A04_-_Statement_of_Work_(SOW)_Updated.pdf

PDF 2 MB Posted

Attached to
FLAGPOLE ENHANCEMENT WITHIN FORT FREDERICA
Solicitation number
140P5426R0008
Issued by

About this file

This is a Statement of Work (SOW) for flagpole restoration and beautification services at Fort Frederica National Monument, issued by the National Park Service (NPS) located at 6515 Frederica Road, St. Simon Island, Georgia 31522.

The project encompasses five primary tasks: (1) flagpole surface preparation and coating rehabilitation using lead-safe work practices with non-abrasive methods, applying an epoxy corrosion-inhibiting primer, high-build epoxy intermediate coat, and UV-resistant aliphatic polyurethane finish coat in white, achieving 8-12 mils total dry film thickness; (2) installation of new underground electrical service consisting of a 120-volt, single-phase, 20-amp branch circuit from the Visitor Center (approximately 185 feet) installed in 2-inch PVC Schedule 80 conduit with 24 inches minimum earth cover, including two in-grade LED luminaires, transformer, GFCI receptacle, and astronomical timer; (3) construction of a 4-foot-wide concrete walkway with minimum 4-inch thickness and Faux Tabby Finish using washed oyster shell broadcast over freshly placed concrete; (4) construction of a non-structural brick-clad pedestal around the existing flagpole footing using modular brick in running bond with 3/8-inch mortar joints, marine-grade plywood sheathing, weather-resistive barrier, and precast concrete cap, with total finished height not exceeding 49 inches; and (5) furnishing and installation of two exterior powder-coated metal benches anchored to concrete surfaces. The contractor must designate a Lead Competent Person and maintain EPA RRP certification with at least one EPA Certified Renovator on-site during lead-disturbing activities. Pre-mobilization deliverables include project work plans, product data sheets, coating system specifications, and material samples. Closeout deliverables require waste disposal documentation, DFT measurement records, equipment warranties, and operational demonstrations. The project emphasizes protection of historic resources in compliance with the Secretary of the Interior's Standards, requires coordination with the Park Representative with 48-hour advance notice for inspections, and mandates that all non-conforming work be corrected at no additional cost to the Government.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FORT FREDERICA NATIONAL MONUMENT

FLAGPOLE RESTORATION AND BEAUTIFICATION

NATIONAL PARK SERVICE (NPS)

1.0 BACKGROUND

Fort Frederica National Monument (FOFR) preserves significant 18th-century cultural resources and provides visitor services within a historically sensitive landscape setting. The flagpole area near the Visitor Center is a focal point for visitor arrival and interpretation. Address: 6515 Frederica Rd. St. Simon Island, GA 31522.

Existing conditions include deteriorated coating on the steel flagpole, limited nighttime visibility of the flag, aging pedestrian surfaces, and a lack of coordinated site furnishings in the area.

This project improves the functionality and visual integration of the flagpole area while maintaining compatibility with the historic character of the Visitor Center setting.

Project objectives include:

• Installing lighting to allow the flag to be flown in accordance with flag display practices during evening hours

• Rehabilitating the flagpole to prevent corrosion and extend service life

• Constructing a Faux Tabby Finish concrete sidewalk surface that reflects the existing materials and character of the Visitor Center site

• Providing a brick-clad pedestal that visually anchors the flagpole while remaining non-structural

• Installing benches to improve visitor comfort and site use

2.0 SCOPE OF WORK

The Contractor shall provide all labor, supervision, materials, equipment, tools, transportation, and incidentals necessary to complete the following work at the FOFR flagpole area:

• Perform surface preparation and full coating rehabilitation of the existing steel flagpole

• Provide underground electrical service from the Visitor Center to the flagpole area

• Install lighting, transformer, controls, pedestal, and associated conduit systems

• Construct new concrete walkway areas with Faux Tabby Finish

• Construct a framed and brick-clad architectural pedestal around the existing flagpole footing

• Furnish and install two exterior benches

Work includes coordination of construction sequencing to protect new and existing site features and to prevent conflicts between trades.

3.0 TASKS

3.1 – Flagpole Surface Preparation and Coating (Lead-Based Paint Compliance)

3.1 – Flagpole Surface Preparation and Coating

Laboratory testing has confirmed the presence of lead-based paint on the existing steel flagpole. All surface preparation and coating activities shall be performed in accordance with applicable lead-safe work practices and environmental protection requirements.

The Contractor shall rehabilitate the existing steel flagpole coating system using non-abrasive, lead-safe surface preparation methods. Open abrasive blasting is prohibited.

The Contractor shall remove the halyard, cleats, and accessories as necessary to complete the work.

Surface preparation shall be limited to the removal of loose rust, scale, and deteriorated coatings using methods such as:

• Hand scraping

• Hand sanding

• Power tool cleaning only when equipped with integral shrouds and HEPA vacuum attachments

Surface preparation shall achieve a condition equivalent to SSPC-SP 2 (Hand Tool Cleaning) and SSPC-SP 3 (Power Tool Cleaning) sufficient to provide sound substrate and adequate adhesion for the specified coating system.

All work shall be conducted in compliance with OSHA 29 CFR 1926.62 (Lead in Construction). The Contractor shall implement lead-safe work practices including, but not limited to:

• Establishment of a regulated work area

• Use of appropriate personal protective equipment

• Prohibition of dry sweeping or uncontrolled dust generation

• Use of HEPA-filtered equipment

• Daily cleanup of work areas

Containment Requirements (Exterior Work):

• Provide ground containment consisting of secured polyethylene sheeting extending a minimum of 10 feet from the base of the flagpole

• Prevent migration of paint chips, dust, or debris beyond the containment area

• Collect, containerize, and properly dispose of all lead-contaminated waste in accordance with federal, state, and local regulations

• Maintain the work area free of visible debris at the end of each workday

Following surface preparation, the Contractor shall apply a compatible high-performance coating system consisting of:

• Epoxy corrosion-inhibiting primer

• High-build epoxy intermediate coat where required

• UV-resistant aliphatic polyurethane finish coat, color white

Coatings shall be applied only within manufacturer-recommended environmental limits.

The coating system shall achieve a total Dry Film Thickness (DFT) between 8 and 12 mils with individual coat thicknesses as follows:

• Primer: 2–4 mils DFT

• Intermediate: 4–6 mils DFT

• Finish: 2–3 mils DFT

DFT shall be verified using a calibrated dry film thickness gauge in accordance with ASTM D7091. Areas failing to meet specified DFT requirements shall be recoated.

Upon completion, the Contractor shall reinstall all removed hardware and verify proper flag operation.

3.2 – Electrical Service and Lighting Installation

The Contractor shall install new electrical service to the flagpole area.

The Contractor shall provide one continuous 120-volt, single-phase, 20-amp branch circuit from the Visitor Center electrical panel to the flagpole-area lighting pedestal. The distance is approximately 185’. Conductors shall be copper and shall be no smaller than #12 AWG. Conductors shall be sized to limit voltage drop to 3% maximum at the pedestal under the actual connected load, and conductors shall be upsized as required.

The branch circuit shall be installed in 2-inch diameter PVC Schedule 80 conduit. Underground conduit shall be installed with a minimum of 24 inches of earth cover. Approximately 85 linear feet of conduit shall be installed by directional boring beneath existing sidewalks and the parking area. The conduit shall be installed as a continuous run without underground splices and shall include a pull string.

The Electrical Contractor shall furnish and install a corrosion-resistant Unistrut-mounted pedestal assembly. The pedestal shall support a weatherproof GFCI receptacle with an in-use cover, an outdoor-rated step-down transformer, and an astronomical timer control.

Low-voltage lighting conductors shall be installed in a separate conduit system extending from the transformer to each fixture location.

The Contractor shall install two (2) in-grade, walk-over rated LED luminaires in the concrete at the locations shown on the drawings.

3.3 – Concrete Walkway with Faux Tabby Finish

The Contractor shall place new concrete 4’ wide walkway sections with a minimum thickness of 4” using air-entrained concrete with a minimum compressive strength of 4,000 psi.

• The walkway surface shall receive a Faux Tabby Finish.

• Washed oyster shell shall be broadcast over the surface of freshly placed concrete.

• The shells shall be embedded to achieve approximately one-sixteenth inch of mortar cover.

• A surface retarder shall be applied to delay the set of surface paste.

• After initial curing, the surface shall be washed to expose the shell.

• The contractor shall cut control joints at spacing to match existing concrete surfaces.

• The surface shall then be cured and sealed.

Full-depth expansion joints shall be installed wherever new concrete abuts existing concrete.

3.4 Brick-Clad Pedestal Construction

The Contractor shall construct a non-structural architectural pedestal around the existing flagpole footing.

The pedestal core shall consist of pressure-treated framing with marine-grade plywood sheathing. A continuous capillary break shall be installed between the concrete footing and wood framing.

The sheathing shall be covered with 30-pound asphalt felt or equivalent weather-resistive barrier. A minimum one-inch air cavity shall be maintained between the WRB and the brick veneer. Brick ties shall be corrosion resistant.

Brick veneer shall consist of modular brick laid in running bond with 3/8-inch mortar joints. The veneer shall be constructed to fifteen courses in height, approximately 39⅜ inches to the underside of the cap.

Through-wall flashing and weep openings shall be provided at the base of the veneer.

A precast concrete cap with drip edges shall be installed. The total finished height of the pedestal shall not exceed 49 inches.

3.5 – Site Furnishings Installation

The Contractor shall furnish and install two exterior benches. Benches shall be powder-coated metal or approved equal and shall be anchored to concrete surfaces in accordance with manufacturer instructions.

4.0 REQUIREMENTS

The following material and performance requirements apply to the work described in Section 3.0 Tasks.

4.1 Flagpole Coating System Requirements

4.1.1 Lead Based Paint Preparation

Work under this contract involves disturbance of coatings confirmed to contain lead. The Contractor shall comply with all applicable federal, state, and local regulations governing work involving lead-based paint.

Personnel Qualifications

• The Contractor shall designate a Lead Competent Person in accordance with OSHA 29 CFR 1926.62 (Lead in Construction). The Competent Person shall be present during lead-disturbing activities and shall be responsible for implementation of lead-safe work practices, establishment of regulated areas, and oversight of containment.

• The Contractor shall be a firm certified under the EPA Renovation, Repair, and Painting (RRP) Rule (40 CFR Part 745 Subpart E).

• The Contractor shall have at least one EPA Certified Renovator assigned to the project and available during work involving disturbance of painted surfaces.

Work Practices

• All work shall be performed using lead-safe work practices that minimize the generation and dispersion of lead-containing dust and debris.

• Open abrasive blasting, uncontained sanding, grinding, or other high-dust-generating methods are prohibited.

• Power tools shall be equipped with integral shrouds and HEPA-filtered vacuum systems.

• Dry sweeping, use of compressed air, or other methods that disperse dust into the air are prohibited unless used in conjunction with HEPA filtration.

Containment and Control

• The Contractor shall establish a regulated work area to restrict access during lead-disturbing activities.

• Provide ground containment consisting of secured polyethylene sheeting extending a minimum of 10 feet from the work area or as required to fully contain debris.

• Containment measures shall be sufficient to prevent migration of dust, chips, or debris to adjacent surfaces, soil, or visitor areas.

• At the end of each workday, all visible debris shall be collected and removed from the site or secured within containment.

Cleaning and Waste Management

• All debris, paint chips, dust, and disposable materials generated during the work shall be collected, containerized, and disposed of in accordance with applicable regulations.

• Cleaning of work areas shall be performed using HEPA vacuuming and/or wet cleaning methods.

• Waste shall not be buried, dispersed, or left on park property. All waste shall be disposed of by the Contractor in accordance with Local, State, and Federal Regulations for disposal of lead-based paint.

Coating materials shall comply with the following performance standards:

• Surface preparation abrasives shall conform to SSPC-AB 1 (Mineral and Slag Abrasives) or approved equal.

• Surface preparation shall achieve a surface profile appropriate for the coating system, typically 1.5 to 3.0 mils, verified in accordance with ASTM D4417.

• Epoxy primer and intermediate coatings shall be high-performance industrial coatings meeting MPI #108 (Epoxy

Primer, Rust-Inhibitive) and MPI #154 (High-Build Epoxy), or approved equal, and shall be compatible as a complete system.

• The finish coat shall be an aliphatic polyurethane meeting MPI #72 (Aliphatic Polyurethane) or approved equal.

• Dry Film Thickness (DFT) measurements shall be taken in accordance with ASTM D7091 using a calibrated gauge.

4.2 Electrical Materials Requirements

Electrical materials shall comply with the following:

• Conduit materials shall comply with UL 651 for rigid PVC conduit and shall be Schedule 80 where exposed.

• Conductors shall comply with ASTM B3 and shall be rated THWN-2 or approved equal.

• All fittings and enclosures shall be listed for wet locations.

4.3 Faux Tabby Concrete Requirements

Concrete materials shall comply with the following:

• Ready-mixed concrete shall conform to ASTM C94.

• Portland cement shall meet ASTM C150 Type I or II.

• Fine and coarse aggregates shall meet ASTM C33.

• Air entrainment shall comply with ASTM C260.

• Surface retarder shall be a commercially manufactured product intended for exposed aggregate finishes.

4.4 Brick Veneer Requirements

Masonry materials shall comply with the following:

• Brick units shall conform to ASTM C216, Grade SW.

• Mortar shall conform to ASTM C270 Type N.

• Flashing materials shall comply with ASTM D226 for asphalt felt or approved equal.

• Brick color shall be Manufacturer’s standard color, color TBD, subject to Government approval.

4.5 Bench Requirements

Benches shall be constructed of precast concrete or molded recycled plastic (poly) designed for exterior use in public settings. Materials shall be resistant to corrosion, rot, and UV degradation.

• Bench color shall be Manufacturer’s standard color, color TBD, subject to Government approval.

• Fasteners and anchorage hardware shall be stainless steel meeting ASTM F593 or hot-dipped galvanized in accordance with ASTM A153.

5.0 DELIVERABLES

The Contractor shall provide the following documentation for review and acceptance.

5.1 Pre-Mobilization Deliverables

The following items shall be submitted and approved prior to the start of field work.

General

Task 1 – Flagpole Coatings

Task 1A

• Project work plan and schedule describing sequencing of tasks

• Site logistics and equipment staging plan

• Documentation of Lead Competent Person training

• Proof of EPA RRP Firm Certification

• Copy of Certified Renovator credentials

• Lead-safe work plan describing containment, work methods, and waste handling procedures

Task 1B

• Coating system product data sheets

• Abrasive media product data

• Containment method description

• Manufacturer application instructions

Task 2 – Electrical

• Lighting fixture cut sheets

• Transformer and astronomical timer data

• Pedestal mounting hardware data

• Conduit and conductor product data

Task 3 – Faux Tabby Concrete

• Concrete mix design

• Oyster shell sample

• Surface retarder product data

• Sealer product data

Task 4 – Brick Pedestal

• Brick product data

• Brick color sample (color TBD)

• Mortar product data

• WRB and flashing product data

• Precast cap product data

Task 5 – Benches

• Bench product data

• Bench color sample (color TBD)

• Anchorage hardware data

5.2 Closeout Deliverables

The following items shall be submitted upon completion of work.

General

• As-built documentation showing underground conduit routing and depths

• Confirmation of site cleanup

Task 1 – Flagpole Coatings

Task 1A

The Contractor shall provide the following upon completion of work involving lead-based paint:

• Waste disposal documentation, including manifests and receipts for all lead-contaminated materials removed from the site

• A signed statement certifying that all work was performed in accordance with OSHA 29 CFR 1926.62 and specified lead-safe work practices

• Documentation identifying the designated Lead Competent Person responsible for oversight of the work

• Confirmation that all containment materials, debris, and visible dust have been removed and that the work area has been cleaned using HEPA and/or wet cleaning methods

• Photographic documentation of containment and final site conditions (optional but recommended)

Task 1B

• Coating manufacturer warranty

• DFT measurement records

Task 2 – Electrical

• Lighting system operational demonstration

• Equipment warranties

Task 3 – Faux Tabby Concrete

• Product data for concrete sealer

Task 4 – Brick Pedestal

• Product warranties for materials

Task 5 – Benches

• Manufacturer warranty documentation

6.0 RESOURCE PROTECTION

All work shall be conducted in a manner that protects historic, cultural, and natural resources within Fort Frederica National Monument.

6.1 Historic Resource Compliance

All activities shall comply with the Secretary of the Interior’s Standards and Guidelines for the Treatment of Historic Properties. Work shall avoid unnecessary disturbance to historic features, structures, and landscapes.

No historic materials or features shall be altered, removed, or damaged except as specifically authorized.

6.2 Archeological Sensitivity

Ground-disturbing activities occur in an area of known archeological sensitivity.

• Archeological monitoring may be required during excavation or subsurface work as directed by the Government.

• The Contractor shall coordinate with the COR prior to beginning any ground disturbance.

If archeological materials, artifacts, or features are encountered:

• Work in the immediate area shall stop immediately.

• The Contractor shall protect the discovery location from disturbance.

• The Contractor shall notify the COR at once.

• Work shall not resume in the affected area until authorized by the Government.

6.3 Protection of Existing Features

The Contractor shall protect existing pavement, structures, utilities, vegetation, and site features from damage.

Construction equipment shall not operate outside approved work limits.

6.4 Waste and Debris Control

Debris, blasting media, packaging, and construction waste shall be contained and removed from the site. No materials shall be buried or left on park property.

6.5 Public and Visitor Safety

Work shall be conducted to minimize disruption to visitor circulation. Temporary barriers, signage, and closures shall be provided as required by the approved safety and logistics plan.

7.0 QUALITY ASSURANCE / INSPECTIONS

The Contractor is responsible for quality control of all work and shall perform all inspections, measurements, and tests necessary to ensure compliance with the Contract requirements.

The Government may conduct quality assurance observations. Such observations do not relieve the Contractor of responsibility for proper construction.

7.1 Contractor Quality Control

The Contractor shall provide competent supervision and inspection of all work. The Contractor shall verify that materials, installation methods, and finished work comply with the requirements of this Scope of Work.

Work that does not meet specified requirements shall be corrected at no additional cost to the Government.

7.2 Inspection Coordination

The Contractor shall notify the Park Representative a minimum of 48 hours in advance of work requiring inspection or observation.

The Contractor shall not proceed with the following work until it has been observed by the Park Representative, where applicable:

• Surface preparation of the flagpole prior to application of primer

• Installation of underground conduit prior to backfill

• Installation of flashing and weeps prior to completion of brick veneer

• Completion of the Faux Tabby test panel

• Final installation and aiming of lighting fixtures

7.3 Coatings Verification

The Contractor shall measure and document Dry Film Thickness (DFT) in accordance with ASTM D7091. Records shall be provided to the Park Representative upon request.

7.4 Mockup Standard

The approved Faux Tabby test panel shall serve as the visual standard for acceptance of the finished concrete work.

7.5 Final Acceptance

Final acceptance will be based on:

• Conformance with approved submittals

• Proper operation of lighting systems

• Completion of surface coatings

• Completion of masonry and site work

• Submission of required deliverables

02-SOW.pdf
1.0 BACKGROUND
2.0 SCOPE OF WORK
3.0 TASKS
3.1 – Flagpole Surface Preparation and Coating (Lead-Based Paint Compliance)
3.2 – Electrical Service and Lighting Installation
3.3 – Concrete Walkway with Faux Tabby Finish
3.4 Brick-Clad Pedestal Construction
3.5 – Site Furnishings Installation
4.0 REQUIREMENTS
4.1 Flagpole Coating System Requirements
4.1.1 Lead Based Paint Preparation
Personnel Qualifications
Work Practices
Containment and Control
4.2 Electrical Materials Requirements
4.3 Faux Tabby Concrete Requirements
4.4 Brick Veneer Requirements
4.5 Bench Requirements
5.0 DELIVERABLES
5.1 Pre-Mobilization Deliverables
5.2 Closeout Deliverables
6.0 RESOURCE PROTECTION
6.1 Historic Resource Compliance
6.2 Archeological Sensitivity
6.3 Protection of Existing Features
6.4 Waste and Debris Control
6.5 Public and Visitor Safety
7.0 QUALITY ASSURANCE / INSPECTIONS
7.1 Contractor Quality Control
7.2 Inspection Coordination
7.3 Coatings Verification
7.4 Mockup Standard
7.5 Final Acceptance

Sketch SOW.pdf