A04_Statement_of_Work_Boat_Ramps_0044043673.pdf
PDF 1 MB Posted
- Attached to
- Boat Ramp Replacement Project at Kirwin NWR
- Solicitation number
- 140FGA26R0023
About this file
This is a Scope of Work (SOW) for the demolition and replacement of three concrete boat ramps at Kirwin National Wildlife Refuge in Kirwin, Kansas (Project #6R-KS-461-100).
The contractor must demolish and replace two double-lane concrete boat ramps at the North Shore (1,067 sq ft) and South Shore (combined 4,090 sq ft), demolish two concrete boat docks (bulkheads) totaling 1,490 sq ft, and extend, reinforce, and potentially relocate wave breaks at both locations. The North Shore boat ramp replacement includes integration of the 620 sq ft bulkhead as part of the ramp structure. The South Shore work addresses a separate 870 sq ft bulkhead. Total concrete removal required is 7,981 sq ft. All concrete ramps shall be reinforced with #4 epoxy-coated rebar, 6 inches thick, finished with non-skid V-groove surface (1-inch deep), and designed to support AASHTO HS-20 live loads. Each ramp lane shall be 20 feet wide with a median for steel boat dock installation (30 ft x 6 ft). Ramp slopes must be 12-20% (preferred 14%), with water elevation considerations: 20-year historical low of 1,702.03 ft and high of 1,729.31 ft. Concrete above water level shall be pour-in-place (4,000 psi minimum with epoxy rebar 12 inches each way); below water level shall be precast and pushed. Wave breaks shall extend approximately 40 feet using reused demolished concrete riprap (12-18 inches) and imported riprap as needed, with non-woven geotextile underlayment (minimum 8 oz, AASHTO M288 compliant).
The work includes preconstruction site assessment, mobilization with designated staging areas, water control via low water level work or temporary coffer dams/sheet piling, soil erosion control with perimeter turbidity curtains and concrete washout collection areas, site/subgrade preparation with 95% compaction (ASTM D 1557 Modified Proctor), six-inch aggregate base installation, dredging of accumulated sediments with approved disposal, and environmental compliance with Best Management Practices, Clean Water Act requirements, and OSHA standards. Construction limitations include no uncured concrete entering water, cast-in-place concrete limited to two or more feet above water surface, equipment fueling/maintenance prohibited within 100 feet of water unless secondary containment provided, and minimum vegetation clearing. Site cleanup requires removal of all debris, restoration to original condition, and native vegetation or riprap stabilization of disturbed areas. The project completion deadline is 60 days from notice to proceed. Contractor availability is Monday-Friday 8:00 a.m.–4:00 p.m., with emergency functions potentially required during non-duty hours. All products and equipment carry a minimum one-year labor warranty unless extended warranty is purchased by the Government.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work for the Replacement of Multiple Boat Ramps at Kirwin National Wildlife Refuge
Project #: 6R-KS-461-100
Kirwin NWR
702 E Xavier Rd, Kirwin, KS 67644
Project Overview
The purpose of this project is to demolish and replace three (3) deteriorated concrete boat ramps at Kirwin National Wildlife Refuge. A high percentage of refuge visitation comes from the utilization of the boat ramps for authorized recreational activities, primarily hunting and fishing. The rehab of these boat ramps will improve public safety, enhance protection of refuge and visitor property, and reduce long-term maintenance costs. They will be designed to accommodate modern vehicles and trailers, support increased loads, and comply with current design standards for boat ramp construction. The ramps will be replaced with two (2) double-lane concrete boat ramps. Each lane will be separated with a median with space for a steel boat dock (30 ft x 6 ft). There are two (2) concrete boat docks (bulkheads), one at the North Shore (620 sq ft) that is part of the North Shore boat ramp structure, and one at the South Shore (870 sq ft), which need to be demolished as well.
The bulkhead at the North Shore should be treated as part of the North Shore Boat Ramp structure. The wave breaks at both boat ramp locations need to be extended, reinforced, and potentially moved altogether.
Figure.7¡.South.Shore.boat.ramps.(north.and.south.lanes).
aerial.view¡
Figure.8¡.Two‗lane.North.Shore.boat.ramp.aerial.view.with.a.
roll‗in.aluminum.boat.dock¡
Background
The two-lane North Shore boat ramp was also constructed in 2001 and is 1,067 sq ft. The ramp is in poor working condition and no longer supports the demand for vehicle use due to the uneven and deteriorated concrete. The ramp is also too narrow and too short to accommodate the fluctuating reservoir water levels and vehicle size.
The two lanes at the South Shore boat ramp were also constructed in 2001. As seen in Figure 5, the north lane at the South Shore boat ramp is 1,483 sq ft and the south lane is 2,607 sq ft. Both lanes are in poor working condition and no longer support the demand for vehicle use due to the uneven, deteriorated concrete. The ramps are also too narrow and too short to accommodate the reservoir levels and vehicle size.
Figure.9¡.Two‗lane.boat.ramp.at.the.North.Shore¡.Boulders.are.
placed.on.each.lane.to.keep.visitors.from.driving.on.them¡
Figure.❶¡.North.lane.of.the.South.Shore.boat.ramp¡.Boulders.are.
used.to.prevent.vehicle.use.and.to.mark.boat.ramp.closure¡
Figure.0¡.Boat.ramp.lanes.do.not.extend.to.reservoir.when.water.
elevation.is.low¡.Reservoir.water.elevation.at.the.time.this.photo.
was.taken.was.7?❸7❷¡89.ft¡
Figure.❷¡.Boat.ramp.subgrade.is.washed.out.due.to.fluctuating.
water.levels?.severe.weather?.and.heavy.erosion¡
Work to be Performed
The Contractor shall provide all labor, materials, equipment, and services required to demolish and replace the North Shore and South Shore concrete boat ramps, demolish a concrete boat dock (bulkhead) at each site, and extend, reinforce, and potentially move two existing wave breaks (breakwaters) at Kirwin NWR.
This work includes, but is not limited to:
Preconstruction Site Assessment
• Prior to any fieldwork, the Contractor shall conduct a site walk-through with the station and the Contracting Officer’s Representative to verify existing boat ramp dimensions and conditions, shoreline geometry, water levels, access routes, and staging areas.
Mobilization and Site Access
• The Contractor shall speak with the station to establish designated staging and equipment laydown areas in approved locations to minimize disturbance to refuge land.
• The Contractor shall install construction signage and barriers to restrict public access to active work zones.
Water Control and Isolation
Given that some of the construction work will occur at the water interface, the Contractor shall implement one of the following methods:
• Perform work during low water levels, OR
• Install temporary coffer dams, sheet piling, or other approved barriers to isolate the work area
Water discharge from any water control method must be controlled to prevent erosion and sedimentation while complying with the Clean Water Act.
Soil Erosion and Sediment Control
• All soil erosion and sediment control practices shall be installed in accordance with the requirements of federal, state, and local regulations, and shall be installed in the correct sequence and maintained until proper stabilization is well established.
• The Contractor shall install a perimeter turbidity curtain in the reservoir to prevent silt and pollutants from dispersing. The curtain shall be installed before work begins in the water.
o Anchor the curtain so that it stays in place.
o Barriers shall be inspected daily.
o Repair or replace barrier when damaged.
• The Contractor shall construct an area to collect the washout water from concrete trucks used on this project.
o Sediment shall be removed from the washout collection when it has reached ½ depth of the barrier height.
o Barriers shall be inspected daily.
o Repair or replace barrier when damaged.
Environmental Protection Measures and Safety
To protect the habitat of Kirwin NWR:
• No uncured concrete or runoff from uncured concrete should be allowed to enter the water.
• Cast-in-place concrete for ramp construction should be limited to portions of the ramp located two or more feet above the water surface elevation.
• Use clean riprap to armor-cut or fill slopes below normal high-water elevation.
• Place riprap along both sides and at the toe of ramp to prevent current, waves, and prop wash from eroding or undermining the structure.
• Limit vegetation clearing to the minimum area necessary.
• Immediately contain and report any spills or contamination.
• Prohibit fueling or maintenance of equipment within 100 ft of the water body unless secondary containment is provided.
• Ensure compliance with federal, state, and local environmental regulations, including permitting as applicable.
Demolition and Site/Subgrade Preparation
• Sawcut concrete slabs at one-fourth to one-third of the slab’s thickness to create clean edges.
• Remove existing concrete slabs, reinforcement, and embedded materials.
o Total sq ft of concrete that needs to be removed is 7,981sq ft.
• Properly dispose of demolition debris in compliance with federal, state, and local regulations. Concrete from demolished boat ramps will be used by the station as riprap and does not need to be hauled off-site. Holding area will be specified by station.
• Excavate unsuitable base materials as required.
• Prevent debris from entering the water using containment methods such as mats or barriers.
After demolition the Contractor shall:
• Proof-roll and evaluate subgrade for stability and load bearing capacity.
• Grade and prepare subgrade to ensure proper slope of 12-20% (preferred 14%) and drainage.
• Remove and replace unsuitable or soft soils with engineered fill.
• Compact subgrade to a minimum of 95% of maximum dry density (ASTM D 1557 – Modified
Proctor).
• Subgrade must be inspected and approved before concrete placement.
Aggregate Base Installation
• Place a six-inch crushed aggregate base layer.
• Compact base to a minimum of 95% of maximum dry density (ASTM D 1557 – Modified
Proctor).
• Grade base to match the required ramp slope (preferred 14%).
Excavation and Grading
• Excavate to required lines and grades for new ramp construction.
• Ensure proper tie-in with existing parking areas and shoreline elevations.
• Maintain positive drainage away from the boat ramps.
Ramp Design and Construction
• Contractor shall construct three new reinforced concrete boat ramps designed to:
o Meet current design standards for recreational boat ramps.
Ramps should support at least AASHTO HS-20 live loads.
o Accommodate the weight and size of modern vehicles and boat trailers.
o Ensure safe, even transitions between ramp sections and adjacent shoreline.
• The concrete ramps at the North Shore and South Shore will consist of two lanes separated by a median for a boat dock. Each lane will be 20 ft wide. All concrete boat ramps shall have a thickness of 6 inches.
• A vertical curve must be installed at the top of the ramp to provide a smooth transition between the maneuver area grade and the ramp slope. Slope should be 4-12%.
• The ramp above water level should be pour-in-place. The ramp below water level should be precast and pushed.
o Concrete shall be 4,000 psi minimum compressive strength and be reinforced with #4 epoxy coated rebar 12 inches each way.
• 20-year historical low-water elevation: 1702.03 ft (Streambed = 1662.3 ft).
• 20-year historical high-water elevation: 1729.31 ft (not including flood levels).
• All concrete boat ramps shall be finished with a non-skid V-groove finish (1” deep). The grooves shall be formed in the ramp surface, angled 30 degrees from the perpendicular axis of the ramp.
• Additional information located in specifications and drawings.
Dredging
• Contractor shall remove accumulated sediments from in-water portions of the boat ramps and adjacent maneuvering areas if required.
• Dredged materials shall be:
o Transported to approved upland disposal sites, OR o Reused onsite if suitable and approved
• Implement erosion and turbidity control measures during dredging operations.
• Comply with Clean Water Act requirements and all federal and state environmental regulations.
• Additional information located in specifications.
Wave Break Extension
• Extend wave breaks by approximately 40 ft by placing riprap, installation of geotextile underlayment, and ensuring the extended structure is properly integrated with the existing wave break.
• Riprap used should consist of reused concrete from the demolished boat ramps and imported riprap as needed.
o Size: 12-18 inches.
• Geotextile fabric:
o Non-woven, minimum 8 oz weight.
o Should meet AASHTO M288.
• Additional information located in specifications.
Environmental and Safety Compliance
• Implement Best Management Practices (BMPs) to protect water quality and surrounding wildlife habitat during construction.
• Ensure compliance with federal, state, and local environmental regulations, including permitting as applicable.
• Follow all OSHA standards to maintain a safe construction site.
• No uncured concrete or runoff from uncured concrete should be allowed to enter the water.
• Cast-in-place concrete for ramp construction should be limited to portions of the ramp located two or more feet above the water surface elevation.
• Use clean riprap to armor-cut or fill slopes below normal high-water elevation.
• Place riprap along both sides and at the toe of ramp to prevent current, waves, and prop wash from eroding or undermining the structure.
• Limit vegetation clearing to the minimum area necessary.
• Immediately contain and report any spills or contamination.
• Prohibit fueling or maintenance of equipment within 100 feet of the water body unless secondary containment is provided.
Site Cleanup
• Removal of all debris and construction materials from the work area.
• Proper disposal of all waste and debris in accordance with local regulations.
• Restoration of work area to its original condition.
• Any areas disturbed during construction that are outside of the ramp footprint shall be regraded to original contours and stabilized with native vegetation or riprap if necessary.
Timeline
• Completion of project within 60 days of the notice to proceed.
Inspection and Acceptance
• The Government reserves the right to inspect any and all phases of the work performed under this contract and will conduct a final inspection prior to acceptance of the work. The Contractor shall notify the Technical Coordinator, Station Manager, Contract Officer Representative, and Contract Officer at least five business days prior to scheduling the final inspection. Provide all operations, maintenance manuals, and training in routine maintenance to assure expected boat ramp life.
Availability
• Normal duty hours are Monday through Friday 8:00 a.m. – 4:00 p.m. The Contractor shall provide emergency contact information.
• Non-duty hours include weeknights, weekends, and Government holidays (New Year’s Day, Martin Luther King Jr. Day, President’s Day, Memorial Day, Juneteenth, Fourth of July, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving, and Christmas).
• Emergency/Miscellaneous functions may be required to be scheduled during non-duty hours due to the nature of the work or specific scheduling requirements. Emergency work is required when immediate action is necessary to correct or prevent loss or damage of Government property, or to eliminate hazards to the public, personnel, or equipment.
• Water, sewer, and electricity can be used by Contractor. Ensure that no damage is done to the systems.
Quality Control (QC)
• Quality Control will be maintained in accordance with industry standards and made available to the agency upon request. Installation must comply with manufacturers specifications and applicable codes including OSHA, ASME, and NFPA.
Quality Assurance (QA)
• Labor warranty for all products and equipment shall be at least one year unless an extended warranty is purchased by the Government.