the Stormwater Pollution Prevention Plan.
· Habitats: Protect natural habitats and ecological systems on facility site (as identified in the Environmental Assessment).
· Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.
· Waste Management: Employ processes that ensure the generation of as little waste as possible. Waste disposal in landfills shall be minimized. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.
Minimize Construction Impacts
The following mitigation measures shall be implemented to minimize the impacts of construction activities:
· Soil Erosion: Protect against erosion and topsoil depletion. Storm Water Pollution Prevention Plan required. National Pollution Discharge Elimination System (NPDES) permit is required for storm water discharge for projects which disturb one acre or more.
· Exotic Vegetation and Noxious Weeds: Prevent the introduction and minimize the spread of exotic vegetation and noxious weeds. Incorporate the following procedures:
Any fill, rock, or additional topsoil needed shall be obtained from a Government approved source. All areas disturbed by construction shall be re-vegetated using approved native seed and/or plants.
All equipment brought to the site shall be free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Contractor shall ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving equipment to project area. Equipment shall be considered free of soil, seeds and other such debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools is not required.
· Special Status Species: To protect any unknown or undiscovered threatened, endangered, or special status species, the construction contract will include provisions for the discovery of such. The contractor should contact the park for direction for evaluation of any special species at the site.
· Visitor Experience: The following mitigation measures shall be incorporated into the action alternatives to minimize the impacts of construction activities on the visitor experience:
· Air and Water Pollution Control: Air quality impacts are expected to be temporary and localized. To minimize these impacts, the following actions shall be taken:
· To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.
· To reduce construction dust, water shall be applied to problem areas. Equipment shall be limited to the project area to minimize soil disturbance and dust generation.
· Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Keep volatile wastes in covered containers.
· Storm Water Pollution Prevention Plan (SWPPP): Submit a SWPPP according to the applicable state and federal requirements to the Contracting Officer (CO) for approval. (See Technical Requirements) Before starting construction, the Contractor shall implement the approved SWPPP. National Pollution Discharge Elimination System (NPDES) permit is required for storm water discharge for projects which disturb one acre or more; follow regulatory requirements for Notice of Intent and Notice of Termination.
2.3.2 Construction Support
Staging Areas
Construction sites will be limited to the smallest feasible area. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.
Staging is limited in or near the construction area. Construction equipment and material storage shall be located in previously disturbed areas near the construction site. All staging areas shall be returned to pre-construction conditions once construction is complete. Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the COR.
Structures:
Trailers, Storage, Field Offices, Staging Area and Sheds: Location to be approved by the Park Superintendent, or if delegated, the COR.
Storage Sheds: If used, provide weather tight sheds or other covered facilities for storage of materials subject to weather damage.
If used, all temporary water, sewer, sanitary facilities and electric utilities, shall be completely removed upon project completion. Remove temporary utility connections.
The location of the Staging Area for construction equipment will require COR approval. Construction Camp: Establishment of a construction camp will not be permitted.
Construction Zones
Construction zones shall be fenced with Contracting Officer’s Representative (COR) approved construction barrier fencing, plastic or portable fencing, before any construction activity. The fencing shall define the construction zone and confine activity to the minimum area required for construction. Workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing.
Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with the most current version of the MUTCD.
Special Construction Requirements
Working hour restrictions and access to the SUCR Park will have to be coordinated with the COR and Park Staff. As well as any other project specific requirements that the contract may need to complete the construction.
Normal Park working hours is from 7:00 am to 5:00 pm.
Parking of Construction Vehicles
Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s) to be agreed upon at initial site visit/pre-construction meeting and as approved by the COR.
2.3.3 Submittals During Construction Submittals:
· All submittals shall be transmitted using National Park Service form CM-16R. (A copy of the form is included at the end of this section.) No action will be taken on a submittal item unless accompanied by the transmittal form.
· As specified in the individual sections, forward submittals to Contracting Officer (CO) at least 14 days before need for approval. Unless a different number is specified, submit one reproducible original and two copies of each shop drawing, two copies of manufacturer's catalog sheets (cut sheets), one specimen of each sample, and two copies of all other submittals requested.
· Samples: Samples shall be large enough to illustrate clearly the functional characteristics and full range of color, texture, or pattern.
· Manufacturers' Catalog Sheets: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use.
· Manufacturer's Installation Instructions: When contract documents require compliance with manufacturer's printed instructions, provide one complete set of instructions for Contracting Officer (CO) and keep another complete set of instructions at the project site until substantial completion.
· CO reserves the right to require submittals in addition to those called for in individual sections.
· Approved Equals: For each item proposed as an "approved equal," submit supporting data, including:
· Comparison of the characteristics of the proposed item with that specified. o Changes required in other elements of the work because of the substitution. o Name, address, and telephone number of vendor.
· Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
· A request for approval constitutes a representation that Contractor:
· Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
· Will provide the same warranties for the proposed item as for the item specified.
· Has determined that the proposed item is compatible with interfacing items.
· Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
· Waives all claims for additional expenses that may be incurred as a result of the substitution.
· Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
· Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.
· Submittal Numbering shall have the following items:
· Number each submittal consecutively.
· For re-submittals use the original submittal number, plus a letter suffix beginning with A.
· Additional re-submittals of the same item shall contain the original number with the next consecutive letter.
· Contracting Officer's Review:
· Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor's approval.
· Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.
· The returned submittal will be marked in one of three ways as defined below:
· APPROVED: Acceptable with no corrections.
· APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
· DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The CO will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
Construction Submittal Types
Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
· Product Data: Collect information into a single submittal for each element of construction and type of product or equipment
· Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, use of CAD for the Shop Drawings is permitted.
· Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
· Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials
Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
· General: Prepare and submit Informational Submittals required by individual Specification Sections.
· Informational submittals include but are not limited to Coordination Drawings, Certificates, Test reports, Manufacturer’s instructions, Division 01 Management Plans, etc.
Contractors Review
Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
General Submittal Procedures
Prepare and submit submittals using Transmittal Form CM-16 for products and materials shown in Part 4.0, Technical Requirements or as required by the Construction Specifications developed for the project will be stated at the end of technical section and will be approved accordingly as stated above in Contracting Officer’s Review.
CO reserves the right to require submittals in addition to those called for in individual sections.
Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
Processing Time: Allow enough time for submittal review, including time for re-submittals. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action Submittals: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
2. Informational submittals: Allow 10 days for review of each submittal.
Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. Transmittal Form: All submittals shall be transmitted using National Park Service form CM-16, which can be obtained from the CO.
2. Physical samples: Deliver the physical sample to the CO (or designee) on site for processing.
Contracting Officer's Review
Action Submittals: Contracting Officer (CO) will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the Transmittal Form. The submittal will be marked in one of three ways as defined below:
1. Approved: Acceptable with no corrections.
2. Approved with Notations: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
3. Disapproved – Resubmit: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The CO will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
Informational Submittals: CO will review each submittal and will either accept or reject them.
Submittal List
An example of a Submittal List is included at the end of this section. (The latest version of the Submittal List and Review Estimate template is on the DSC Workflows website, http://www.nps.gov/dscw/publicforms.htm#dt. The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The technical requirements indicate the type and specify submittal requirements. The terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
Use for Construction
Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction
2.3.4 Quality Control General
The quality of all work shall be the responsibility of the Contractor. Testing shall be the responsibility of an independent testing laboratory. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
Quality Control Daily Reports shall be completed by the Quality Control Supervisor. Test reports shall be completed by person performing the test.
The CO may designate locations of tests.
Quality Control Staff
The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.
The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor supplemented, as necessary, by additional certified testing technicians.
Documentation
Maintain Quality Control Daily Reports, Daily Test Report Information Sheets, and Accessibility Inspection Reports, http://www.nps.gov/dscw/publicforms.htm#cf, of quality control activities and tests.
Quality Control Daily Reports may not be substituted for other written reports required under clauses of the contract, such as Disputes, Differing Site Conditions, or Changes.
Enforcement
The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer (CO).
2.3.5 Working Hour Restrictions
All work and deliveries shall be limited to the weekday hours of 7:00 am to 5:00 pm unless otherwise approved by the CO 48 hours prior to the proposed after hour work request. No work shall occur on National Park Service holidays or weekends without prior approval.
2.3.6 Temporary Services
Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
Fire Protection: Observe and enforce standards of fire prevention. No open fires shall be allowed. Provide one fire extinguisher on each vehicle or piece of equipment, as well as one extinguisher for each 1,500 square feet of building. Extinguishers shall have a minimum UL rating of 2-A:10-B:C. A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.
Spark Arresters: Equip all gasoline or diesel powered equipment used in potential forest or grass fire locations with spark arresters approved by the U. S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by CO. Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Locate service areas a minimum of 50 feet from buildings. Shut down equipment before refueling.
Smoking: Smoking within buildings or temporary storage sheds is prohibited.
Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided. A hot work permit is required for welding work.
Electricity and Lighting: Use of existing electrical power service will be permitted, as long as equipment is maintained in a condition acceptable to the NPS. Electrical power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. Coordinate work with CO. Temporary electrical work shall meet requirements of the current version of NFPA 70
(NEC) Article 590. When temporary connections are removed, restore existing utility services to their original condition.
Water: Potable water is available on site. Make connections to existing facilities as needed. Facilities must be cleaned and maintained in a condition acceptable to the NPS. Water from the existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. When temporary connections are removed, restore existing utility services to their original condition.
Sanitary Facilities: Contractor shall provide and maintain temporary toilet facilities in accordance with State Health Department and National Park Service regulations. Enclosures shall be weatherproof, sight proof and of sturdy construction. Completely remove sanitary facilities on completion of work.
2.3.7 Access
Coordinate construction efforts with the CO such that there is minimal impact to the work of the National Park Service personnel and the visiting public.
During construction of the scheduled facilities, the Design Build Contractor shall have limited access to the site based on regular work hours or as approved by the CO.
2.3.8 Preservation of Adjacent Features
Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas outside the work limits, repairing or replacing damaged trees and plants, at no additional expense to the National Park Service.
Provide temporary barriers to protect existing trees, plants and root zones that are to remain in place. Do not remove, injure or destroy trees or other plants without prior approval. Consult with the COR, but needs to be noted as no cost to the Government. Remove agreed upon roots and branches that interfere with construction. Carefully supervise excavation, grading, backfilling, and other construction operations near trees and plants, to prevent damage.
2.3.9 Existing Utilities
Disruptions of services shall be kept to a minimum. The Contractor shall coordinate with the local utility companies before any disturbance of earth or excavation is taken place. All disruptions shall be arranged at least 48 hours in advance with National Park Service and must be approved by COR.
Construction procedures will prevent accidental disruptions to facilities outside the project limits by investigation of existing utilities and protection during construction: accidental disruptions shall be remedied at no cost to National Park Service.
2.3.10 Hauling Restrictions
Comply with all legal load restrictions in the hauling of materials. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
2.3.11 Accident Prevention
Accident Prevention Program: Prior to the Preconstruction Meeting submit an accident prevention program. The program must be accepted by the NPS before any on site work can begin. The program shall comply with OSHA and project requirements. The Contractor shall perform in strict conformance with all Health Requirements Manual EM 385-1-1 dated 30 November 2014, and 29 Code of Federal Regulation (CFR) 1910 and 1926 of the Occupational Safety and Health Act (2007), as required.
Emergencies In the event of an emergency the Contractor will utilize 911 services. Include the following:
Name of responsible supervisor to carry out the program; monthly safety meetings; first aid procedures; outline of each phase of work, hazards associated with each phase and methods proposed to ensure property protection, and safety of the public, National Park Service staff and DBC employees; training; planning for possible emergency situations; housekeeping and fire protection.
Accident Reporting: Reportable accidents, defined as death, occupational disease, traumatic injury to contractor’s personnel, NPS employees or the public, property damage of any accident in excess of $100 and fires, must be reported within seven days. Complete the CM-22 DSC Contractor Accident/Property Damage Report template, http://www.nps.gov/dscw/publicforms.htm#ct, and forward to the Contracting Officer (CO).
Quality Assurance: Ensure that all employees are physically qualified to perform their assigned duties in a safe manner. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals and operating instructions, and be capable of operating such equipment.
Accident Prevention Products: Provide the following:
· First aid facilities.
· Personnel protective equipment: Meet requirements of NIOSH and MSHA.
· Emergency instructions, including telephone numbers and reporting instruction for ambulance, physician, hospital, fire department and park police. Place in conspicuous locations at the worksite.
· Adequate egress at all times in accordance with the Standard for Safeguarding Construction, Alteration, and Demolition Operations (NFPA 241).
· Fall protection plan
· Hard hats for all employees.
· Designate and post signs in all hardhat areas.
Training: It is the responsibility of the Contractor to provide training for first aid and hazardous material handling and storage to ensure the safety of their employees. The required training certifications for contractor employees will be submitted to the COR.
2.3.12 Temporary Controls
Housekeeping: Keep project neat, orderly, and in a safe condition at all times.
Weather Protection: When inclement weather is expected, provide temporary protection, for areas where roofing, siding, windows, doors or other enclosing elements have been removed or have not been installed. Inspect protective coverings frequently to ensure that they are functioning properly.
2.3.13 Project Close-out
Posted Operating Instructions: Furnish operating instruction attached to or posted adjacent to equipment. Include wiring diagrams, control diagrams, control sequence, start-up adjustment, operation, lubrication, shutdown, safety precautions, procedures in case of equipment failure and other items of instruction recommended by manufacturer.
Cleaning: Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.
Thoroughly clean building interiors. Pick up and remove all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.
Before submitting a request for final inspection, submit the following:
· Operation and Maintenance Data: As specified below and in Performance Requirements and Specifications.
· Operating Tools: As specified in the individual sections.
· Special Tools: One set of special tools required to operate, adjust, dismantle, or repair equipment. Special tools are those not normally found in possession of mechanics or maintenance personnel.
· System Demonstration and Training: As specified below and in Performance Requirements and Specifications.
· Mechanical and Electrical Systems: Verify the following in writing:
· All systems are complete.
· All systems have been properly started and are operational.
· All controls are complete and operational, and sequences have been checked and are functioning properly.
· Testing and Balancing Report: As required in the technical specifications.
Operation and Maintenance Data: Provide three sets of 3-ring binders with operation and maintenance data, to the Contacting Officer, Project Manager and Contracting Review Officer for review, prior to the final inspection. Data shall include manufacturer's standard literature, equipment data sheets, vendor-furnished as-built drawings; custom written data not included in manufacturer’s standard literature; schedules, warranties, parts lists, test results, and subcontractor list.
After NPS review is completed, incorporate comments, and submit 4 final sets of operation and maintenance data to the CO.
System Demonstration and Training: Train designated personnel in adjustment, operation, including seasonal and emergency operations, if applicable; maintenance; and safety requirements of equipment and systems. Instructors shall be thoroughly trained in operating theory as well as practical operation and maintenance work for each type of equipment or system. The sequence of the training shall follow the approved outline of the training guide; i.e. Operating and Maintenance Data. Individual sections specify the duration of training required. If no duration is listed, provide training of sufficient duration to adequately cover the subjects.
Digital recordings of demonstrations and training sessions:
Provide original and one copy of each recording. Label each digital recording with the date of demonstration or training, the instructor's name, and provide an index of the contents. The index shall list the start and end time of each subject covered during the training session. Provide a separate digital recording for each separate training session.
2.3.14 Substantial Completion and Final Inspection
Submit written certification to the Contracting Officer (CO) that the project, or designated portion of project, is substantially complete, and request a final inspection. Upon receipt of written request that project is substantially complete, the CO will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
When work is determined to be substantially complete, the CO will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The CO will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the CO will notify the DBC in writing. After completing work, the DBC shall resubmit certification and request a new final inspection.
If, following final inspection, the work is determined to be substantially complete, CO will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the CO may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.
Acceptance of the work: After all deficiencies have been corrected, the CO will issue a Letter of Final Acceptance.
2.4 Forms
SUBMITTAL LIST.
Park/PMIS/Project Title
SUBMITTAL
REQUIREMENTS (indicate with an "X")
Spec. Sec.
Par. No.
Description
| INFORMATIONAL |
| ACTION |
| CERT./LAB TEST |
| REPORT/CALC. OR PLAN |
| Mfg. DATA |
& INSTRUCTIONS
| SHOP DRAWING |
| SAMPLE |
| Mfg. DATA |
& INSTRUCTIONS
3.1 PERFORMANCE REQUIREMENTS
3.2 Facility Performance
All work performed shall comply with applicable laws, regulations, and NPS policies and guidelines, http://www.nps.gov/dscw/laws-policies.htm.
3.3 Elements and Products
In addition to requirements specified in other articles, provide products and elements that comply with the following:
· Where “no substitutions” is indicated, use only the product (or one of the products) specified.
· Products:
· Where a product is specified only by a manufacturer name and model number/brand name, the Contractor shall use only that model/brand product.
· Where the properties of a product are specified by description and/or with performance criteria, the Contractor shall use products that comply with the description and/or performance criteria. (preferred)
· Where manufacturers are listed for a particular product, the Contractor shall use a product made by one of those manufacturers that also complies with other requirements.
· Where actual brand name products are not identified by either the CO or the Contractor, the DBC shall identify the products to be used.
· During Construction:
· The Contractor shall identify actual brand name products used for every product, except commodity products specified by performance or description.
· Where a product is specified by performance requirements with test methods, and if so specified, the Contractor shall provide test reports showing compliance.
· The Contractor shall provide manufacturer's product literature for each brand name product.
o The Contractor shall provide the manufacturer's certification that the product used on the project complies with the contract documents.
· Before End of Closeout:
o The Contractor shall provide copies of all manufacturer warranties that extend for more than one year after completion.
4.0 TECHNICAL REQUIREMENTS
**See separately attached technical specifications**
5.0 ATTACHMENTS
See attached inspection report image1.png image2.png