This document appears to be a Statement of Work (SOW) for the demolition and removal of an existing wood frame storage building, including associated electrical work, under a federal contract opportunity.

The SOW provides general information and requirements for the project, which is located in Eagle County, Colorado. It outlines the submittals required, such as work schedules and electrician qualifications, and details the quality assurance standards, delivery and storage specifications, and project/site conditions. The SOW also covers project meetings, preparation, salvage of certain items, disposal of debris, and warranty requirements. The work described in this SOW will not be measured for direct payment, but the cost will be considered included in the bid price for other contract items.

The related federal contract opportunity is for the "BLM-CO STATE BRIDGE BUILDING REMOVAL" project, solicitation number 140L1724Q0027, issued by the Department of the Interior Bureau of Land Management Colorado Region.

View the file

Other files for this federal contract opportunity

Other files attached to BLM-CO STATE BRIDGE BUILDING REMOVAL, newest first.
File Type Posted
Sol_140L1724Q0027_Amd_0002.pdf PDF
Sol_140L1724Q0027_Amd_0001.pdf PDF
Sol_140L1724Q0027.pdf PDF
A06-Location_of_Site.pdf PDF
B13_-Past_Performance_Questionnaire.doc DOC document
A06-Electrical.pdf PDF
A06-_Existing_Site_Plan.pdf PDF
A04-BID_Schedule.pdf PDF
A06-Building_Demo.pdf PDF
A06-Rough_Carpentry.pdf PDF
A06-Building_Details.pdf PDF
B03-DOL_Wage_Determination.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL INFORMATION AND REQUIREMENTS

State Bridge Building Removal 11/01

01009 - 1

SECTION 01009

PART 1: GENERAL

1.1 SUMMARY

A. Description of Work: Furnishing labor, equipment, supplies, and materials as needed, for the demolition and removal of an existing wood frame storage building. Work also includes miscellaneous electrical work associated with the building removal.

B. Location: Work under this Contract is in Eagle County, Colorado. The work location is shown on the drawings.

1.2 DEFINITIONS

A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing.

1.3 SUBMITTALS

A. Scope: Submittals include work schedules and electrician qualifications information.

B. Requirements: Refer to specifications for submittals required. Allow at least 5 working days for review. Submittals shall be delivered electronically in “PDF” format to bvecchia@blm.gov.

C. Identification of Submittals: Completely identify each submittal by showing at least the following information:

1. Name and address of submitter, plus name and telephone number of the individual to contact for further information.

2. Name of project as it appears in these specifications.

3. Contract number, drawing number, and specification section number to which the submittal applies.

4. Whether this is an original submittal or resubmittal.

1.4 QUALITY ASSURANCE

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

01009 - 2

C. Equipment: Prior to ordering equipment, verify dimensions and functions of equipment proposed for use including the electrical service requirements.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Delivery: Protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.

B. Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling.

1.6 PROJECT/SITE CONDITIONS

A. Access to the Work: As per Federal Acquisitions Regulations Clause 52.236-10. Access to work locations within the sites shall be limited to existing roads only.

B. Environmental Considerations: As per Federal Acquisitions Regulations

Clause 52.236-9 and 52.236-10.

1.7 SEQUENCING AND SCHEDULING

A. Work Schedule: The schedule shall be submitted within 5 calendar days after signing the Notice to Proceed and as per Federal Acquisitions Regulations Clause 52.236-15. When requested, submit an updated schedule. At a minimum, the schedule will state the estimated timeframes for the work to be performed.

PART 2: PRODUCTS

(There are no applicable requirements.)

PART 3: EXECUTION

3.1 PROJECT MEETINGS

A. Pre-Work Conference:

1. Will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.

3. Be prepared to summarize and explain procedures planned for the project.

B. Progress Meetings:

1. To be held at the project site, or as determined by the Contracting

Officer.

01009 - 3

2. May be called by either the Contracting Officer or the Contractor.

Request shall state who should attend and include an agenda.

C. Final Inspection:

1. To be held at the project site, or as determined by the Contracting Officer.

2. Notify the Contracting Officer in writing at least 5 working days before the completion date so the Government can schedule final inspection.

3.2 PREPARATION

A. Work Limits and Control Points: Will be established by the Contracting Officer.

3.3 SALVAGEABLE ITEMS

A. Requirements: Salvageable items consisting of electrical circuit breaker box including wiring, conduits, and miscellaneous electrical items, existing phone junction box, phone call box, phone sign, and miscellaneous items associated with the phone system shall become the property of the Contractor. Remove and store items designated as salvage until the items are re-installed as shown on the drawings. Replace the items designated as salvage for the Government that are lost or destroyed during demolition work.

3.4 DISPOSAL OF DEBRIS

A. Requirements: Items or debris not designated as salvage for the Government shall become the property of the Contractor. Disposal of materials in a legal manner and payment of fees required is the Contractor's responsibility.

3.5 WARRANTY

A. Requirements: Materials and equipment furnished under this Contract shall be covered by the most favorable commercial warranties given to customers for such materials or equipment. The rights or remedies provided herein are in addition to and do not limit rights afforded to the Government by other clauses of this Contract. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the Contract the Contractor shall:

1. Obtain warranties that would be given in normal commercial practices.

2. Require warranties to be executed, in writing, for the benefit of the

Government.

3. Submit warranties to the Contracting Officer prior to the final inspection.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this section will not be measured for payment.

01009 - 4

4.2 BASIS OF PAYMENT

A. Payment: No direct payment for the work described under this section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.

END OF SECTION