A04_SOW_Install_Gates_at_Government_Wash_Area_(Rev__7_21_25).docx
DOCX document 650 KB Posted
- Attached to
- LAKE25-0115-INSTALL GATES AT GOV WASH
- Solicitation number
- 140P8125Q0065
About this file
This document is a Statement of Work (SOW) for the National Park Service's Lake Mead National Recreation Area, detailing a project to fabricate and install four metal gates at specific locations within the Government Wash area. The primary objective is to restrict unauthorized vehicle access and mitigate resource damage, littering, and safety concerns caused by dispersed camping. The gates will be constructed from carbon steel with 6" diameter post sleeves, 3" diameter arms, and 5" diameter posts, painted brown, and equipped with reflective tape and locking mechanisms.
The project requires the contractor to excavate and set gate posts in 3' x 3' x 3' concrete footings at four precise GPS-located sites along Northshore Road and utility access roads. The contractor will be responsible for gate fabrication, installation, site cleanup, temporary traffic control, and ensuring gates are visually level, functional, and secure. The solicitation is issued by the Department of the Interior National Park Service Pacific West Region, with the specific solicitation number 140P8125Q0065, targeting gate installation at Lake Mead National Recreation Area.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAKE – Fabricate and Install Gate at 8.0 Mile and Boxcar Cove Road
Lake Mead National Recreation Area
Boulder City, Nevada
SERVICES REQUEST: Fabricate and Install Gates at Government Wash Area
DATED: July 21, 2025
Prepared By: Trent Martinez, Supervisory Facility Operations Specialist
NATIONAL PARK SERVICE
Lake Mead National Recreation Area A04 statement of work: Fabricate and Install Gate at 8.0 Mile and Boxcar Cove Road
1. Background Lake Mead National Recreation Area (LAKE) is a U.S. national recreation area in Southeastern Nevada and Northwestern Arizona. Operated by the National Park Service, Lake Mead NRA follows the Colorado River corridor from the westernmost boundary of Grand Canyon National Park to just north of the cities of Laughlin, Nevada and Bullhead City, Arizona. LAKE offers many recreational opportunities including boating, hiking, fishing, and both tent and RV camping. Because of these attractions, dispersed camping of RV’s and campers in unauthorized areas has become a growing concern. Specifically, the Government Wash area of LAKE has become inundated with disperse camping that has resulted in resource damage, littering of trash, and lead to major health and safety concerns.
This project will fabricate and install four metal gates at the area of Government Wash. The gates will be of metal pipe construction and will need to span the entire road to restrict access of vehicles during closures. In addition to the gate, attachment poles will be installed to lock the gate arms in the open position. Gate drawings have been attached to this document as a guideline for fabrication and installation.
2. project Location:
Project locations:
1. Northshore Road Hwy 167 and 8.0 Mile Road GPS Coordinates 36.157489, -114.808090
2. Northshore Road Hwy 167 and Boxcar Cove Road GPS Coordinates 36.156848, -114.793656.
3. Government Wash Road and Utility Access Road GPS Coordinates 36.143153, -114.847190
4. Northshore Road and Utility Access Road GPS Coordinates 36.148631, -114.846218
3. Project Tasks
The following tasks shall be completed by contractor as a part of this contract:
a) Fabricate gates, gate posts, and attachment posts based on drawings attached to document, tasks within this statement of work, and information requested by NPS COR and maintenance staff. All pipe used for construction of the gate will be carbon steel and at a minimum have schedule 40 wall thickness.
b) Gate arms will have a 6” diameter post sleave and 3” diameter arms. Gate post will be made of 5” diameter pipe and pipe hinge to allow gate arms to sleave over post and utilize pipe hinge. Attachment posts will be made of 5” diameter pipe.
c) Gate arms shall lock with a pin to each other when closed and shall lock to attachment posts by chain when kept open. NPS will provide padlocks for locking the gates and other components chains, pins, fasteners, and accessories shall be provided by the contractor.
d) Paint all metal finishes brown (NPS will provide exact color code) with high performance oil-based enamel paint.
e) Excavate and set gate posts and attachment posts in a 3’ x 3’ x 3’ concrete footing just outside of edge of road. Contractor shall set exact location of posts to assure proper opening and closure of the gates and gate elements in the field.
f) Excavate and set gate attachment posts according to the drawings assuring gate arms open with the flow of traffic of each lane and are slightly past parallel to road edge when secured open.
g) Install highway approved reflective tape along the top post of the gate arms and around the top of each gate arm, attachment post, and bollard.
h) Assure gate arms swing fluidly, lock and open without use of force, weight, or additional tools. Pins and locking mechanism are easy to remove and use without hammers or adjustments.
i) Finished gate will be visually plumb and level, paint will be free of chips and scratches, fasteners and pins will be secure, and concrete foundations will be smooth and level.
j) All equipment tracks showing on unpaved surfaces will be raked, debris removed from site, and road swept of debris caused by the construction.
4. Contractor Use of Premises
a) Contractor will keep worksite organized and clean as work allows
b) Designated areas for staging and contractor access will be identified by NPS COR
c) Contractor will be responsible for disposal of all construction debris and waste
d) Contractor will provide temporary traffic control while working in the road and road shoulders in accordance to the Nevada Department of Transportation Guidelines
e) Any government property damaged during this project will be replaced at the contractor’s expense
f) COR has the right to revoke any of the above privileges at any time if cleanliness or unprofessional behavior warrants it image1.wmf
File details come from the government source that posted it. Updated .