A04_Statement_of_Work.pdf

PDF 5 MB Posted

Attached to
Government housing landscaping at Lake Mead Nation
Solicitation number
140P8122Q0012
Issued by

View the file

Other files

File Type Posted
Questions_and_Answers_0001.pdf PDF
Sol_140P8122Q0012_Amd_0001.pdf PDF
B11_Site_Visit_Sign_in_Sheet_0001.pdf PDF
B08_Invoice_Payment_Request.docx DOCX document
Sol_140P8122Q0012.pdf PDF
B08_Release_of_Claims.pdf PDF
B08_Transmittal.pdf PDF
B03_General_Decision.pdf PDF
B08_Contract_Price_Schedule.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LAKE MEAD NATIONAL RECREATION AREA

BOULDER CITY, NEVADA

Replace Housing Fencing, Irrigation, and Landscape

(Boulder Beach, Las Vegas Bay, and Callville Bay)

Contract Requirements

NATIONAL PARK SERVICE

November 1, 2021

DIVISION 1 GENERAL REQUIREMENTS

SECTION 01110 SUMMARY OF WORK

1.1 DESCRIPTION

The project is located at Lake Mead National Recreation Area. The locations inside the park are Boulder Beach Las Vegas Bay, and Callville Bay Housing Area.

The work covered by this contract consists of, but not limited to;

A. (IRRIGATION SYSTEM: LINES, HEADS, VALVES, TIMERS, AND PVB) Remove and dispose of existing old and outdated irrigation systems and replacing with all new components. This includes removing the irrigation control valves, control boxes, existing backflow devices, irrigation water lines, bubbler heads etc. The old system will need to be remove from the project site and legally dispose of them into a landfill or incinerator outside the park. The new system will be mostly above ground system.

(beside the water lines going to each tree/brush) (Example - Pictures #1 and #2 in the specs) to have a better understanding.

1. The new pressure vacuum breaker (PVB) will be brass and will have two shut off valves on the device and union coupling on each end for replacement in the future. (Picture #1 has an example) This new PVB is a testable device that will need to be tested/check annual by our Utility Branch here at Lake Mead. The PVB will need to be installed 12 inches minimum above the highest sprinkler head/bubbler head in use. This new PVB will need to have a control box over it. The control box will need to removal and secure in a way that the wind does not blow it away.) All pipes before and after the PVB will be insulated for below freezing temperatures. (ONLY

THE PIPES THAT ARE ABOVE GROUND)

2. All new irrigation lines leading out of the control box will be ¾ inch PVC (polyvinyl chloride pipe –color white – “schedule 40”). This includes all the fixing that will be used to connect the lines to together. This new line will need to be trench below the ground surface approximately 5 – 6 inches below grade. The new bubbler heads going to each tree/bush will have a ½ inch plastic riser coming out of the ground. The new riser will need to be approximately 4- 5 inches above the ground surface. The new bubbler heads will need to be adjustable to change the water flow to each tree/bush. (example will be in Picture #4 in the specs)

3. The new irrigation control valves will be above ground valves.

(example in picture #1 in the specs) These valves will be above ground anti-siphon valves. Must be installed upright and no valve can be located downstream of the antisiphon valve. The new anti-siphon must be at least 6 inches above the highest sprinkler/bubbler head. These new valves will need to have a control box over it. The control box will need to removal and secure in a way that the wind does not blow it away.

4. The new irrigation control timer will need to be an exterior timer.

This timer will need to have an exterior cover plate to protect the control bottoms and screen from the sun UV rays. (example in picture #3) Contractor may use existing irrigation wire (if present) in the old box to wirer new timer. The outlet that is powering the timer will need to have an exterior outlet cover installed. The existing timer does not have this cover. (example #5 in specs)

*NOTE* All irrigation lines and trenches will be inspected by the Contracting Officer Representative (COR) before any lines, fixing, valves, bubbler heads etc. are cover with dirt material. The new irrigation system will be turn on and inspected by the COR of any leaks that might be present before backfilling. The contractor will need to schedule this walkthrough with the COR.

B. (REMOVING TREES AND STUMPS) Removing existing and or dead trees around the housing area includes old stumps. The stumps will need to be removed completely or grind below the ground surface. (approximately 4 to 6 inches below grade) The vegetation and debris will need to be remove from the project site and legally dispose of them into a landfill or incinerator outside the park. Contractor will use dirt material around the work area to back fill the hole to level ground.

C. (REPAIRING/REPLACING CHAIN LINK FENCE and INSTALL NEW CHICKEN WIRE MESH) Replacing old chain link fence, poles, top rails and the fence doors that are broken and or damage. Many of the fences in the housing area are broken, rusted though, not in line anymore etc. Doors are not closing properly due to the above. The existing fence is approximately 4 feet high. In addition, install all new ½ inch Hardware Cloth galvanized 19-gauge chicken wire mesh around the perimeter of new and existing fence line. The new galvanized mesh needs to be approx. 20 inches high from the ground surface. Contractor will need to use high gauge wire to secure to chain link fence (this galvanized mesh is to keep snake out of the backyards.)

D. (NEW LANDSCAPING MATERIAL) Removing old landscape materials (dirt and rocks approximately ¼ inch – 18 inches in size or smaller. *Bigger boulders may need to be moved and then place back for yard decoration) and installing new landscape material.

Only about 3-4 inches from the ground surface needs to be removed. New material will be 3/8 minus dirt material. (gold in color. Match what existing color at Quarters #407 and Quarters #408) Weed barrier fabric will be installed before new dirt material is installed. New material will need to be at least 2 inches deep and not topping or flowing over the street or sidewalk curve lip. The new landscape dirt will be slope/graded away from the housing foundation. The old material will need to be haul outside the park or can be used to help with the sloping around each of the houses before the new material is installed. Once the new 3/8 minus dirt materials is installed it will need to wet down with water and a plate compacter machine will be used to compact the new material together. Contractor may use the water spigots at each of the houses for the water supply. Each existing tree(s) will have a moat around the whole base of the tree. Contractor will have to remove any weeds, brushes, or vegetation that "may” grow from the schedule site visit to when the contractor receives the notice to proceed from the Contracting Officer.

E. (INSTALL NEW RETAINING LANDSCAPE BRICK WALL) Pavestone, Rampart BevF Tan 6 x 16 retaining wall block or equivalent. Liquid Nail Landscape block adhesive or equivalent. 5/8” crushed rock or equivalent base material. The retaining walls shall be constructed in strict accordance with the specifications, recommendations, and instructions of the retaining wall block manufacture. The base of the retaining wall shall be no closer than 4 feet from the existing chain link fencing, but may, depending on the site conditions, be further from the fencing. The retaining wall shall roughly parallel the existing fencing, in straight, as long as practical, runs. Where the retaining walls change direction, all curves shall be uniform and fair. All retaining walls shall be level to within + or – ½ inch from end to end. The top of the walls shall be flat, in one continuous plane. The height of the retaining walls shall be from the base of the slope to the projected level plane of the associated yard. The walls shall be constructed on a level, compacted base of crushed 5/8-inch rock or equivalent fill, roughly 4 to 6 inches in depth and 24 to 28 inches wide. First course of block shall be embedded a minimum of 4 inches below the surrounding grade. The grade at the base of the wall shall not exceed ½ inch per foot of slope away from the wall base. A minimum of 12” of crushed rock shall be placed and compacted immediately behind the wall and separated from the adjacent existing soil by a geotextile fabric. Clean, landscape appropriate fill shall be placed and compacted behind the crushed rock/geotextile fabric, to bring the yards up to a level, smooth, grade. The top course of retaining wall blocks shall be fixed in place with appropriate landscape block adhesive. The top of the wall shall be topped with wall cap block, held in place with landscape adhesive. The yard area behind the retaining wall shall be filled and graded to be smooth, and in plane with the top course of the retaining wall, and to be sloped away from the house for a fall of 6 to 8 inches.

At the conclusion of the work, all excess material, debris, trash, associated with the work shall be roved from the Park, and the site left in a neat and clean manner.

1.1A WORK TO BE DONE PER LOCATION

A. Quarters #409

1. Remove x3 old stumps. (Approx. 28 inches, 18 inches, and 8 inches in diameter) – x1 front yard, x1 backyard in the fence line, x1 left side of house.

2. Remove x10 dead brushes/trees (left side of house) including the approx. 57 linear feet of existing irrigation line.

3. Trim/cut x5 limb hanging over carport structure of the house and cut x4 dead limbs on the tree in the backyard.

4. Repair fence (left side of the house) replace the man gate door in the backyard (leading toward the lake) and replace the vehicle gate door leading to the front yard. (right and left supporting poles need to be replace. (approx. 35 linear feet)

5. Install approx. 230 liner feet of all new ½ inch Hardware Cloth galvanized 19-gauge chicken wire mesh around the perimeter of new and existing fence line. Approx. 20 inches high from ground.

Remove any existing mesh and dispose out of the park

6. Remove all debris (leafs, trash, and vegetation out of the backyard that is stack up against the fence line and throughout the backyard)

7. Install new retaining landscape wall in the backyard. Approx. 90 liner feet long.

8. Install weed barrier fabric and new 3/8 minus dirt material in the backyard within the fence line. Above and below the new retaining wall. Removing old landscape materials (dirt and rocks approximately ¼ inch in size or smaller) and installing new landscape material. New material will need to be 2 inches in deep.

Will need to wet down with water and a plate compacter machine will be used to compact the new material together. The grade for the new material will need to scope away from the house for drainage.

B. Quarters #411

1. Remove old irrigation system and dispose of it. (Inside and outside the fence) *see below for drawing.

2. Install new irrigation system which will be relocated near/next to the existing water meter control box. Included new pressure vacuum breaker (PVB) - Size 1-inch, new anti-siphon valves, irrigation lines, new sprinkler heads/bubblers, and x2 new control boxes (one over the anti-siphon valve and one over the PVB)

3. Remove x3 trees/brushes and their stumps. (approx. 47 inches, 27 inches, and 34 inches in diameter) – in backyard within fence.

4. Install new control timer and outlet cover. Contractor will need to add wire to the timer due that the irrigation system is being relocated to the other side of the house. The existing timer is located in the carport.

5. Repair fence line (left side of the house – approx. 35 linear feet), replace the man gate door in the backyard (leading toward the lake), and replace the vehicle gate door leading to the front yard, and replace man gate door on left side of house next to carport.

6. Install approx. 215 liner feet of all new ½ inch Hardware Cloth galvanized 19-gauge chicken wire mesh around the perimeter of new and existing fence line. Approx. 20 inches high from ground Remove any existing mesh and dispose of out of the park

7. Trim x4 limb hanging over carport structure of the house and one limb handing over housing unit # 410) * Contractors will need watch out for any utilities.

8. Remove x4 dead stumps. (x2 front yards and x2 left side of the house)

9. Install new retaining landscape wall in the backyard. Approx. 87 liner feet long.

10. Install weed barrier fabric and new 3/8 minus dirt material in the backyard within the fence line. Above and below the new retaining wall. Removing old landscape materials (dirt and rocks approximately ¼ inch in size or smaller) and installing new landscape material. New material will need to be 2 inches in deep.

Will need to wet down with water and a plate compacter machine will be used to compact the new material together

C. Quarters #501

1. Remove old irrigation system and dispose of it.

2. Install new irrigation system which will be located near/next to the existing water meter control box. Included new pressure vacuum breaker (PVB), new anti-siphon valves, irrigation lines, new sprinkler heads/bubblers, and x2 new control boxes (one over the anti-siphon valve and one over the PVB)

3. Remove x2 tall palm trees and their stumps (outside the fence)

4. Remove x1 Oleander bush/tree on the backyard (inside the fence line)

5. Install new control timer “wire” to existing timer. The existing timer is located in the carport. Contractor can install wirer on the edge of roof line under the facial with clamp wirer holders to get to the timer.

6. Repair fence. Replace the vehicle gate door in the backyard leading toward the front of the house, (Opening approx.10ft 3inch). x6 fences poles need to be replaced completely due to rust and no longer in tack. Secure the top rail as well.

7. Install approx. 215 liner feet of all new ½ inch Hardware Cloth galvanized 19-gauge chicken wire mesh around the perimeter of new and existing fence line. Approx. 20 inches high from ground Remove any existing mesh and dispose off out of the park

8. Remove concrete slap in the backyard near vehicle gate door and legally dispose of material into a landfill or incinerator outside the park. Grade surface to match exist level and surrounding area.

9. Install weed barrier fabric and new 3/8 minus dirt material in the backyard within the fence line. Removing old landscape materials (dirt and rocks approximately ¼ inch in size or smaller) and installing new landscape material. New material will need to be 2 inches in deep. Will need to wet down with water and a plate compacter machine will be used to compact the new material together. New materials will need to be scope away from the house for drainage.

D. Quarters #550 Fence

1. Repair/replace fence. Repair the vehicle gate door in the backyard leading toward the front of the house (right side of the house), (Opening approx.11 feet). x11 fences poles need to be replaced completely due to rust and no long in tac. Top rail needs to be replaced and or repair and secure to new post/poles.

2. Install approx. 215 liner feet of all new ½ inch Hardware Cloth galvanized 19-gauge chicken wire mesh around the perimeter of new and existing fence line. Approx. 20 inches high from ground.

Remove any existing mesh and dispose off out of the park.

3. Remove any vegetation that will be touching the fence line.

(vegetation that is dead or alive)

E. Quarters #551 Fence

1. Repair/Replace fence. Repair the vehicle gate door in the backyard leading toward the front of the house (right side of the house), (Opening approx.11 feet). x9 fences poles need to be replaced completely due to rust and no long in tac. Top rail needs to be replaced and or repair and secure to new post/poles.

2. Install approx. 220 liner feet of all new ½ inch Hardware Cloth galvanized 19-gauge chicken wire mesh around the perimeter of new and existing fence line. Approx. 20 inches high from ground.

3. Remove any vegetation that will be touching the fence line.

(vegetation that is dead or alive)

F. OPTION LINE: Quarters #409 Front Yard Landscape

1. Install weed barrier fabric and new 3/8 minus dirt material in the front yard of house. Approx. 1,841 square feet See picture below (The house to the street cub) Removing old landscape materials (dirt and rocks approximately ¼ inch in size or smaller) and installing new landscape material. New material will need to be 2 inches in deep. Will need to wet down with water and a plate compacter machine will be used to compact the new material together. New materials will need to be scope away from the house for drainage.

G. OPTION LINE: Quarters #411 Front Yard Landscape

1. Install weed barrier fabric and new 3/8 minus dirt material in the front yard of house. Approx. 2,236 square feet (The house to the street cub) Removing old landscape materials (dirt and rocks approximately ¼ inch in size or smaller) and installing new landscape material. New material will need to be 2 inches in deep.

Will need to wet down with water and a plate compacter machine will be used to compact the new material together. New materials will need to be scope away from the house for drainage

1.2 LOCATION

Las Vegas Bay and Boulder Beach Housing area. Below are the Lat/Long of each of the areas.

(Best to copy and paste this into google)

A. Boulder Beach Housing Area: 36.044629, -114.814147

B. Las Vegas Bay Housing Area: 36.118388, -114.870579

C. Callville Bay Housing Area: 36.140841, -114.728515

1.3 PERFORMANCE PERIOD: The project schedule is based on calendar days from the period of performance (POP) start date.

The total performance period for this project is 120 calendar days. (4 months)

1.4 FIELD VERIFICATION

A. The Contractor shall field verify all existing conditions affecting the work in this contract before ordering any materials, equipment or parts. The scheduling of field verification site visits shall be coordinated with the COR. *(Note that these measurements are estimates only. It is the contractor’s responsibility to ensure the accuracy of their measurements)

1.5 CONTRACTOR'S USE OF PREMISES

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to our park tenants which are employees that work at Lake Mead National Recreation Area.

B. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

C. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for interruption of existing utility service, if appropriate.

1. Contractor shall be responsible for locating and preventing damage to known utilities before starting any work or digging. If damage occurs, repair of the utility at no additional expense to the Government.

D. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials according to the Department of Transportation.

E. Work Limits: The Contractor shall be confined to conduct his work to job site area and work limits as shown on drawings or approved by the Contracting Officer. Contractor shall be responsible to pay for rehabilitation work for any resource damage outside authorized work limits.

F. Care shall be taken to ensure that fuel, oil and other spills do not occur. If spills occur, cleanup will be completed at no additional expense to the Government.

1.6 DESIGNATED OFFICIALS

A. The NPS Contracting Officer's Representative (COR)/Inspector will be:

Bret Satowski, Housing Officer, Lake Mead NRA Telephone: 702-305-7267 E-mail: bret_satowski@nps.gov

B. The Contracting Officer (CO) will be:

Jim Read Telephone: 760-252-6112 E-mail: jim_read@nps.gov

1.7 TIME OF CONDUCTING WORK

A. All work will be completed during the hours of 7:00 AM to 5:00 PM local time (Monday – Friday) due to the tenants that are living in the housing area. If the time needs to be changed the contractor will need to get approval from the Lake Mead Housing Program Manager and the Contraction Officer.

1.8 WORK/CONSTRUCTION SCHEDULE

A. The Contractor shall provide a work/construction schedule to the Contractor Officer Representative (COR) and the Contractor Officer (CO) before any work begins. This will give the tenants a heads up on when will begin around their house.

1.9 CLEANING JOB AFTER COMPLETED

A. All driveway, sidewalks, roads, patios, and or porches will be brushed off and/or power washed before leaving the job site.

END OF SECTION 01010

SECTION 01170 ACCIDENT PREVENTION

1.1 DESCRIPTION

A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

B. The Contractor shall be responsible for establishing an effective accident prevention program that accounts for all phases of the work and the methods to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.

1.2 QUALITY ASSURANCE

A. Qualifications of Employees

1. Contractor shall ensure that employees are physically qualified to perform their assigned duties in a safe manner.

2. Contractor shall not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Coordination procedures. Contractor shall ensure that operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment safely.

1.3 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forward to the Contracting Officer a DI 134 form, which may be obtained from the Contracting Officer.

B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

C. FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of work being performed at the site.

D. PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

1.5 EXECUTION

A. EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

B. Protective equipment

1. Contractor shall ensure that personal protective equipment is maintained in a serviceable condition.

2. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

C. Hard hats and protective equipment areas

1. Hard hats shall be worn at all times in locations and conditions as required by OSHA.

2. It is the Contractor's responsibility to require all those working on or visiting the site to wear appropriate protective equipment at all times as required by OSHA.

D. Training

1. First Aid: Provide adequate training to ensure prompt and efficient first aid.

2. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

END OF SECTION 01310

SECTION 01310 PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating operations on this project including, but not limited to the following:

1. Supervisory and administrative personnel.

2. Project meetings.

3. Coordination procedures.

1.2 SUPERVISORY AND ADMINISTRATIVE PERSONNEL

A. General: In addition to the project superintendent, the Contractor shall provide other supervisory and administrative personnel as required for proper work performance. This may include special personnel required for coordination of operations with subcontractors and material suppliers.

1.3 PROJECT MEETINGS

A. Submittals required prior to the Pre-performance meeting.

1. Letter designating the Project Superintendent.

2. Proposed work schedule.

3. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor.

4. Waste and recycling plan.

B. Pre-construction meeting: Once the contract is awarded, an initial orientation meeting will be scheduled for a time and date that is agreeable to the Government and Contractor and will be conducted over the phone. Lake Mead personnel and Contracting Officer will be present to go over any specific requirements of the project with the Contractor and the Contractor’s supervisory and administrative team.

1. Agenda: Items to be discussed will include but not be limited to:

1. Park Rules and Regulations.

2. General correspondence procedures.

3. Payments to the Contractor.

4. Acceptance/rejection of work.

5. Subcontractors.

6. Documents required under contract.

7. Local emergency phone number.

2. Once the start date has been established, the Contractor shall submit the proposed work schedule to the Government for approval.

1.5 PAYMENTS

A. All payments will be submitted online (IPP system)

END OF SECTION 01310

SECTION 01330 SUBMITTALS

A. The intent of this section is to explain submittal requirements before and during construction.

B. This section also includes the requirements for properly handling "Substitutions" and "Comparable Products" the Contractor submits as being "equal" to the product that has been specified.

C. The contractor will submit submittals to the COR for review on the Pressure Vacuum Breaker (PVB) and the anti-siphon valves.

1.2 MODIFFICATIONS

A. Any changes to this contract shall be in writing in accordance with FAR clause 52.212-4(c), Contract Terms and Conditions. The contractor should notify the Contracting Officer immediately.

1.3 GOVERNMENT-FURNISHED ITEMS

A. Government-Furnished Items: Contractor shall use government furniture weed barrier.

The weed barrier is located in the Boulder Beach housing area on the basketball court. (36.043888, - 114.814161) copy and paste into google. It’s the contractors responsible to move weed barrier from the basketball court to each housing located. Government will NOT move it for the contractor.

SECTION 01570 TEMPORARY CONTROLS

A. This Section includes administrative and procedural requirements for providing temporary controls.

1.2 HOUSEKEEPING

A. Keep project site neat, orderly, and in a safe condition at all times.

B. Provide enough containers for collecting debris and materials to be recycled.

C. Keep volatile wastes in covered containers.

1.3 DISPOSAL

A. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.

B. Immediately remove hazardous rubbish from project site. Remove all debris from project site and legally dispose of them into a landfill or incinerator, private dumping areas outside the park. Do not burn or bury refuse inside the park.

1.4 FIRE PROTECTION EQUIPMENT

A. Extinguisher shall have a minimum UL rating of 2-A: 10-B: C. (Should be on the job site at all times)

1.5 AIR AND WATER POLLUTION CONTROL

A. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.

B. Do not dispose of volatile wastes or oils in storm or sanitary drains.

C. Do not allow waste materials to be washed into streams or bodies of water.

1.6 WATER/RESTROOMS

A. Potable water is available on site. Make connections to existing facilities as needed.

Facilities must be cleaned and maintained in a condition acceptable to the NPS.

C. Toilets: Restrooms are not available onsite. Contractors use the restroom facilities at the campground or picnic area which is not near the work site. Contractor may bring portable/mobile restroom on the work site. It’s the contractors responsible to maintain/clean their own restroom. Once work is complete, the contractor has 3 business to remove the unit off the job site and out of the park.

TRAFFIC CONTROLS

A. Traffic Controls: Erect and maintain barricades, lights, danger signals, and warning signs as required for a safe work area.

1. Protect existing site improvements, such as curbs, sidewalks, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

3. Illuminate barricades and obstructions at night.

4. Protect pedestrian traffic when needed.

5. Install Barrier Tape were directed by Contracting Officer.

6. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

B. Perform work in a manner that assures the safety and convenience of the public and protects the workers and property adjacent to the project.

1.8 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.

Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

C. If equipment is used, it will need to be inspected by ONE of the following Individuals. Please contact them to set up appointment before bringing equipment on the job site.

1. Kelley Wallace: Kelly_Wallace@nps.gov; (702) 293-8662 (Biologist)

2. Clayton Merrill: Clayton_Merrill@nps.gov: (702) 293-8650 (Biological Science Technician)

3. Carrie Norman: Carrie_Norman@nps.gov: (702) 293-8734 (Biologist)

4. Bryan Moore: Bryan_Moore@nps.gov: (702)-249-6181 (Biologist)

END OF SECTION 01570

Specs.

Picture #1

Picture #2 mailto:Kelly_Wallace@nps.gov mailto:Clayton_Merrill@nps.gov mailto:Carrie_Norman@nps.gov mailto:Bryan_Moore@nps.gov

Picture #3

Picture #4

Picture #5

PICTURES OF EACH OF THE HOUSING AREA

Quarters # 409 – Trees and Stumps to be removed.

Quarters #411

Retaining Wall

Quarters #501

Qtrs # 550/550 Fence Line

SECTION 01110 SUMMARY OF WORK
1. Letter designating the Project Superintendent.
2. Proposed work schedule.
3. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor.
4. Waste and recycling plan.
1.3 DISPOSAL
A. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.
B. Immediately remove hazardous rubbish from project site. Remove all debris from project site and legally dispose of them into a landfill or incinerator, private dumping areas outside the park. Do not burn or bury refuse inside the park.
A. Extinguisher shall have a minimum UL rating of 2-A: 10-B: C. (Should be on the job site at all times)
1.5 AIR AND WATER POLLUTION CONTROL
A. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.
B. Do not dispose of volatile wastes or oils in storm or sanitary drains.
C. Do not allow waste materials to be washed into streams or bodies of water.
1.6 WATER/RESTROOMS
A. Traffic Controls: Erect and maintain barricades, lights, danger signals, and warning signs as required for a safe work area.
1. Protect existing site improvements, such as curbs, sidewalks, pavement, and utilities.
2. Maintain access for fire-fighting equipment and access to fire hydrants.
3. Illuminate barricades and obstructions at night.
4. Protect pedestrian traffic when needed.
5. Install Barrier Tape were directed by Contracting Officer.
6. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

B. Perform work in a manner that assures the safety and convenience of the public and protects the workers and property adjacent to the project.

1.8 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution...
B. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressur...
C. If equipment is used, it will need to be inspected by ONE of the following Individuals. Please contact them to set up appointment before bringing equipment on the job site.
1. Kelley Wallace: Kelly_Wallace@nps.gov; (702) 293-8662 (Biologist)
2. Clayton Merrill: Clayton_Merrill@nps.gov: (702) 293-8650 (Biological Science Technician)
3. Carrie Norman: Carrie_Norman@nps.gov: (702) 293-8734 (Biologist)
4. Bryan Moore: Bryan_Moore@nps.gov: (702)-249-6181 (Biologist)
END OF SECTION 01570