STATEMENT OF WORK ADDENDUM_0001.pdf
PDF 78 KB Posted
- Attached to
- CACO - REHAB OF COAST GUARD BEACH RESTROOM
- Solicitation number
- 140P4320R0016
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and A_0001.pdf | ||
| Sol_140P4320R0016_Amd_0001.pdf | ||
| B03 DOL DBA GD MA20200001.pdf | ||
| A04 SOW.pdf | ||
| Sol_140P4320R0016.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK ADDENDUM
Exterior and Interior Rehab of Coast Guard Station Restroom
CAPE COD NATIONAL SEASHORE
Coast Guard Beach Road, Eastham, MA
July 30, 2020
Please make the following additions and deletions to the contract SOW -
On page 1, Scope, Base Proposal Work Elements;
Replace the following: “replace gutters and downspouts,” With: replace damaged downspout sections (approximately 50%). All gutters and downspouts shall be painted to match existing.
Add: repair and reinstall conductor heads, park will provide missing conductor head.
On page 9, Materials: Gutters and Downspouts;
Add: Epoxy for conductor heads shall be as designed for the application.
Add: Paint for gutters, downspouts and conductor heads shall be intended for the application, color to match existing.
On page 15, Installation: Exterior Finishes;
Add: On all conductor heads, contractor shall remove minor dents, realign joints, apply a skim coat of epoxy patching material to interior surfaces, re-solder joints, repaint to match existing and reinstall.