A04 SOW.pdf
PDF 398 KB Posted
- Attached to
- CACO - REHAB OF COAST GUARD BEACH RESTROOM
- Solicitation number
- 140P4320R0016
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and A_0001.pdf | ||
| STATEMENT OF WORK ADDENDUM_0001.pdf | ||
| Sol_140P4320R0016_Amd_0001.pdf | ||
| B03 DOL DBA GD MA20200001.pdf | ||
| Sol_140P4320R0016.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Exterior and Interior Rehab of Coast Guard Station Restroom
CAPE COD NATIONAL SEASHORE
Coast Guard Beach Road, Eastham, MA
April 16, 2020
Scope This project is to perform cyclic maintenance on the historic Coast Guard Beach restroom building. This project funds work aimed at protecting the exterior fabric of the building and maintaining the appearance at the Coast Guard Bathhouse at Cape Cod National Seashore, as well as replacing interior and exterior building components that are reaching the end of their useful life.
The contractor shall minimize disturbance to the site and items to remain to the greatest extent possible unless directed otherwise.
The contractor shall provide all labor, materials, tools, and equipment required to complete this work.
All work performed under this contract shall be done in accordance with applicable local, State, and Federal codes, bylaws and ordinances in effect at the time of this work.
Measurements Estimated dimensions and quantities are provided as a guide only. The contractor is responsible for verifying all measurements and dimensions. The contractor shall take all measurements for quantities of materials and note existing conditions for the installation of new work. All ancillary work, cutting and /or removal of existing work necessary for the installation of new work shall be done as required as part of this contract.
Site Examination It is the responsibility of the contractor to examine the work site to confirm existing conditions and required quantities prior to submitting a proposal on this project. Location, date and time of the site visit will be listed in the solicitation.
Base Proposal Work Elements Contract Line Item Number 10 - Exterior work shall include:
replace gutters and downspouts, scrape, repair as necessary, re-glaze, and refinish wood windows, color to match existing, replace any deteriorated fascia, cornerboards, baseboards, soffits and trim in-kind with pre-finished wood material to match existing - assume replacement of 25 linear feet of fascia, 25 linear feet of cornerboards, 32 linear feet of baseboards, 25 linear feet of soffits, 250 linear feet of trim boards eliminate all bird nesting cavities, install bird-proofing materials, scrape and re-finish all exterior surfaces, caulk all joints and gaps.
Scope, Option Proposal Work Elements Option: Contract Line Item Number 20 – Repair of restroom and changing room floors shall include:
prepare restrooms and changing rooms for floor repairs, shot-blast, diamond grind or power scarify the existing restroom and changing room floors, (the contractor shall evaluate the ideal method to prepare these floors for epoxies and resurfaces) repair cracks and imperfections in floors, if necessary, for a smooth uniform surface, seal floors with moisture-vapor-transmission-mitigating primer, install self-leveling epoxy slurry flooring in restrooms and changing rooms, install wear-resistant urethane protective surface.
Option: Contract Line Item Number 30 – First floor interior work shall include:
repair bathroom wall wainscoating as necessary – assume 300 sq ft, scrape, repair and refinish first floor bathroom windows, walls and ceilings, replace metal access panel doors and air grates, remove and reattach bathroom partitions as necessary, Option: Contract Line Item Number 40 - Plumbing work shall include:
replacement of all plumbing items and piping in the pipe chase including flushing lines, replacement of shutoff valves and all piping in pipe pit, vent stack repair with fittings, replacement of all piping, fixtures and fittings at floor mop basin, replacement of all plumbing for fixtures, replacement of all fixtures in the restrooms, and addition of hose bibb for custodial, additional piping and fittings to isolate each restroom and also each fixture in each restroom, additional cleanouts for sediment removal, cleaning out of all waste lines, replacement of all pressure tanks in kind, and all associated electrical and plumbing, replacement of water heater and all associated electrical and plumbing.
Option: Contract Line Item Number 50 - Electrical work shall include:
replace fluorescent fixtures throughout building with LED fixtures, replace light fixtures in chase-way with LED fixtures, replace first floor main panel board service and affiliated circuit breakers, replace all GFCI outlets throughout building, replace all hand dryers.
Option: Contract Line Item Number 60 – Second floor interior work shall include:
remove 9” floor tiles and replace with sheet vinyl flooring, remove baseboard heating, cap connections if necessary and repair openings, scrape, repair as necessary, and refinish wood window interiors, scrape and refinish stairs, replace vinyl stair treads, scrape, repair and refinish second floor doors, walls, trim and ceilings, Historic Nature of Work Site The contractor shall note the historical significance of the site upon which the work will be performed.
Because of the historic nature of this site, certain aspects of the work of this Contract will not be carried out with materials and/or methods commonplace in the modern construction industry. It shall be incumbent upon the contractor to furnish staff who can execute first-class workmanship in the materials and methods specified, and who will take any necessary precautions to protect the elements of this historic site not scheduled to receive work.
The park has not tested the upstairs for hazardous materials. Based on the age of the building, it is suggested the contractor confirm the status of materials prior to commencement of work and handle them in accordance with regulations.
Utilities and Services The contractor shall provide and maintain sanitary facilities for workers.
The contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. Notify Contracting Officer and utility companies of proposed locations and times for excavation. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
Water Service: Water from existing water system is normally available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. If water is not available, the contractor shall provide temporary water at no additional cost to the contract for project use.
Electric Power Service: Electric power from existing system is normally available for use during construction without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs.
Arrange with utility company and government for time when service can be interrupted, if necessary, to make connections for temporary services. If electric power is not available, the contractor shall provide temporary power at no additional cost to the contract for project use.
Permits and Approvals If appropriate, the contractor is responsible for contacting Dig Safe (#811) or other approved utility marking entity for pre-marking of all underground utility locations within project area prior to any ground disturbance. Prior to commencement of any on-site excavation work, provide COR with copies of proof of pre-marking from utility marking entity.
The contractor shall obtain all required permits for the performance of the work specified in Contract Documents at no additional cost to the contract.
Submittals and Deliverables The contractor shall submit fall protection plan and safety plan that complies with OSHA standards within 3 business days after award.
The contractor shall submit a traffic safety management plan that addresses public and contractor parking, vehicular circulation, pedestrian circulation, laydown, moving of materials and equipment within 3 business days after award.
The contractor shall submit an environmental protection plan that addresses protection of existing landscape elements, including lawn areas within 3 business days after award.
The contractor shall propose location of laydown and stockpile area for NPS approval. Laydown and stockpile shall be confined to any existing paved areas only.
Product Data: provide manufacturers' literature on characteristics of materials, maintenance, parts list and warranties. Submit only pages which are pertinent. Mark each copy to identify pertinent products referenced to the specifications. Provide manufacturers’ literature, drawings, and technical data sufficient to fully define the material and to demonstrate full compliance with the contract specifications.
Manufacturer's Installation Instructions: Include special precautions from manufacturer.
Drawings: submit drawings as appropriate.
Materials: submit representative samples of all materials to be used in sizes adequate to define the purpose of the material and determine its suitability.
Manufacturer's certificate: certify that products meet or exceed specified requirements.
Upon completion of project, submit as-builts in electronic form suitable to Park.
Safety and Environmental Protection Requirement Maintain project area in a neat, orderly and safe condition at all times. All work areas shall be made secure and safe after hours, on weekends and holidays.
Unless otherwise indicated by the park, all debris and removed material is the property of the contractor and shall be recycled or legally disposed of in a manner that is consistent with local and state regulations. All waste, trash and debris generated as part of this project must be secured from wind and rodent action.
The contractor shall take all necessary precautions to prevent fire during construction. The contractor shall provide and maintain suitable fire protection equipment. Protection Equipment Required: Furnish a minimum of one UL Class 2A, 2-1/2 gallon water type stored pressure extinguisher, and one UL Class 10, Type I, 15 pound A:B:C carbon dioxide extinguisher at each work site.
No radios or smoking (including vaping) will be allowed on the job site. Confined-space entry, fall protection and hardhat use will conform to safety rules and regulations.
The contractor is responsible for securing the site and the work of the contract. During the execution of this contract, the contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards. The contractor shall provide barriers, temporary fencing, signage, etc. wherever work could cause injury to workers or visitors, and ensure that ladders, scaffolding and equipment are secured from public access during off-hours.
The contractor shall provide and maintain environmental protection during the life of the Contract to control pollution or to correct conditions that develop during construction.
Equipment shall not be allowed to operate outside the limits of work or to disturb existing vegetation.
Construction equipment shall be kept in good repair, without leaks of hydraulic or lubricating fluids.
The contractor must visually inspect all equipment prior to commencing work every day and at the mid-point in the work day for leaks. If such leaks or drips do occur, they shall be cleaned up immediately.
Confine equipment maintenance to one location. Control runoff in this area to prevent contamination of soils and water. No equipment repair will be allowed on the site.
It is the contractor’s responsibility to ensure that any disturbance or damage done during the course of this project to the existing utilities, landscape, building or government materials, shall be repaired or restored to its original condition by the contractor at the contractor’s expense prior to completion of the job.
Work and Weather Limitations Regular work hours are between 7AM to 4PM Monday through Friday. Unless otherwise requested and approved in advance, no work shall take place after hours, on holidays or weekends. Requests must be made 48 hours in advance.
The contractor shall be responsible for storage of all materials and equipment; the Park must approve the contractor’s use of any space on the site in advance.
Proceed with project only when existing and forecasted weather conditions will permit work to be performed according to manufacturers' recommendations and warranty requirements. Ensure temperatures are over the minimum installation temperatures recommended by material manufacturers.
Security and Safety The contractor shall have unescorted access to the construction site. The contractor shall coordinate with the COR for access to all locations.
The COR or the COR’s alternate will not be required to be at the site location during all working hours.
Regulations
• Occupational Safety and Health Administration (OSHA)
• National Institute for Occupational Safety and Health (NIOSH)
• Massachusetts General Laws and Department of Environmental Protection regulations and statutes
• Town Board of Health Regulations
Materials The contractor shall furnish, supply, and install all necessary materials to successfully complete the project requirements. Unless explicitly indicated, new materials shall match those being replaced.
Where a product is specified only by a manufacturer name and model number/brand name, the contractor shall use only that model/brand product. Where the properties of a product are specified by description and/or with performance criteria, the contractor shall use products that comply with the description and/or performance criteria. Where manufacturers are listed for a particular product, the contractor shall use a product made by one of those manufacturers that also complies with other requirements. Where actual brand name products are not identified by either the Contracting Officer or the contractor, the contractor shall identify the products to be used.
Restroom and changing room flooring Crack repair material shall be a sandable epoxy, polyurethane, or polyurea based crack repair or crack filling compound.
Moisture vapor transmission mitigating primer shall be a two component, 100% solids, alkali resistant epoxy prime coat intended for concrete surfaces subjected to moisture vapor transmission (MVT). As an advisory to the contract, FloroPoxy MVT-99 Primer meets the requirements of this contract.
Self-leveling epoxy slurry flooring shall have the following characteristics: Sward Hardness, ASTM D2240, Compressive Strength ASTM C579, Tensile Strength, ASTM D2370, Abrasion Resistance: Taber Abrader CS-17 Wheel, 1000 gm. load, 1000 cycles, ASTM D4060, Coefficient of Friction: James Friction Tester, ASTM D2047, Indention MIL-D-3134F, Impact Resistance ASTM D3134. As an advisory to the contract, FloroStoneTM, Decorative Self-Leveling Epoxy Slurry Flooring System meets the requirements of this contract. Color shall be Meadow Green FS-400.
Wear-resistant urethane protective surface shall be a high solids aliphatic urethane coating wih the following characteristics: Sward Hardness, ASTM D2240, Tensile Strength, ASTM D2370, Abrasion Resistance, Taber Abrader CS-17 Wheel, 1000 gm. load, 1000 cycles, ASTM D4060, Coefficient of Friction, James Friction Tester, ASTM D2047, Percent Elongation, Coating, ASTM D2370, Percent Elongation, Resin Only, ASTM D2370. As an advisory to the contract, Florowear 7100 High Traffic Urethane Flooring System meets the requirements of this contract.
Sheet vinyl floor covering shall be 12’ wide low-VOC Grade 1 scratch, stain and scuff resistant with a waterproof core in a tile pattern to be selected by the COR from samples provided by the contractor.
Floor covering adhesive shall be compatible, low-odor, zero-VOC recommended by floor covering manufacturer for bonding flooring installations over porous and non-porous substrates under heavy static loads.
Heat weld rod to connect two pieces of sheet vinyl together shall be 3.5mm diameter weld rod as recommended by the sheet vinyl flooring manufacturer for the product specified with color to match flooring.
Plumbing All plumbing components shall be lead-free.
Waste pipes and fittings shall be PVC plastic pipe: ASTM D2665, schedule 40 PVC. Socket fittings: ASTM D2665, made to ASTM D3311 drain, waste and vent pipe patterns. Joining material: ASTM D2564, solvent cement approved by pipe manufacturer. Sink P-Traps shall be schedule 40 PVC with threaded connections for easy cleanout.
Vent stack material shall be PVC, designed for the purpose and sized to match existing, with appropriate support brackets.
Domestic water piping and fittings shall be copper pipe: ASTM B88, copper tubing, hard drawn, Type L.
Fittings: ASTM B16.18, cast copper alloy, or ASTM B16.22, wrought copper. Joining material: ASTM B32, Alloy SN95, or SN94 lead free solder. Valves shall be same size as upstream piping. Exposed piping at plumbing fixtures shall be chrome-plated brass pipe.
Ball Valves: 4-inch and Smaller, Class 150, 600 psi, ASTM B584 bronze body and bonnet, two- piece construction, chrome-plated brass ball, conventional port, bronze or brass stem; Teflon seats and seals;
threaded or soldered end connections, vinyl-covered steel lever handle and handle memory stop.
Unions: ASME B16.22, wrought copper solder joint, ground seat. Rated for 250 psig minimum working pressure at 180 degrees F. temperature.
Flanges: Class 125, cast bronze flanges. 150 psig minimum working pressure, with bolt insulators, dielectric gasket, bolts, and nuts.
Bolts and Nuts: Type 316 stainless steel square head machine bolts and heavy hex nuts.
Gaskets: ASME B16.21, nonmetallic, flat, 1/16-inch, full faced, for potable water service.
Dielectric Connections: Fitting having insulating material isolating joined dissimilar metals.
Floor drains: Replace floor drains with new to match existing size and fit in existing pipes. Adjust to new flooring and connect to existing piping.
Water hammer shock absorber shall meet ASSE standard 1010, bellows or piston type with pressurized cushioning chamber, size based on water-supply fixture units.
Water heater shall be a 4500 watt stainless steel 40 gallon electric water heater with 316 stainless steel tank and two stainless steel element. As an advisory to the contract, Westinghouse Model # WER040C2X055 meets the requirements of this contract.
Water pressure tanks and pressure relief valves shall match existing in size, quality, capacity and functionality. Existing pressure tanks are Amtrol model WX-350 with150 psi capacity pressure relief valves. Provide new shutoff ball valves & 3/4” drain valves with hose connection.
Fixtures Provide plumbing fixtures, appliances, and equipment complete and usable. All plumbing fixtures, appliances and equipment, piping, valves, accessories, and appurtenances shall comply with International Plumbing Code (IPC) and all other applicable codes and standards, including energy, water conservation, and local activity regulations and standards.
Toilets shall be ANSI A112.19.2 wall-hung or floor-mounted to match existing, siphon-jet vitreous-china closet bowl, with elongated rim, 1- 1/2 inch spud, china bolt caps. Barrier free adjusted for 16-1/2" bowl height. Acceptable manufacturers: American Standard Companies, Inc., Crane Plumbing, L.L.C./Fiat Products, Eljer, Kohler Co., Peerless Pottery, Inc. Wall Mounted Carrier for toilet: ANSI A112.6.1;
adjustable cast-iron frame, integral drain hub and vent, adjustable spud, lugs for floor and wall attachment, threaded fixture studs with nuts and washers.
Toilet Seat shall be extra heavy-duty, white, elongated, open front without cover, solid polypropylene plastic seat with integral bumpers and hardware. Acceptable manufacturers: Bemis Manufacturing Company, Centoco Manufacturing Corp., Church Seats, Kohler Co., Olsonite Corp.
Toilet flushometers shall be lever-type integral to toilet plumbing.
Urinals shall be vitreous china low-flow wall mounted urinal with integral housing and drain vent. As an advisory to the contract. Acceptable manufacturers: American Standard Companies, Inc., Crane Plumbing, L.L.C./Fiat Products, Eljer, Kohler Co.
Wall Mounted Carrier for urinal: ANSI A112.6.1; cast-iron and steel frame with tubular legs, lugs for floor and wall attachment, threaded fixture studs for fixture hanger, bearing studs.
Sinks shall be ADA wall-mount porcelain with a single opening for a faucet and built in overflow drain.
As an advisory to the contract, Kohler K-2358-1-0 and Kohler K-2035-1-0 meet the requirements of this contract.
Faucets shall be brass metered flow as manufactured by Moen, Delta, American Standard, Central Brass.
No plastic fixtures will be allowed. Hose bibbs in restrooms for custodian shall be solid brass with integral vacuum breaker and key handle.
Sealant for joints between fixtures and walls, floors, and counters shall be sanitary-type, one-part, mildew-resistant, silicone sealant. Match sealant color to fixture color.
Air grilles and fasteners shall be 316 stainless steel, to match size, function and appearance of existing.
A-J Manufacturing is a supplier of air grilles.
Access panel doors and fasteners shall be 316 stainless steel, to match size, function and appearance of existing.
Electrical Hand dryers shall be no heat 4.5 Amps 110/120V GreenSpec Listed, 10 Second Dry Time, 500 Watts Surface Mounted , activated by infrared optical sensor, ADA-Compliant, HPD Certified, White Epoxy cover finish, adjustable speed and sound control, adjustable heat control, washable metal mesh filter, entire dryer internally grounded, airflow rate 19,000 LFM at nozzle and 16,000 LFM at average hand position of 4 inches below air outlet, made in the USA. Dimensions: 11 3/4” W x 12 11/16” H x 6 11/16” D, Weight: 15-17 lbs. As an advisory to the contract, Excel Dryer XLERATOReco XL-BW-ECO 1.1N -H as manufactured by Excel Dryer Inc., East Longmeadow, MA meets the requirements of this contract.
Overhead light fixtures shall be surface-mounted 4 foot 35 watt LED luminaires, sealed to prevent intrusion of moisture and dust and UL approved for wet locations, 4000K rated with ABS housing and polycarbonate lens, stainless steel mounting bracket and lens clips and heavy duty bracket for ceiling installation, with internal occupancy sensor. As and advisory to the contract, Model BVTPLED-40-4KMV- ET with MC613VDRC included as manufactured by LED Lighting Wholesale Inc. meets the requirements of this contract.
Branch circuit connection between disconnect and water heater shall be either LFNC or LFMC type cable.
GFCI duplex outlets shall be new to match existing.
Panel Board service shall be equivalent electrically sized panelboard, Single Phase, 100 amp, 120/240 volt, 22 Space (minimum) with Main disconnect and 20 (single pole) 20 amp breakers, 1 (single pole) – 15 amp breaker, 1 (2-pole) 30 amp breaker.
Wood for exterior fascia, cornerboards, baseboards, soffits and trim New board materials shall be clear grade: species, sizes and profiles to match existing, assume STK grade red cedar. materials shall be factory pre-finished.
Fasteners Fasteners shall be of a length sufficient to penetrate into the sheathing at least ¾”, stainless steel type 316 nails or screws specifically intended for the use required. No staples or non-316 stainless steel fasteners will be allowed.
Bird proofing materials shall be stainless steel repellant devices designed for the purpose as manufactured by Nixalite of America, Bird B Gone, Inc. or other approved equivalent.
Window sash chain shall be heavy-duty brass to match existing. Include all necessary hardware. Any missing window components shall match existing.
Finishes All finishes shall be factory applied to all surfaces of new wood materials in a manner consistent with manufacturer’s recommendations and best practices of the industry.
Interior paints, primers, sealers, and undercoats shall be suitable for bathrooms and compatible with the finish coat and each other. Include mold and mildew inhibiters. Finish coat paint shall be semi-gloss enamel, color to be selected by COR from samples provided by the contractor. Acceptable paint manufacturers include: Benjamin Moore & Co: www.benjaminmoore.com., PPG Architectural Finishes, Inc: www.ppgaf.com., Sherwin-Williams Company: www.sherwin-williams.com.
For exterior surfaces, the first coat shall be opaque oil-based semi-solid stain-blocking solid color stain with mold and mildew inhibitors. Top coats shall be opaque oil-based stain-blocking paint with mold and mildew inhibitors. Color: to match existing.
Painting and finishing products for use in the work shall be the standard best or top brands produced for each particular kind of material required herein.
The contractor shall obtain the same products used in factory finish for treatment of all field cuts prior to installing cut material, in accordance with manufacturer’s recommendations.
Caulking for joints or gaps around doors, windows, or siding where water invasion may occur shall be Benjamin Moore Elastomeric 465 01 Caulk, or an approved equivalent.
Glazing Compound shall be linseed oil putty.
Wainscoating, if necessary, shall match existing in material and appearance.
Vinyl stair treads shall be heavy-duty rubber stair treads intended for commercial or industrial use with compatible adhesive. Nose of stair tread must conform to the shape of the stair tread. Include non-slip vinyl mat of similar appearance at landing.
Gutters and Downspouts
Gutters shall match existing wood gutters, including finish. Gutter outlet shall be 16oz Copper B Style Outlet for Half Round Gutter. Downspouts shall be rectangular white aluminum sized to match a sample provided by the park.
Epoxy consolidant for gutter end grain shall be one-part polyurethane high-performance sealant, Sonneborn NP 1 or an approved equivalent.
Workmanship The contractor is responsible for appropriate quality control and workmanship shall be the best of their respective kinds and in full accordance with applicable codes.
Make sure all work is flush, square, level and has proper reveals per manufacturer’s specs. If not sure ask COR before starting.
When a manufacturer or a standard uses subjective words, e.g., “should, could, may”, etc., these words shall mean “shall, will, required”, etc. When the word “recommended” is used, it shall mean “required”. If there is a conflict between general and specific provisions, the specific shall govern.
Ensure that all work is free from dirt, damage or defects. Pick up extra materials within 2 days of job completion. Do not use windows for access or to pull cords, hoses or siding materials though. Do not cut through trim or siding while on the building to avoid damaging the underlayment. Do not nail cleats or wood blocks onto or in finished siding products. Appropriate manufacture cleats shall be used that slide up under shakes. Never splice trim or siding when full-length material will fit.
Upon Notice to Proceed, the contractor shall make steady and uninterrupted progress toward the completion of the work of this contract.
All work shall be done under appropriate weather conditions, as defined by the manufacturers of the relevant products and in compliance with all codes in effect at the time of installation.
Demolition Before beginning any demolition or deconstruction work, inspect and examine the site to determine the extent of the work. Take necessary precautions to avoid damage to existing items, including trees, to remain in place, to be reused, or to remain property of Government.
Provide waste-collection containers in sizes adequate to handle waste from construction operations.
Comply with requirements of agency(ies) with jurisdiction.
Unless otherwise indicated, disposal of removed materials shall be the contractor's responsibility.
Salvage items of a historical nature, including copper downspouts and conductor heads. All debris and removed material is the property of the contractor and shall be recycled or legally disposed of in a manner that is consistent with local and state regulations.
Disconnect and remove all existing plumbing fixtures in Men’s and Women’s restrooms. Disconnect and remove all piping, valves, venting and fixtures in plumbing chase. Disconnect and remove existing pressure tanks and water heater and associated items.
Disconnect and remove main electrical panel, all existing 4’ fluorescent lighting fixtures, round lighting fixtures in chase-ways and GFCI outlets. Second floor hall overhead light to remain.
Remove all bird nesting and roosting materials and debris.
Disconnect, remove and dispose of baseboard heating. Cap connections as necessary and repair any openings in wall or floor.
Remove and dispose of 9” floor tiles on second floor in accordance with all current regulations in a manner that does not damage sub-floor.
Remove and dispose of vinyl stair treads and repair and damage or defects in stairs.
Storage of Equipment and Materials The contractor shall be responsible for storage of all materials and equipment; the Park COR and / or Project Inspector must approve the contractor’s use of any space on the site in advance.
Upon completion of the work of this contract, the storage area shall be left broom clean by the contractor.
Installation All work shall be done in conformance with the Secretary of the Interior Standards for the Treatment of Historic Properties.
Workers performing plumbing and electrical work shall be licensed by the Commonwealth and be able to provide a current copy of license upon request.
Flooring: restrooms and changing rooms Carefully remove baseboard in a manner allowing reinstallation prior to commencing floor work.
Before application of surface treatment, the floor shall be examined for spalls, pits, holes, cracks, nonfunctional joints, etc. Repair cracks and imperfections in floors, if necessary for a smooth uniform surface. For functional or expansion joints, these shall be treated with 100% solids elastomeric resin having a minimum elongation of 150%.
Shot-blast, diamond grind or power scarify as required to obtain clean, open porous concrete (the contractor shall evaluate the ideal method to prepare these floors for epoxies and resurfaces). Remove sufficient material to provide a sound surface, free of laitance, glaze, efflorescence, and any bond-inhibiting curing compounds or form release agents. Remove grease, oil, and other penetrating contaminants. Repair damaged and deteriorated concrete to acceptable condition; leave surface free of dust, dirt, laitance, and efflorescence.
Mix components according to flooring system manufacturer’s instructions. The surface should be dry prior to application of materials. Ensure the substrate is always kept clean, dry, and free of any contaminants. The handling and mixture of any material associated with the installation of the system shall be in accordance with the manufacturer’s recommendations.
A neat finish with well-defined boundaries and straight edges shall be provided by the applicator.
All areas considered for the application shall be primed with the manufacturer’s primer to seal and penetrate the substrate in preparation for applying the topcoat. Porous concrete substrates may require additional applications of primer followed by an intermediate coat.
Apply self-leveling epoxy slurry flooring in accordance with the manufacturer’s recommendations.
Apply wear-resistant urethane protective topcoat to seal the surface and give the floor improved wear resistance.
No traffic or equipment shall be permitted on the floor during the curing period.
Flooring: second floor Remove all subfloor nails that have backed out and replace with countersunk screws. Repair any defects in subfloor to provide a structurally-sound uniform surface prior to installation of new materials.
Prepare subfloor to ensure proper adhesion of flooring system per adhesive manufacturer’s written instructions.
Lay out flooring to minimize seams. Locate seams in low traffic areas where possible. Install flooring and heat weld rod seams per manufacturer’s current installation guide.
Protect flooring from foot traffic for time specified for adhesive before and after installation per adhesive manufacturer’s instructions to allow proper set up time.
Protect flooring from heavy traffic, point or rolling loads for a minimum of 48 hours or longer depending on conditions, after installation. Wait 48 hours before wet cleaning.
Plumbing and Fixtures Furnish and install new plumbing fixtures, associated piping, and related accessories in restrooms and pipe chase, and connect to existing piping to remain. Location of all fixtures shall be as required by ADA accessibility regulations. Furnish and install all connections and hardware for complete and operational plumbing system. Installation shall be by licensed installer in accordance with manufacturer's recommendations. Seal joints between fixtures and walls, floors, and counters using sanitary-type, one-part, mildew-resistant, color-matching silicone sealant.
Install new custodian hose bibb in sink area in each restroom.
Location of plumbing lines shall be modified as required by field conditions to meet the requirements to accommodate layout and fixtures. The contractor shall furnish and install all connections and hardware for complete and operational plumbing system. Make joints between dissimilar piping by dielectric unions or flanges. The contractor shall verify location and check the condition of existing sanitary and water lines at points of connection of new piping. Verify final equipment locations with field measurements and with the requirements of the actual equipment to be connected.
Remove bottom 4’ of vent stack and replace with PVC to match size of existing. Support vent stack as necessary to maintain its functional integrity. Take care not to damage roof boots or roofing, ensure a weatherproof seal at roof boot.
Waste, water, and other services shall be fully connected to each individual piece of apparatus with required piping, unions, flanges, valves, check valves, and other needed appurtenances. Size cleanouts same as drainage piping. Install cleanouts at each change in direction of piping greater than 45 degrees.
Install cleanouts at base of each stack and each change in direction. Each branch pipe shall be controlled by gate valve where it connects to supply main or riser. Each toilet room, group of fixtures, or isolated fixture shall be separately controlled by valves in accessible location and provided with access doors where necessary. Install ball valve between shock absorber and water line for servicing.
Replace water pressure tanks and all associated electrical and plumbing per manufacturer’s instructions, complete, including pressure relief valves at manifold, with piping and shutoffs and sillcock winter drains.
Install shutoffs for water fountains, outdoor showers and water line to sheds.
Install all piping with 0.25 percent slope toward drain.
Remove and replace floor drains with new to match existing size and fit in existing pipes. Adjust to flooring and connect to existing piping. Clean sediment and debris from drain lines in restrooms, pipe chase and floor mop basin line by water jet all the way to the septic system.
Install swing joints or expansion loops to allow for pipe expansion. Securely anchor pipes so expansion can occur at these joints. Make joints between dissimilar piping by dielectric unions or flanges.
Use reducing fittings wherever a change in pipe size occurs. The use of bushings will not be permitted.
Install low point drains in cold and hot water systems. Install traps on fixtures and equipment requiring connection to sanitary system. Traps shall be same size as pipe on which they occur. Provide cleanouts for all traps. Vent traps as required by local codes.
Provide piping with unions to permit alterations and repairs.
Unless otherwise indicated, exposed piping at plumbing fixtures shall be chrome-plated brass pipe. Sink P-Traps shall be schedule 40 PVC with threaded connections for easy cleanout.
Install water heater, including shutoff and all associated electrical and plumbing per manufacturer’s instructions, including branch circuit.
Flush and clean sanitary lines and remove water and debris before final connection into existing lines.
Electrical Install new main electrical panel and breakers in same location as removed panel.
Install new LED light fixtures in same locations as removed fluorescent fixtures. Install new LED light fixtures in same locations as removed 12” round fixtures in chase-ways.
Install new GFCI duplex outlets in same locations as removed outlets with polycarbonate thermoplastic faceplates to match wall color.
Interior Finishes Paint ceilings, windows, doors and walls. Comply with manufacturer’s recommendations in preparation of surfaces to receive paint and application of paint itself. Procedures shall include, but not necessarily be limited to, the following: Clean and remove oil, grease and loose foreign matter, including mold mildew, dirt and corrosion products, in a manner which causes neither undue damage to the substrate nor damage to, or contamination of, the surroundings or the paint system to be applied.
Pressure wash all surfaces.
Remove all cracked, chipped, and peeling paint. Sand walls and ceiling smooth. All holes, cracks and marks shall be repaired with wall material, fillers, sealants, putties as appropriate for the finish in accordance with industry standards before painting.
Adequately scuff and/or solvent or chemically etch as appropriate to provide satisfactory adhesion for subsequent coats.
Unless otherwise specified, ensure that surfaces are cured and dry before applying additional coats of paints.
Remove all drips/runs or objectionable surface irregularities.
Apply an appropriate primer to any bare surfaces.
Apply paint and related material with an undercoat plus two coats of selected finish color as specified in accordance with manufacturer’s recommendations. Allow each coat to harden for the drying time (or time between coats) recommended by the manufacturer. Ensure each coat of paint is uniform in color, gloss, thickness and texture and free of runs, sags, blisters, or other discontinuities.
Install air grates and access panel doors.
Install stair treads and landing mat according to manufacturer’s directions.
Exterior Finishes Remove and reattach exterior wiring and other items and hardware as necessary.
Repair all areas of deteriorated wood. All new material shall be factory pre-finished. Carefully excise deteriorated sections of wood members. Leave keys to receive repairs, Replace deteriorated wood with dutchmen repairs.
Unless covered elsewhere, the work includes preparation and painting with a three (3) coat system (one
(1) primer coat and two (2) finish coats) of the exterior exposed materials and surfaces of all exterior wooden surfaces and finishes.
No exterior finishing shall be undertaken if air or surface temperature is below 50 degrees Fahrenheit or immediately following rain or until frost, dew or condensation has evaporated.
Remove damaged or deteriorated paint to the next sound layer using the gentlest method possible (e.g., hand scraping and hand sanding) prior to any necessary repairs and repainting.
All surfaces specified to be finished shall be wiped down with a dry cloth and be dry and cleaned free of all dirt, grit, grease, mold, mildew, foreign substances and all loose, peeling, blistering, chalking or scaling paint.
Each coat of finish shall be evenly worked out and allowed to dry according to the manufacturer’s recommendations before subsequent coats are applied. Prime coat of stain and two coats of finish coat to match existing.
Install wood gutters to match existing with mitered returns, pitch minimum ¼”/10’ to downspouts. Seal end grain with epoxy consolidant prior to priming, painting, assembling, sealing, and flashing. Miter and rabbet joints and install recessed lead flashing, seal with caulking. Install gutter outlets. At the lower end, install a sloping piece of lead flashing to make the short length of gutter from the outlet to the low end drain back into the outlet. Treat inside of gutters with raw linseed oil.
Install bird repellant in locations deemed necessary to keep birds from nesting or roosting.
Caulking All joints or gaps around doors, windows, baseboards or siding where water invasion may occur shall be filled with Benjamin Moore Elastomeric 465 01 Caulk, or an approved equivalent, not to be applied until primer coating is applied and allowed to dry a minimum of 24 hours.
Windows Follow best practices regarding removal and reinstallation of glazing compound. Remove all loose and deteriorated glazing compound. If necessary, secure loose glass with glazing points and apply linseed oil glazing material. Allow glazing compound to cure and skin over before paint application.
Apply primer to sash. On all window sash, extend paint 1/16″ onto glass to seal glazing. If sash is operable, it is important to paint bottom edge to prevent water invasion. Paint all sides if sash is removed from structure, to seal against water invasion.
Clean glass prior to finish paint application with glass cleaner that does not contain ammonia.
Apply finish paint. As with the primer, extend paint 1/16″ onto glass to seal glazing. If it is necessary to clean the glass after applying the finish paint, do not break the paint seal between the glass and the finish paint.
Restore windows to full functionality with new sash chain and hardware as necessary. Sashes must meet so that the sash lock engages and the window provides a weathertight seal.
Plumbing Startup Test drain, waste, and vent piping on completion of rough-in. Close openings in piping system and fill with water to point of overflow but not less than 10 feet of head. Water level must not drop from 15 minutes before inspection starts through completion of inspection. Correct leaks and retest system.
Cap domestic water piping and subject piping to static water pressure of 50 psig above operating pressures or 150 psig maximum without exceeding pressure rating of piping system materials. Allow to stand for 4 hours. Correct leaks and loss in pressure and retest system.
Before start-up, verify that piping, and related systems have been tested, and operational and performance tests have been made. Disinfect all water piping and equipment upon completion of piping installation. Following disinfection, flush water from system through its extremities. Continue flushing until samples show quality is comparable with public water supply and complies with requirements of public health authority having jurisdiction.
Clean-Up After completion of the work, construction debris, excess material and equipment shall be removed from the site and legally disposed. The contractor shall use a magnet of sufficient strength to ensure no metal is left behind. Upon completion of the work of this contract, work areas shall be left broom clean by the contractor.
Period of Performance Preconstruction meeting – Will be held within one week of contract award.
Notice to Proceed – Will be provided to the contractor after preconstruction meeting and upon receipt of all required documents.
Material Submittals – Due within 48 hours (or 2 business days) of Notice to Proceed Proposed completed work with all documentation submittals – 60 days after date on the Notice to Proceed for the Base and 120 days after the date on the Notice to Proceed if options are elected.
Map of Project Location
Project Location