This document is a Statement of Work for the delivery of 500 tons of AB gravel and 400 tons of rip rap cobble to the Merced National Wildlife Refuge (NWR). The scope requires delivery and placement of the materials to two locations within the Merced NWR - the North Merced Unit and the East Marsh Unit. The gravel is to be used to cover and repair administration roads and water control structures, while the rip rap is to be placed at designated water control structures. The period of performance is from May 15, 2024 to November 30, 2024, with deliveries required within 48 hours of a request from the site foreman. The contractor must provide virgin or 12" minus fractured rock, with no recycled materials accepted. The government will furnish equipment to finish spreading the gravel after delivery. The Technical Coordinator is Gabriel Sandoval, the Merced Refuge Manager.

View the file

Other files

File Type Posted
GAOA_Gravel_Merced_NWR_SOW-FY24_1_0002.pdf PDF
Sol_140FGA24Q0019_Amd_0002.pdf PDF
B08_Solicitation_Price_Schedule_140FGA24Q0019_0001.xlsx XLSX spreadsheet
Sol_140FGA24Q0019_Amd_0001.pdf PDF
GAOA_Gravel_Merced_NWR_SOW-FY24_0001.pdf PDF
Sol_140FGA24Q0019.pdf PDF
Price_Schedule.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

DELIVER 500 TONS OF ¾ AB GRAVEL AND 400 TONS RIP RAP COBBLE TO

Merced NWR

1. GENERAL: The Merced NWR will require the delivery and placement of 400 tons of virgin 3/4AB gravel and 400 tons of 4-8” Cobble Rip Rap to multiple locations on Merced NWR. Gravel will be spread to cover areas of refuge administration roads and water control structures impacted by activities related to the cleaning of canals and replacement of structures on the Merced unit of the Merced NWR. Rip Rap will be end dumped at designated water control structure locations on the Merced Unit. Gravel and Rip Rap will be delivered or stockpiled at designated water control structures at the Merced unit

2. SCOPE:

Provide a total of 500 tons of virgin ¾ AB gravel and 400 tons 4-8” Cobble Rip Rap to locations (North Merced Unit, East Marsh unit) on the Merced National Wildlife Refuge.

Two hundred (200) tons of ¾ AB gravel, one-hundred sixty (160) of 4-8” Cobble Rip Rap to North Merced Unit.

Three hundred (300) tons of ¾ AB gravel, Two-hundred forty (240) Tons Rip Rap Cobble to East Marsh unit.

A gravel delivery truckload is considered between 20-25 tons. Gravel will be belly dumped or side dumped on existing gravel roads and disturbed construction areas at an even rate. A rip rap delivery truck load will be considered 20 tons and will be stockpiled, or end dumped at designated locations. Areas where gravel and rip rap are to be placed will be marked in advance. Gravel will be placed in quantities to allow coverage of an average width of 7 feet to an average thickness of 4 inches. Some areas may require an average width of 5 feet and others up 10 feet to an average thickness of 4 inches.

Material must be ¾” Class 2 Aggregate Base virgin or 12” minus fractured rock; no recycled materials such as asphalt, porcelain or concrete will be accepted.

3. PLACE/DELIVERY AND PERIOD OF PERFORMANCE: Deliveries will be at various locations within the Merced National Wildlife Refuge. Site Foreman will provide load amount requests and delivery locations on a daily or weekly basis to the contractor, deliveries of the requested amount of materials will be expected within 48 hours of request. Period of performance is from May 15th, 2024 – November 30, 2024.

Delivery locations:

North Merced Unit-200 ¾ AB gravel, 160 Tons Rip Rap Cobble Merced National Wildlife Refuge – Red Barn, North Merced 37.189812°, -120.610951° 6689 W Sandy Mush Rd Merced, CA 95341

East Marsh Merced Unit- 300 Tons ¾”AB, 240 Tons Rip Rap Cobble Delivery within one mile of or stockpile at:

Merced National Wildlife Refuge-Maintenance Shop 7430 W Sandy Mush Rd Merced, CA 95341

4. GOVERNMENT FURNISHED EQUIPMENT OR

MATERIALS/INFORMATION:

Delivery requirement is to belly dump gravel and spread gravel as much as allowed by normal operating practices of delivery equipment at designated locations within the Merced NWR and end dump rip rap. USFWS equipment will finish spreading gravel to final requirements.

5. AVAILABILITY: Normal duty hours are Monday thru Friday 7:00 a.m. – 4:00 p.m.

6. TECHNICAL COORDINATOR: Gabriel Sandoval, Merced Refuge Manager.

Cell Phone 209-587-5530. Office # 209-826-3508.