A04 Specifications 3099889.pdf
PDF 3 MB Posted
- Solicitation number
- 140P8120Q0070
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8120Q0070_Amd_0001.pdf | ||
| B08 Brand Name justification Attachement 2 PMIS309889 SOLE SOURCE CS signed.pdf | ||
| sign locations and specs.docx | DOCX document | |
| Wage Determinations Clark County NV.pdf | ||
| 140P8120Q0070 Supply Clauses.docx | DOCX document | |
| Sol_140P8120Q0070.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAKE MEAD NATIONAL RECREATION AREA
Boulder City, Nevada
PMIS No. 309889 Purchase and Install Park Wide
Flashing Caution Signs
SPECIFICATIONS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
April 2020
TABLE OF CONTENTS
NO. OF PAGES
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 11 40 Work Restrictions 01 27 00 Definition of Contract Price Items 01 31 00 Project Management & Coordination 01 32 16 Installation Schedule …………………………………………………………… 01 33 00 Submittal Procedures 01 33 23 Shop Drawings, Product Data and Samples 01 35 23 Safety Requirements 01 40 00 Quality Requirements ……………………………………………………………. .. 6 01 50 00 Temporary Facilities and Controls…………………………………………… 01 67 00 Product Requirements…………………………………………… 01 73 40 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Closeout Procedures 01 82 00 Demonstration and Training
DIVISION 34 – TRANSPORTATION
34 41 16 Traffic Control Equipment
APPENDIX
LAKE Map and Distances RU2 Systems Inc, FAST 350 Transmittal Form CM-16 RFI Form
DIVISION 01
GENERAL REQUIREMENTS
LAKE – PMIS 309889 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00
PART 1 – GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
Project Location:
The project is located at the Lake Mead National Recreation Area Nevada and Arizona
A. The Work consists of the following:
Furnishing and installing nine (9) flashing cautions signs at Lake Mead National Recreation Area. Six (6) at the existing Entrance Stations and three (3) throughout park. These signs are to be solar powered and permanently mounted.
B. The Work consists of the following:
Furnishing and installing Upgrades to two (2) existing flashing cautions signs at Lake Mead National Recreation Area Entrance Stations.
C. Performance Period: 90 calendar days.
1.2 GOVERNMENT-FURNISHED ITEMS
A. Government-Furnished Items: None Expected.
1.3 PUBLIC USE OF THE SITE
A. General: The project site will be open to the public and park staff during construction.
1.4 CONTRACTOR USE OF SITE
A. General: Limit use of the site during the construction period to the project area limits as outlined on the attached site maps. Do not disturb portions of the site beyond the project area limits.
B. Park Entry: The contractor shall furnish a list of personnel with phone contact information.
Vehicles associated with the contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
LAKE – PMIS 309889 01 11 00 - 2
C. Site Access: The contractor shall access the project site as outlined on the attached site map.
Do not drive vehicles off road or access non-project areas without permission from the contracting officer or park superintendent.
D. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
E. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until
5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer. Contractor must notify Contracting Officer 24 hours prior to commencement of work and provide written notification to all the nearby residences.
F. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
G. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified on the attached site map or as established at the preconstruction meeting.
H. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.
I. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
J. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
K. Refer also to Section 01 11 40 Work Restrictions and Section 01 50 00 Temporary Facilities
& Controls.
1.5 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are available upon request to supplement the information specified in the contract documents: Not applicable.
END OF SECTION 01 11 00
LAKE – PMIS 309889 01 11 40 - 1
WORK RESTRICTIONS
SECTION 01 11 40
1.1 PARK REGULATIONS
A. General: The Contractor must comply with the following rules and conditions:
1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.
2. Ensure equipment is conspicuously marked for identification.
3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.
4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.
5. Control and provide security of Contractor-owned equipment and materials at the work site.
Report immediately missing / lost / stolen property to the park dispatch / law enforcement rangers at 702-293-8998 NON-EMERGENCY.
6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
a. Contractor will provide the Contracting Officer with a listing of its subcontractors and their associated vehicles and employees entering the park on a daily basis.
b. Contractor will provide the Contracting Officer with a listing of anticipated deliveries for each week.
7. Vehicles / Heavy Equipment:
a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.
LAKE – PMIS 309889 01 11 40 - 2
c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.
e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.
f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).
Oversized vehicles must not exceed the clearances along the Park road corridor.
Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).
j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.
k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11).
No loads heavier than the current load rating for the historic Park bridge will be permitted.
8. Emergency Medical and Accident Reporting:
LAKE – PMIS 309889 01 11 40 - 3
a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.
Emergency number: Dial 911 as needed.
Park Dispatch: 702-293-8932 EMERGENCY
Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park:
Park Dispatch: 702-293-8998 NON-EMERGENCY
1.2 RESOURCE PROTECTION
A. General: The park is committed protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to packing / loading. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance. Contact the resource staff directly at 702-371-9673 or 702-293-8849 at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.
2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact park dispatch at 702-293-8998 immediately if animal is hit or injured or will not move off of the road. All contractor personnel working in Lake Mead National Recreation Area must have up-to-date Lake Mead desert tortoise awareness training. Prior to starting work, contact the resource staff directly at 702-371-9673 or 702-293-8849 at least three (3) business days in advance to schedule the desert tortoise awareness training.
3. Archaeological Resources: Archaeological resources are physical evidences of past human activity, including evidences of the effects of that activity on the environment.
Archaeological resources are found above and below ground and underwater. The contractor shall appoint an archaeological monitor during all ground-disturbing activities in archaeological sensitive areas. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer
LAKE – PMIS 309889 01 11 40 - 4
immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.
END OF SECTION 01 11 40
LAKE – PMIS 309889 01 27 00 - 1
DEFINITION OF CONTRACT PRICE ITEMS
SECTION 01 27 00
1.1 DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one bid item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related bid item.
C. Exact mounting locations to be coordinated with NPS Staff. All installation sites will be near the existing Entrance Stations.
1.2 LIST OF CONTRACT LINE ITEMS
Entrance Stations:
A. Contract Price Item No.1 – Entrance Station 658 (Overton Beach):
1. This price item consists of:
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
Provide before and after photographs.
The contractor shall ensure that the project is completed to all industry standards.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
B. Contract Price Item No.2 – Entrance Station 515 (Lake Mead Boulevard):
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
Provide before and after photographs.
The contractor shall ensure that the project is completed to all industry standards.
C. Contract Price Item No.3 – Entrance Station 708 (Temple Bar):
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
Provide before and after photographs.
The contractor shall ensure that the project is completed to all industry standards.
LAKE – PMIS 309889 01 27 00 - 2
D. Contract Price Item No.4 – Entrance Station 218 (Cottonwood Cove):
1. This price item consists of:
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
Provide before and after photographs.
The contractor shall ensure that the project is completed to all industry standards.
E. Contract Price Item No.5 – Entrance Station 701 (Kathrine Landing):
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
Provide before and after photographs.
The contractor shall ensure that the project is completed to all industry standards.
F. Contract Price Item No.6 – Entrance Station 329 (Willow Beach):
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
The contractor shall ensure that the project is completed to all industry standards.
T-Intersections:
G. Contract Price Item No.7 – Location along park road:
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
The contractor shall ensure that the project is completed to all industry standards.
H. Contract Price Item No.8 – Location along park road:
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
The contractor shall ensure that the project is completed to all industry standards.
LAKE – PMIS 309889 01 27 00 - 3
Roadside:
I. Contract Price Item No.9 – Location along park road: Temple Bar
All necessary permits, labor, materials, and equipment to furnish and install flashing caution sign.
The contractor shall ensure that the project is completed to all industry standards.
Upgrades:
J. Contract Price Item No.10 – Entrance Station 518 (Lake Mead Drive Parkway):
All necessary permits, labor, materials, and equipment to furnish and install UPGRADES to existing RU2 Fast 350 solar powered flashing caution sign.
The contractor shall ensure that the project is completed to all industry standards.
K. Contract Price Item No.11 – Entrance Station 704 (Boulder Beach):
All necessary permits, labor, materials, and equipment to furnish and install UPGRADES to existing RU2 Fast 350 solar powered flashing caution sign.
The contractor shall ensure that the project is completed to all industry standards.
END OF SECTION 01 27 00
LAKE – PMIS 309889 01 31 00 - 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00
1.1 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Pre-Installation Meeting. Contracting Officer will notify Contractor of tentative date for the Pre-Installation Meeting.
1. Letter designating Project Superintendent.
2. Installation Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Meeting is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Meeting date, the meeting will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued
1.2 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit an RFI utilizing the form designated by the Contracting officer.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
LAKE – PMIS 309889 01 31 00 - 2
7. Contractor’s signature.
8. Requested date for response.
9. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
END OF SECTION 01 31 00
LAKE – PMIS 309889 01 32 16 - 1
INSTALLATION SCHEDULE
SECTION 01 32 16
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Installation Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Installation Schedule Requirements.
3. Installation Schedule Updates.
B. Purpose: The purpose of the Installation Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Installation Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 SUBMITTALS
A. Schedule of Values: After contract award and before commencing installation submit a schedule of dollar values based on the Contract Price Schedule.
B. Installation Baseline Schedule: After contract award and before commencing installation, submit a baseline schedule, large enough to show entire schedule for entire installation period.
C. Installation Schedule Updates: Prior to the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.
1.3 COORDINATION
A. Coordinate Installation Baseline Schedule with the Schedule of Values, list of subcontracts, payment requests, and other required schedules and reports.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the installation baseline schedule
LAKE – PMIS 309889 01 32 16 - 2
submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.
2.2 INSTALLTION SCHEDULE REQUIREMENTS
A. Installation Baseline Schedule: Prepare Installation Baseline Schedule using computerized scheduling software.
1. Installation Baseline Schedule shall show submittal review, installation start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.
2. Establish procedures for updating Installation Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. Contracting Officer may request an updated Installation Schedule at any time to confirm progress of the work.
END OF SECTION 01 32 16
LAKE – PMIS 309889 01 33 00 - 1
SUBMITTAL PROCEDURES
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 GENERAL SUBMITTAL PROCEDURES
A. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. CM-16 Transmittal Form: All submittals shall be transmitted using National Park Service form CM-16 form, attached to the end of this specification section. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form.
Complete the general information at the top of the form.
a. Provide all required information based on the submittal type
b. Attach all related documents.
c. Sign the CM-16 form in the contractor section at the bottom of the form.
2. Physical samples: Complete the CM-16 form as outlined above, and deliver the physical sample to the CO (or designee) on site for processing. All comments and actions will be documented on the CM-16 form.
END OF SECTION 01 33 00
LAKE – PMIS 309889 01 33 23 - 1
SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
SECTION 01 33 23
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with the requirements.
C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
E. Drawings (DWG): A proprietary binary file format used for storing two- and three- dimensional design data and metadata. It is the most widely used format for CAD drawings. Latest, AutoCAD, format preferred.
1.3 GENERAL SUBMITTAL PROCEDURES
A. General: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual specific sections.
1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.
LAKE – PMIS 309889 01 33 23 - 2
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list.
The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
D. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence when an e-mail notification is received by the Contracting Officer (or designee) indicating the submittal has been posted on the NPS SharePoint website and is ready for review. When the Contracting Officer has completed their review, an e-mail notification will be sent to the Contractor indicating the submittal has been processed. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action Submittals
a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
b. Re-submittal Review: Allow 15 days for review of each re-submittal.
2. Informational submittals
a. Review: Allow 10 days for review of each submittal.
E. Approved Equals:
1. For each item proposed as an “approved equal,” submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
LAKE – PMIS 309889 01 33 23 - 3
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
F. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. CM-SPE Transmittal Form: All submittals shall be transmitted using National Park Service form CM-SPE form. The form is accessed and completed on the NPS/DSC SharePoint Project website. No action will be taken on a submittal item unless accompanied by the CM-SPE transmittal form.
a. Complete the general information at the top of the form.
b. Provide all required information based on the submittal type
c. Attach all related documents.
d. Sign the CM-SPE form in the contractor section at the bottom of the form, and select “submit” when complete.
2. Physical samples: Complete the CM-SPE on the NPS/DSC SharePoint Project website as described above. Deliver the physical sample to the CO (or designee) on site for processing.
All comments and actions will be documented on the CM-SPE form on the NPS/DSC SharePoint Project website.
G. Identification: Submittal number or other unique identifier, including revision identifier.
1. Submittal number shall use a sequential number (e.g., .001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., .001.A).
H. Re-submittals: Make re-submittals using the same process used with the initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in the title block on the CM-SPE and clearly indicate the extent of revision.
3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities.
J. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction.
LAKE – PMIS 309889 01 33 23 - 4
1.4 CONTRACTOR’S USE OF CAD FILES
A. General: At Contractor’s written request, copies of CAD files will be provided, if available, to Contractor for Contractor’s use in connection with Project, subject to the following conditions:
1. Files will be provided as is; no format or other changes to files or changes to the objects in the drawing will be done by the Government.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer’s product specifications.
b. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
c. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.
d. Wiring diagrams showing factory-installed wiring.
e. Printed performance curves.
f. Operational range diagrams.
g. Compliance with specified referenced standards.
h. Testing by recognized testing agency.
4. Submit product data in PDF file format before or concurrent with samples.
B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
LAKE – PMIS 309889 01 33 23 - 5
f. Shop work manufacturing instructions.
g. Templates and patterns.
h. Schedules.
i. Notation of coordination requirements.
j. Notation of dimensions established by field measurement.
k. Relationship to adjoining construction clearly indicated.
l. Seal and signature of professional engineer if specified.
m. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
2. Submit shop drawings as a PDF electronic file.
C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Complete and post the CM-SPE on the NPS SharePoint website for processing and documentation of action on submitted samples.
3. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Submittal Number and title of appropriate Specification Section.
4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
5. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit two (2) full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Contracting Officer will return submittal with options selected.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit four sets of Samples. Contracting Officer will retain three Sample sets; remainder will be returned. Samples NOT Required.
LAKE – PMIS 309889 01 33 23 - 6
D. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by individual Specification Sections.
1. Post informational submittals as PDF electronic files directly to the NPS SharePoint website.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Informational submittals that do not comply with the requirements specified in the Contract Documents will be rejected and one copy will be returned.
B. Coordination Drawings: Comply with the requirements specified in Section 01 31 00 “Project Management and Coordination.”
C. Contractors Construction Schedule: Comply with the requirements specified in Section 01 32 16 “Construction Schedule.”
D. Accident Prevention Plan: Comply with the requirements specified in Section 01 35 23 “Safety Requirements.”
E. Schedule of Values: Comply with the requirements specified in Section 01 32 16 “Construction Schedule.”
F. Waste Recycling Plan: Comply with the requirements specified in Section 01 74 19 “Construction Waste Management and Disposal.”
G. Quality Control Plan: Comply with the requirements specified in Section 01 40 00 “Quality Requirements.”
H. Storm Water Pollution Prevention Plan: Comply with the requirements specified in Section 01 57 23 “Under-An-Acre Pollution Prevention” and any storm water permit requirements identified in Section 01 31 00.
I. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
J. Welding Certificates: Prepare written certification that welding procedures and personnel comply with the requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.
LAKE – PMIS 309889 01 33 23 - 7
K. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying that Installer complies with the requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
L. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying that manufacturer complies with the requirements in the Contract Documents. Include evidence of manufacturing experience where required.
M. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying that product complies with the requirements in the Contract Documents.
N. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying that material complies with the requirements in the Contract Documents.
O. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with the requirements in the Contract Documents.
P. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with the requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
Q. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
R. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
S. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
T. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with the requirements in the Contract Documents.
U. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with the requirements specified in Section 01 78 23 “Operation and Maintenance Data.”
V. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load
LAKE – PMIS 309889 01 33 23 - 8
diagrams if applicable. Provide name and version of software, if any, used for calculations.
Include page numbers.
W. Manufacturer’s Instructions: Prepare written or published information that documents manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
X. Manufacturer’s Field Reports: Prepare written information documenting factory-authorized service representative’s tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with the requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with the requirements.
Y. Permit Compliance Products: Prepare required information for compliance with permit provisions. Products include written notification of project startup, suspension, and completion of work; photo documentation of site conditions; reports; and drawings.
PART 3 - EXECUTION
3.1 CONTRACTOR’S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
3.2 CONTRACTING OFFICER’S ACTION
A. General: Submittals will be disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
1. Any work done or orders for materials or services placed before approval shall be at the Contractor’s own risk.
B. Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-SPE Transmittal Form. The submittal will be marked in one of three ways as defined below:
1. APPROVED: Acceptable with no corrections.
2. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
LAKE – PMIS 309889 01 33 23 - 9
3. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
C. Informational Submittals: Contracting Officer will review each submittal and will either accept or reject it.
D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
END OF SECTION 01 33 23
LAKE – PMIS 309889 01 35 23 - 1
SAFETY REQUIREMENTS
SECTION 01 35 23
PART 1 - GENERAL
1.1 SUMMARY
A. General: This section includes establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Plan: After contract award and before the Pre-Construction conference, submit for review an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within ten (10) days. No progress payments will be made until the Plan is accepted.
1.3 QUALITY ASSURANCE
A. Comply with contract clauses entitled "Accident Prevention" and "Permits and
Responsibilities". In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.
2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
LAKE – PMIS 309889 01 35 23 - 2
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of one hundred dollars ($100). Notify Contracting Officer immediately in the event of a reportable accident. Within seven (7) days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
PART 2 - PRODUCTS
2.1 ACCIDENT PREVENTION PLAN
A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
2.2 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.
2.3 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of applicable ANSI standards.
PART 3 - EXECUTION
3.1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
LAKE – PMIS 309889 01 35 23 - 3
3.2 FIRE AND LIFE SAFETY
A. Comply with all electrical, industry and manufacturers safety standards.
B. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations.
Maintain readily available, on site, MSDS for each chemical if applicable.
1. Immediately report all spills of hazardous materials to the park.
2. Maintain a spill emergency response kit.
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.