This document is a Statement of Work (SOW) for the exterior painting of a duplex and a single-family residence at the N.P.R. Hobe Sound National Wildlife Refuge in Hobe Sound, Florida. The SOW provides a detailed description of the work to be performed, including cleaning and preparing all exterior surfaces, patching and repairing holes and cracks, and applying primer and two coats of exterior grade latex paint on the siding, soffits, fascia, and metal surfaces. The contractor is required to submit product data and color selections for all materials used. A pre-bid proposal meeting will be held at the project site to review the existing conditions and discuss the performance requirements. The project manager and Contracting Officer's Technical Representative (COTR) are identified, and questions regarding the scope of work and technical matters should be directed to the U.S. Fish & Wildlife Service Infrastructure Management Division. The related federal contract opportunity is Solicitation Number 140FC124Q0012, titled "EXTERIOR PAINTING QTRS AT HOBE SOUND NWR", issued by the Department of the Interior Fish and Wildlife Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_Revised_04-04-2024_0001.pdf | ||
| Sol_140FC124Q0012_Amd_0001.pdf | ||
| Q_A_Amd_0001_0001.pdf | ||
| General_Wage_Decision_No__FL20240073_01_05_2024.pdf | ||
| Sol_140FC124Q0012.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Exterior Painting of a Duplex and a Single-Family Residence at N.P.R. Hobe Sound National Wildlife Refuge Hobe Sound, Florida Asset Number Residence Numbers: 10014643 Quarters #1 & #2; 10052601 Quarters #3 December 21, 2023
PART 1. GENERAL
1.1. The contractor shall supply all materials, labor, supplies and equipment to perform all operations required to complete the work in conformance with this statement of work to paint the exterior of Residence Numbers 1,2 (Duplex) and 3 (Single Family Residence, SFR) buildings at the N.P.R. Hobe Sound National Wildlife Refuge (NWR) in Hobe Sound, Florida (see Appendix A for images of residences).
1.2. The refuge is located about 10 miles south of Stuart, Florida, and is accessible from Interstate 95 by going east on Bridge Road until you reach SE Federal Highway. From SE Federal Highway head south for approximately 2 miles and turn east into the Refuge parking lot.
1.3. A Pre-Bid Proposal Meeting will be held at the project site at N.P.R. Hobe Sound NWR. The time and date of this meeting will be mutually agreed upon by the Refuge representative, prospective contractors, Contracting Officer and USFWS Project Manager.
1.3.1. The purpose of the meeting will be to visit the site, review existing conditions, and discuss the performance requirements of the project. Contact the Station to obtain best access to the Refuge or refer to Paragraph 1.2 for directions.
1.3.2. As-built drawings of the building(s) are not available. The site will be viewed at the Pre-Bid Proposal Meeting.
PART 2. DESCRIPTION OF WORK
2.1. Bid Item No. 1: Paint Exterior of Residence Numbers 1 and 2 (Duplex) and Residence 3 (SFR) (Product Data Submittal and color charts, as applicable, are required for all materials used in this section.
2.1.1. Clean and prepare all exterior trim surfaces of the houses. Patch and repair holes and cracks in sofit and/or facia using like materials of existing surfaces, caulk as needed to seal edges, and apply one coat of primer and two coats of exterior grade latex paint on the exterior trim surfaces only.
2.1.2. Clean and prepare all exterior surfaces. Patch and repair holes and cracks in exterior walls using like materials of existing surfaces, caulk as needed to seal windows, doors and other edges, and apply one coat of primer and two coats of exterior grade latex paint on these surfaces.
2.1.3. Hurricane shutter stow boxes and frames are metal and shall require prep, primer and painting using paint appropriate for metal surfaces. Hurricane shutters shall not be painted.
2.1.4. All paints used shall be of a brand that is readily available should an exact match be needed later.
2.1.5. Submit the color selection as part of the product data submittal to the Contracting officers technical:
2.1.5.1. All paint data and colors to be used on the siding, soffits, fascia, and metal surfaces.
2.1.5.2. All product data on the caulks and sealants to be used.
PART 3. GENERAL NOTES
3.1.1. The building will be occupied during project. Care shall be taken to coordinate all construction activities with Refuge personnel.
3.1.2. Non-target surfaces such as windows and shutters, and landscape vegetation must be protected from overspray and/or drippage.
3.1.3. All project debris shall become the contractor’s property and shall be removed from the site and disposed of in a legal manner.
PART 4. PROJECT CONTACTS
4.1. The project manager and the Contracting Officers Technical Rep (COTR) William Miller, Refuge Manager
U.S. Fish & Wildlife Service Nathaniel P. Reed Hobe Sound National Wildlife Refuge
13640 SE Federal Hwy Hobe Sound, FL 33455 Telephone:(772) 341-4852 Fax:(772) 545-7572 Email: William_g_miller@fws.gov
4.2. Questions regarding the scope of work and technical matters shall be directed to:
U. S. Fish & Wildlife Service
Infrastructure Management Division Southeast Region
1875 Century Parkway
Atlanta, GA 30345
Contact: John Stricklan P.E.
Telephone:(404) 694-2431
Email: John_Stricklan@fws.gov Appendix A:
Figure 1. Front View of Residence #1 & #2
Figure 2. North (Side) View of Residence #1 & #2
Figure 3. Back View of Residence #1 & #2
Figure 4. South (Side)View of Residence #1 & #2
Figure 5. Front View of Residence #3, Image A
Figure 6. Front View of Residence #3, Image B.
Figure 7. Back View of Residence #3.
Figure 9. North (Side) View of Residence #3.
Figure 8. South (Side) View of Residence #3
Exterior Painting NPR Hobe Sound NWR Quarters December 21, 2023