SECTION 01 11 00
SUMMARY OF WORK
PART 1 – GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
Project Location: This project is located at The Lake Mead Lodge Complex 322 Lake Shore Road, Lake Mead National Recreation Area, Nevada, consisted of the following buildings:
| Building A |
| Annex building - Lodge Rooms 1-8 |
| 2,600 square feet |
| Building B |
| Lodge Rooms 1-19 |
| 5,000 square feet |
| Building C |
| Main Office and Suites |
| 6,000 square feet |
| Building D |
| Lodge Rooms 20-37 |
| 5,000 square feet |
A. The Work consists of the following:
1. All materials, labor, equipment, and incidentals necessary to properly remove and dispose of asbestos containing material (ACM) from four (4) buildings, square footage shown above. Suspected ACM are; but not limited to; floor tiles, domestic water white corrugated paper pipe insulation and mud fittings, floor linoleum, and sprayed acoustical ceiling. The included report dated July 21, 2010 by Mactec Engineering reported the following:
Results of the asbestos survey and sampling indicated the presence of ACM in the following materials:
· 9-inch by 9-inch floor tiles - Buildings A and C
· l-foot by 1-foot floor tile- Buildings A, B, C, and D
· Domestic water white corrugated paper pipe insulation and mud fittings - Buildings B and D.
· Bathroom floor linoleum -Buildings A, B, C, and D.
· Spray-on acoustical ceiling spray - Building C, conference room.
2. All materials, labor, equipment, and incidentals necessary to properly remove and dispose of friable asbestos was noted in the maintenance rooms of Buildings Band D. The friable asbestos was in poor condition in these rooms.
3. All materials, labor, equipment, and incidentals necessary to properly remove and dispose of pad-mounted transformers were observed behind each building. Transformers can contain PCBs. No labeling denoting PCB content was identified on the transformers and based on age and appearance; they are assumed to contain PCBs. The following transformer designations were observed:
| Building |
| Location |
| Transformer Designations |
| Building A |
| Behind Building |
| AA-106 |
| Building B |
| Behind Building |
| AA-107 &AA-257 |
| Building C |
| Behind Building |
| AA-194 & AA-200 |
| Building D |
| Behind Building |
| AA-48 & AA-216 |
4. All materials, labor, equipment, and incidentals necessary to properly remove and dispose of fluorescent lighting typically associated with lamp ballasts. Lamp ballasts can contain PCBs and used light tubes can contain mercury. Used ballasts and 1ight tubes should be disposed of by using approved recycling or disposal vendors. Lamp ballasts and light tubes were observed in Building C. These materials will require specialized handling and disposal.
B. Remove regulated and non-regulated ACM and other hazardous items noted above in accordance with Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA), Nevada Division of Environmental Protection, Nevada Occupational Safety and Health Enforcement Section (OSHES), and Clark County Department of Air Quality (CCDAQ). All friable material must be removed and non-friable material that may crumble during demolition will need to be removed as construction waste. During removal, all materials that contain more than 1% asbestos by weight must be accounted for and removed. The amount of asbestos material leaving the worksite must match the amount delivered to the disposal site, with any conflicts noted and resolved by the project manager. The disposal site must be a site certified by the EPA to dispose of asbestos containing materials.
C. EPA Category I Friable Regulated ACM (RACM) acoustical ceiling spray; OSHA Category II RACM wall texture and joint compound; OSHA Category II Non-Friable and Non-Regulated ACM floor tiles must be abated by a licensed asbestos abatement contractor in order to comply with Federal, State, and County regulations.
D. After the ACM and other hazardous items noted above have been abated from the site, a third-party visual clearance assessment will be performed by an OSHA licensed Asbestos Abatement Consultant in order to comply with Nevada OSHES and CCDAQ regulations.
E. All hazardous materials shall be handled, removed and disposed of in a legal manner, meeting all local and federal requirements and laws. All disposal shall be certified and proof of such, shall be submitted to the Contracting Officer.
F. Performance Period: Shall be 60 calendar days.
1.2 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work.
1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.
3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.
4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.
5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.
B. Government-Furnished Items: The government will furnish the following products or materials for use on this contract: None anticipated.
1.3 PUBLIC USE OF THE SITE
A. General: The project site will be closed to the public during construction. The contractor shall at all times conduct his operations to ensure the least convenience to the public. Temporary closures may be permitted upon specific written approval of the contracting officer.
1.4 CONTRACTOR USE OF SITE
A. General: Limit use of the site during the construction period to the project area limits as outlined on the attached site map. Do not disturb portions of the site beyond the project area limits.
B. Park Entry: The contractor shall furnish a list of personnel with phone contact information. Vehicles associated with the contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees. All vehicles entering the park shall stop at the entrance station for granted access each time entering the park.
C. Site Access: The contractor shall access the project site as outlined on the attached site map. Do not drive vehicles off road or access non-project areas without permission from the contracting officer or park superintendent.
D. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
E. Working Hours: Regular work hours shall be limited to daylight hours from 8:00 a.m. until 5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer.
F. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
G. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified on the attached site map or as established at the preconstruction meeting.
H. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.
I. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
J. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
K. Refer also to Section 01 11 40 Work Restrictions and Section 01 50 00 Temporary Facilities & Controls.
1.5 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are available upon request to supplement the information specified in the contract documents:
1. Final Hazardous Material Evaluation/Abatement Recommendation Report Dated July 21, 2010.
2. Lake Mead Lodge FONSI.
3. Lake Mead Lodge Boundary Map
4. LAME 150265 Annex A Exist Condition Dwgs 5-18-10.
END OF SECTION 01 11 00
LAKE – 220532 Statement of Work image1.emf
Microsoft_Word_Document.docx
LAKE MEAD
NATIONAL RECREATION AREA
Boulder City, Nevada
PMIS No. 220532C
Lake Mead Boulder Beach Motel Lodge Abatement Project
April 2020
CONTRACT SPECIFICATIONS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
image1.jpeg image2.emf
Microsoft_Word_Document1.docx
TABLE OF CONTENTS
NO. OF PAGES
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 3
01 11 40 Work Restrictions 4
01 35 23 Safety Requirements 4
01 50 00 Temp Facilities and Controls 4
01 73 40 Execution 3
01 74 19 Construction Waste Management & Disposal 1
01 77 00 Closeout Procedures 2
02 23 00 Site Clearing 2
APPENDIX
Lake Mead Lodge Boundary Map
LAME 150265 Annex A Existing Condition Dwgs
Final Hazard Evaluation Abatement Report
Lake Mead Lodge Fonsi image3.emf
Microsoft_Word_Document2.docx
SECTION 01 11 40
WORK RESTRICTIONS
1.1 PARK REGULATIONS
A. General: The Contractor must comply with the following rules and conditions:
1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.
2. Ensure equipment is conspicuously marked for identification.
3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.
4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.
5. Control and provide security of Contractor-owned equipment and materials at the work site. Report immediately missing / lost / stolen property to the park dispatch / law enforcement rangers at 702-293-8998 NON-EMERGENCY.
6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
a. Contractor will provide the Contracting Officer with a listing of its subcontractors and their associated vehicles and employees entering the park on a daily basis.
b. Contractor will provide the Contracting Officer with a listing of anticipated deliveries for each week.
7. Vehicles / Heavy Equipment:
a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.
c. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.
e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.
f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the Park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).
j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.
k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11). No loads heavier than the current load rating for the historic Park bridge will be permitted.
8. Emergency Medical and Accident Reporting:
a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.
Emergency number: Dial 911 as needed.
Park Dispatch: 702-293-8932 EMERGENCY
Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park:
Park Dispatch: 702-293-8998 NON-EMERGENCY
1.2 RESOURCE PROTECTION
A. General: The park is committed protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to packing / loading. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance. Contact the resource staff directly at 702-371-9673 or 702-293-8849 at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.
2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact park dispatch at 702-293-8998 immediately if animal is hit or injured or will not move off of the road. All contractor personnel working in Lake Mead National Recreation Area must have up-to-date Lake Mead desert tortoise awareness training. Prior to starting work, contact the resource staff directly at 702-371-9673 or 702-293-8849 at least three (3) business days in advance to schedule the desert tortoise awareness training.
3. Archaeological Resources: Archaeological resources are physical evidences of past human activity, including evidences of the effects of that activity on the environment. Archaeological resources are found above and below ground and underwater. The contractor shall appoint an archaeological monitor during all ground-disturbing activities in archaeological sensitive areas. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.
END OF SECTION 01 11 40
LAKE – PMIS 220532 01 11 40 - 4
WORK RESTRICTIONS
image4.emf
Microsoft_Word_Document3.docx
SECTION 01 35 23
SAFETY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. General: This section includes establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Plan: After contract award and before the Pre-Construction conference, submit for review an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within ten (10) days. No progress payments will be made until the Plan is accepted.
1.3 QUALITY ASSURANCE
A. Comply with contract clauses entitled "Accident Prevention" and "Permits and Responsibilities". In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.
2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
LAKE – PMIS 220532 01 35 23 - 1
SAFETY REQUIREMENTS
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of one hundred dollars ($100). Notify Contracting Officer immediately in the event of a reportable accident. Within seven (7) days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
PART 2 - PRODUCTS
2.1 ACCIDENT PREVENTION PLAN
A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, caveins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
2.2 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.
2.3 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of applicable ANSI standards.
PART 3 - EXECUTION
3.1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 FIRE AND LIFE SAFETY
A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).
B. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain readily available, on site, MSDS for each chemical.
1. Immediately report all spills of hazardous materials to the park.
2. Maintain a spill emergency response kit.
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.4 SAFETY MEETINGS
A. As a minimum, conduct weekly fifteen (15) minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one (1) day after the meeting.
B. Conduct monthly safety meetings for all levels of supervision. Meetings shall be attended by all contractors and subcontractors performing work on the site. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the Accident Prevention Plan. The Contracting Officers Representative will attend the meeting and enter the results of the meetings into the daily log.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment at all times. As a minimum, provide six (6) six hard hats for use by visitors.
3.6 TRAINING
A. First Aid: Provide adequate training to an adequate number of personnel to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 01 35 23
image5.emf
Microsoft_Word_Document4.docx
SECTION 01 50 00
TEMPORARY FACILITIES & CONTROLS
1.1 TEMPORARY FACILITIES AND CONTROLS
A. General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.
1. Temporary Utilities: The following utilities are available for use at the project site:
a. Not Applicable.
2. Temporary Sheds of Field Offices: The construction of temporary sheds, field offices, or structures will not be allowed at the project site. If the contractor requires a temporary office space with a phone connection, the government will attempt to make these accommodations without charge.
3. Site Enclosure Fence: For uncontrolled sites, the contractor shall construct an enclosure fence, barrier, or partition to prevent people and animals from entering the site except by gates / doors.
4. Traffic Controls: The contractor shall erect and maintain barricades, danger signals, and warning signs in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition. The contractor shall provide adequate traffic control, including flaggers or either side of any work performed in the road. Any workers on or near the road must wear highly visible, bright clothing.
END OF SECTION 01 50 00
LAKE – PMIS 220532 01 50 00 - 2
TEMPORARY FACILITIES & CONTROLS
image6.emf
Microsoft_Word_Document5.docx
SECTION 01 73 40
EXECUTION
EXECUTION
EXAMINATION
Retain paragraph and subparagraph below for renovation work. Revise to suit Project.
Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed.
Before beginning work, investigate and verify the existence and location of systems, utilities, and other construction affecting the Work.
Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.
PREPARATION
Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.
Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.
Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents caused by differing field conditions outside the control of the Contractor, submit a request for information to the Contracting Officer in accordance with Division 01 Specification 01 31 00 “Project Management and Coordination”.
INSTALLATION
General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
Make vertical work plumb and make horizontal work level.
Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.
Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.
Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.
Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.
Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.
Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.
Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
PROGRESS CLEANING
This Article refers to regular cleaning operations conducted while construction is in progress. Requirements for final cleaning before Substantial Completion are included in Division 01 Section "Closeout Procedures."
General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.
Site: Maintain Project site free of waste materials and debris.
Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
Remove liquid spills promptly.
Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.
Contractor shall provide progress cleaning that minimizes sources of food, water, and harborage available to pests.
Concealed Spaces: Remove debris from concealed spaces before enclosing the space.
Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.
Limiting Exposures: Supervise construction operations to assure that no part of the construction completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
Final Cleaning: At completion of Work, remove all remaining waste materials, rubbish, tools, equipment, machinery and surplus materials, and clean all exposed surfaces; leave Project clean and ready for occupancy.
CORRECTION OF THE WORK
Repair or remove and replace defective construction. Restore damaged substrates and finishes.
Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
Restore permanent facilities used during construction to their specified condition.
Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.
Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.
Remove and replace chipped, scratched, and broken glass or reflective surfaces.
END OF SECTION 01 73 40
LAKE – PMIS 220532 01 73 40 - 1
EXECUTION
image7.emf
Microsoft_Word_Document6.docx
SECTION 01 74 19
CONSTRUCTION WASTE MANAGEMENT & DISPOSAL
1.1 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Disposal: Transport waste materials off Government’s property and legally dispose of them.
END OF SECTION 01 74 19
LAKE – PMIS 220532 01 74 19 - 1
CONSTRUCTION WASTE MANAGEMENT
& DISPOSAL
image8.emf
Microsoft_Word_Document7.docx
SECTION 01 77 00
CLOSEOUT PROCEDURES
1.1 CLOSEOUT SUBMITTALS
Submit the following before requesting final inspection:
Instruct NPS personnel in the basic operation, adjustment, and maintenance of products, equipment, and systems.
1.2 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within ten (10) days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
B. If, following final inspection, the work is determined to be substantially complete, Contracting Officer will prepare a Punch List to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the Punch List within thirty (30) calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.
C. If, following final inspection, the work is not determined to be substantially complete; Contracting Officer will notify Contractor in writing. After completing work, Contractor shall request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
1.3 FINAL ACCEPTANCE OF THE WORK
A. After all deficiencies have been corrected, a Letter of Final Acceptance will be issued.
END OF SECTION 01 77 00
LAKE – PMIS 220532 01 77 00 - 1
CLOSEOUT PROCEDURES
image9.emf
Microsoft_Word_97_-_2003_Document.doc
Copyright 2011 by The American Institute of Architects (AIA)
Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA
SECTION 02 23 00
SITE CLEARING
Revise this Section by deleting and inserting text to meet Project-specific requirements.
This Section uses the term "Architect." Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.
Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.
1.1 RELATED DOCUMENTS
Retain or delete this article in all Sections of Project Manual.
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Protecting existing vegetation to remain.
2. Removing existing vegetation.
3. Clearing and grubbing.
4. Stripping and stockpiling topsoil.
5. Removing above- and below-grade site improvements.
6. Disconnecting, capping or sealing, and abandoning site utilities in place.
Retain subparagraph below if erosion- and sedimentation-control measures are not included in Section 01500 "Temporary Facilities and Controls."
7. Temporary erosion- and sedimentation-control measures.
B. Related Sections:
Retain Sections in subparagraphs below that contain requirements Contractor might expect to find in this Section but are specified in other Sections.
1. Section 01500 "Temporary Facilities and Controls" for temporary utility services, construction and support facilities, security and protection facilities, and temporary erosion- and sedimentation-control measures.
1.3 DEFINITIONS
Retain definitions remaining after this Section has been edited.
A. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.
B. Surface Soil: Soil that is present at the top layer of the existing soil profile at the Project site. In undisturbed areas, the surface soil is typically topsoil; but in disturbed areas such as urban environments, the surface soil can be subsoil.
Retain one of first two paragraphs below; revise to define "topsoil" according to local practices if required. Topsoil is raw material that typically needs screening and amending before meeting planting soil mix requirements. First paragraph assumes topsoil depth is known and shown or specified; second paragraph assumes that Contractor will identify and determine depth of existing topsoil. Coordinate with "Topsoil Stripping" Article.
C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil and is the zone where plant roots grow.
D. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil and is the zone where plant roots grow. Its appearance is generally friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches (50 mm) in diameter; and free of subsoil and weeds, roots, toxic materials, or other non-soil materials.
Retain one or both of first two paragraphs to suit Project. See Evaluations.
E. Plant-Protection Zone: Area surrounding individual trees, groups of trees, shrubs, or other vegetation to be protected during construction, and indicated on Drawings.
Retain second option in first paragraph below if Contractor will determine extent of one or more tree-protection zones.
F. Tree-Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction and defined by a circle concentric with each tree with a radius 1.5 times the diameter of the drip line unless otherwise indicated.
G. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.4 MATERIAL OWNERSHIP
A. Cleared materials shall become Contractor's property and shall be removed from Project site.
1.5 INFORMATIONAL SUBMITTALS
A. Existing Conditions: Documentation of existing trees and plantings, adjoining construction, and site improvements that establishes preconstruction conditions that might be misconstrued as damage caused by site clearing.
Revise subparagraphs below and insert additional requirements to suit Project.
1. Use sufficiently detailed photographs or videotape.
2. Include plans and notations to indicate specific wounds and damage conditions of each tree or other plants designated to remain.
Revise paragraph below to suit Project.
B. Record Drawings: Identifying and accurately showing locations of capped utilities and other subsurface structural, electrical, and mechanical conditions.
1.6 QUALITY ASSURANCE
Retain this article if Work of this Section is extensive or complex enough to justify a preinstallation conference.
A. N/A
1.7 PROJECT CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Contracting Officer or Contracting Officer’s Representatives.
2. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction.
Retain first paragraph below to suit Project; coordinate with Owner.
B. Improvements on Adjoining Property: Authority for performing site clearing indicated on property adjoining Lake Mead will be obtained by Contracting Officer or Contracting Officer’s Representative before award of Contract.
1. Do not proceed with work on adjoining property until directed by Contracting Officer or Contracting Officer’s Representative.
Retain first paragraph below to suit Project. Indicate items to be salvaged on Drawings or in schedules.
C. Salvable Improvements: Carefully remove items indicated to be salvaged and store on Lake Mead premises.
Retain one option in first paragraph below. First option is a generic term that is known in various states by different names listed in the other options.
D. Utility Locator Service: Call Before You Dig who? for area where Project is located before site clearing.
Retain option in first paragraph below if protection zones and protection-zone fencing are required.
E. Do not commence site clearing operations until temporary erosion- and sedimentation-control and plant-protection measures are in place.
Retain first three paragraphs below if tree- or plant-protection zones are required.
F. The following practices are prohibited within protection zones:
Revise subparagraphs below to suit Project.
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Foot traffic.
4. Erection of sheds or structures.
5. Impoundment of water.
6. Excavation or other digging unless otherwise indicated.
7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.
G. Do not direct vehicle or equipment exhaust towards protection zones.
H. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones.
Retain paragraph below to suit Project.
I. Soil Stripping, Handling, and Stockpiling: Perform only when the topsoil is dry or slightly moist.
PART 2 - PRODUCTS
2.1 MATERIALS
Retain first paragraph below if soil backfill is required in below-grade areas after site clearing.
A. Satisfactory Soil Material: Requirements for satisfactory soil material are specified in Section 02300 "Earthwork."
1. Obtain approved borrow soil material off-site when satisfactory soil material is not available on-site.
Retain paragraph below if needed for cut ends of steel reinforcement in concrete to remain; revise to suit Project.
B. Antirust Coating: Fast-curing, lead- and chromate-free, self-curing, universal modified-alkyd primer complying with MPI #79, Alkyd Anticorrosive Metal Primer or SSPC-Paint 20 or SSPC-Paint 29 zinc-rich coating.
VOC limit in subparagraph below is the EPA limit for rust-preventive architectural coatings; revise to suit Project.
1. Use coating with a VOC content of 420 g/L (3.5 lb/gal.) or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during construction.
Revise first paragraph below to suit regional standards or office practices; delete if specified in Section 02231 "Tree Protection and Trimming." Insert requirement for flagging trees to be relocated if required.
B. Locate and clearly identify trees, shrubs, and other vegetation to remain. Wrap a 1-inch blue vinyl tie tape flag around each tree trunk at 54 inches above the ground.
C. Protect existing site improvements to remain from damage during construction.
1. Restore damaged improvements to their original condition, as acceptable to Contracting Officer or Contracting Officer’s Representative.
3.2 TEMPORARY EROSION AND SEDIMENTATION CONTROL
Retain this article if erosion- and sedimentation-control measures are not included in Section 01500 "Temporary Facilities and Controls."
Insert specific procedures or installation requirements for temporary soil protection and stabilization, erosion controls, stormwater runoff controls, and sedimentation controls. If particular products are required, add product standards and descriptions to Part 2.
A. Provide temporary erosion- and sedimentation-control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways, according to erosion- and sedimentation-control Drawings and requirements of authorities having jurisdiction.
Retain first paragraph below if tree- or plant-protection zones are required.
B. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.
C. Inspect, maintain, and repair erosion- and sedimentation-control measures during construction until permanent vegetation has been established.
D. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.
3.3 TREE AND PLANT PROTECTION
Retain this article if required. If retaining, Drawings should show tree- and plant-protection zones and protection-zone fencing.
A. General: Protect trees and plants remaining on-site according to requirements in Section 02231 "Tree Protection and Trimming."
B. Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are damaged by construction operations, in a manner approved by Contracting Officer or Contracting Officer’s Representative.
3.4 EXISTING UTILITIES
Retain one of first two paragraphs below. Retain first if Owner arranges for this work; retain second if Contractor performs this work.
A. Contracting Officer or Contracting Officer’s Representative will arrange for disconnecting and sealing indicated utilities that serve existing structures before site clearing, when requested by Contractor.
1. Verify that utilities have been disconnected and capped before proceeding with site clearing.
B. Locate, identify, disconnect, and seal or cap utilities indicated to be removed or abandoned in place.
Retain one of two subparagraphs below.
1. Arrange with utility companies to shut off indicated utilities.
C. Locate, identify, and disconnect utilities indicated to be abandoned in place.
Generally retain first paragraph below unless there are no existing utilities. Coordinate with requirements in Section 01500 "Temporary Facilities and Controls" for temporary utilities.
D. Interrupting Existing Utilities: Do not interrupt utilities serving facilities occupied by National Park Service Employees or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
Revise subparagraphs below to suit Project. Change "Architect" to "Owner" or other responsible party if required.
1. Notify Contracting Officer or Contracting Officer’s Representative not less than three days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer or Contracting Officer’s Representative’s written permission.
Retain one of two paragraphs below. If retaining first, coordinate utility removals with requirements in Section 02300 "Earthwork"; if retaining second, coordinate with earthwork sections and with applicable fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security and utilities sections and Section 02221 "Building Demolition" and Section 01732 "Selective Demolition."
E. Excavate for and remove underground utilities indicated to be removed.
F. Removal of underground utilities is included in earthwork sections and with applicable fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security and utilities sections and Section 02221 "Building Demolition" and Section 01732 "Selective Demolition."
3.5 CLEARING AND GRUBBING
A. Remove obstructions, trees, shrubs, and other vegetation to permit installation of new construction.
1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated.
2. Grind down stumps and remove roots, obstructions, and debris to a depth of 18 inches below exposed subgrade.
3. Use only hand methods for grubbing within protection zones.
4. Chip removed tree branches and dispose of off-site.
Retain paragraph below if required. Coordinate with Section 02300 "Earthwork."
B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated.
1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches and compact each layer to a density equal to adjacent original ground.
3.6 TOPSOIL STRIPPING
A. Remove sod and grass before stripping topsoil.
Retain one option for topsoil depth in first paragraph below if depth is known. Delete options if Contractor will identify and determine depth of existing topsoil. Coordinate with topsoil definition retained in "Definitions" Article.
B. Strip topsoil to depth of 6 inches in a manner to prevent intermingling with underlying subsoil or other waste materials.
Revise subparagraph below if other materials are known to be mixed into unsuitable, existing native surface topsoil or existing in-place surface soil.
1. Remove subsoil and nonsoil materials from topsoil, including clay lumps, gravel, and other objects more than 2 inches in diameter; trash, debris, weeds, roots, and other waste materials.
Revise paragraph below if topsoil is to be removed from site. Insert here or indicate on Drawings the quantity of topsoil to be stockpiled or reused, if known.
C. Stockpile topsoil away from edge of excavations without intermixing with subsoil. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust and erosion by water.
1. Limit height of topsoil stockpiles to 72 inches.
2. Do not stockpile topsoil within protection zones.
3. Dispose of surplus topsoil. Surplus topsoil is that which exceeds quantity indicated to be stockpiled or reused.
Retain subparagraph above or below to suit Project.
4. Stockpile surplus topsoil to allow for re-spreading deeper topsoil.
3.7 SITE IMPROVEMENTS
Revise first paragraph below and add specific items to suit Project.
A. Remove existing above- and below-grade improvements as indicated and necessary to facilitate new construction.
B. Remove slabs, paving, curbs, gutters, and aggregate base as indicated.
1. Unless existing full-depth joints coincide with line of demolition, neatly saw-cut along line of existing pavement to remain before removing adjacent existing pavement. Saw-cut faces vertically.
2. Paint cut ends of steel reinforcement in concrete to remain with two coats of antirust coating, following coating manufacturer's written instructions.