STATEMENT OF WORK ADDENDUM_0001.pdf

PDF 78 KB Posted

Attached to
CACO - REHAB OF COAST GUARD BEACH RESTROOM
Solicitation number
140P4320R0016
Issued by

View the file

Other files

File Type Posted
Q and A_0001.pdf PDF
Sol_140P4320R0016_Amd_0001.pdf PDF
B03 DOL DBA GD MA20200001.pdf PDF
A04 SOW.pdf PDF
Sol_140P4320R0016.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK ADDENDUM

Exterior and Interior Rehab of Coast Guard Station Restroom

CAPE COD NATIONAL SEASHORE

Coast Guard Beach Road, Eastham, MA

July 30, 2020

Please make the following additions and deletions to the contract SOW -

On page 1, Scope, Base Proposal Work Elements;

Replace the following: “replace gutters and downspouts,” With: replace damaged downspout sections (approximately 50%). All gutters and downspouts shall be painted to match existing.

Add: repair and reinstall conductor heads, park will provide missing conductor head.

On page 9, Materials: Gutters and Downspouts;

Add: Epoxy for conductor heads shall be as designed for the application.

Add: Paint for gutters, downspouts and conductor heads shall be intended for the application, color to match existing.

On page 15, Installation: Exterior Finishes;

Add: On all conductor heads, contractor shall remove minor dents, realign joints, apply a skim coat of epoxy patching material to interior surfaces, re-solder joints, repaint to match existing and reinstall.