This Performance Work Statement (PWS) details a hazardous fuels reduction project for the Bureau of Land Management in White Pine County, Nevada. The project involves hand piling and cutting of pinyon and juniper trees across 414 acres (Units 1-3 for hand piling) and 124 acres (Unit 4 for cut and pile) in the Duck Creek Basin area, approximately 16 miles northeast of Ely. The primary objectives are community and watershed protection through vegetation management, with prescribed fire planned to remove created slash piles.
Key specifications include constructing hand piles between 5-7 feet in diameter and 4-6 feet in height, maintaining no more than one live pinyon or juniper stem per acre, and piling all slash greater than 2 inches in diameter. The project has strict environmental and timing considerations, with work prohibited between February 28th and July 31st due to sensitive resource restrictions. The contract period of performance is up to 30 days from award, with a total performance period of one calendar year. Contractors will be paid on a per-acre basis, with separate line items for hand pile and cut and pile treatments, and final payment contingent on satisfactory project completion and government inspection.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L3925Q0070.pdf | ||
| B03_SCA_Wage_Determination_White_Pine_2015-5601_Rev25.pdf | ||
| Bid_Schedule_-_Duck_Creek_Cut___Pile.pdf | ||
| A06_Maps_-_Combined.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Duck Creek Basin and Sawmill, Hand Pile 2025 Cut and Pile Performance Work Statement Page 1 of 4
Hazardous Fuels Hand Thinning Maintenance and Pile
Performance Work Statement
Work performed will be hazardous fuel reduction and mitigation within wildland urban interface with the goal of community and watershed protection. Prescribed fire will be utilized to remove the slash piles created by this project.
A. Project Area Description and Location
The contractor is responsible for furnishing all labor, equipment, supervision, transportation, supplies and materials to hand pile 414 acres of previously hand thinned treatment and cut and hand pile 124 acres of previously hand thinned treatment. All pinyon and juniper slash (previously cut) will be piled in hand pile units. All pinyon and juniper within the cut and pile units will be cut and piled as well as all of the pinyon and juniper slash that has been previously cut within the treatment units. No other species are to be removed or damaged. Leave areas, acreage and boundaries may be altered prior to implementation of the project to mitigate sensitive resource concerns that may reduce the acreage.
Work under this Contract is located in White Pine County, State of Nevada. The project area is located in Duck Creek Basin along the west side of the Schell Creek Mountain Range approximately 16 miles northeast of Ely, NV and within South Steptoe Valley along the West side of the Cave Valley Road (County Road 45) approximately 8 miles south of Ely (refer to attached Map). The area is typical Great Basin sagebrush communities.
Access to the Units 1, 2, and 3 is along the Duck Creek Basin Highway State Route 486 which is a paved road that can be accessed from Highway 93 approximately 15 miles north of Ely. Access to Unit 4 is along Cave Valley Road (County Road 45) Travel south-east approximately 6 miles from Ely on US Highway 50 to Cave Valley Road. Then travel south for approximately 1.75 miles. From the Cave Vally Road there are a few improved and unimproved roads that intersect the treatment unit. Several treatment units border private lands.
Contractors wishing to cross private lands to access the treatment units will be responsible for securing permission.
Although the roads are in good condition and the terrain within the project areas is gentle, four-wheel drive vehicles are recommended due to the potential for unexpected inclement weather conditions.
There are no seasonal weather restrictions unless heavy rains occur or during periods of snow melt which may result in an intermittent work schedule due to muddy conditions. Work shall not occur if project implementation is creating excessive rutting. Roads will be considered impassable when saturated and access into the project area may be closed by the government during this time.
The following legal land descriptions apply:
• Township 19 North; Range 65 East; Sections 28 and 29; MDM.
• Township 18 North; Range 65 East; Sections 29 and 32; MDM.
• Township 17 North; Range 65 East; Sections 7, 18, 19; MDM.
• Township 15 North; Range 63 East; Section 25; MDM
Cut and Pile Performance Work Statement Page 2 of 4
The treatment area boundaries will be outlined on a map provided by the Government. The Contractor will be responsible for ensuring that they are within treatment boundaries by utilizing a Global Positioning System (GPS) unit. The contractor may flag the boundaries of the unit at their discretion however, the contractor would be responsible for the removal of all flagging. Leave areas and boundaries may be altered prior to implementation of the project to mitigate sensitive resource concerns.
It is recommended that potential bidders become familiar with access to and within the sites, the density of the trees to be cut and the trees to be left by unit, and the timing restrictions by unit (see Section C).
There is a large variance in the density of the different tree species within the units. Pinyon and juniper is to be slashed and piled while mahogany will not be removed (see Section B.).
B. Specifications and Requirements
a. Hand Pile
Piling of all material greater than 2 inches in diameter will be conducted within the treatment units specified within the shapefile and the attached map. Pinyon and juniper slash may need to be cut in order to build piles sizes specified within each treatment unit. Piles shall be constructed to be between 5 and 7 feet in diameter and 4 to 6 feet in height. If there is not enough slash to construct piles of this size piles are to be constructed as close as possible with a height approximately 2/3 of the base. Piles shall be placed as far as practical from other tree species not targeted. Preferred pile placement will be on top of or directly next to pinyon and juniper saplings within the units.
A requirement of no more than one live pinyon or juniper stem per acre and all pinyon an juniper slash greater than 2 inches in diameter will be piled after treatment will be adhered to. If inspections indicate the quality of the work in all/some aspects does not meet this standard the unit will be reworked. Standard will be randomly sampled during inspections by the government representative via a transect and communicated to the contractor’s point of contact. The sampled areas may involve portions of a unit and not the entire unit and will be at the discretion of the government representative.
b. Cut and Pile
Cutting and piling will be conducted within the treatment units specified within the shapefile and the attached map. Trees shall be cut as specified within each treatment unit. Boles shall be cut as close to the ground as possible with a maximum height of 6 inches. Piles shall be constructed in the same manner as described under “Hand Pile”.
A requirement of no more than one live stem per acre remaining after treatment and all pinyon and juniper slasher greater than 2 inches in diameter will be piled will be adhered to. If inspections indicate the quality of the work in all/some aspects does not meet this standard the unit will be reworked. Standard will be randomly sampled during inspections by the government representative via a transect and communicated to the contractor’s point of contact. The sampled areas may involve portions of a unit and not the entire unit and will be at the discretion of the government representative.
Contractors are to submit a single bid for each line item on a per acre basis using the table in Attachment 1.
Cut and Pile Performance Work Statement Page 3 of 4
Table 1 – Table of treatment units by line item, treatment and size.
Line Item
Unit Number
Treatment Description
Total Acres
010 Unit 1 Hand Pile 122 020 Unit 2 Hand Pile 102 030 Unit 3 Hand Pile 190 040 Unit 4 Cut and Hand Pile 124
C. Environmental Considerations
The project site shall be cleaned up, and all refuse removed to an approved landfill at the Contractor’s expense.
The Contractor shall not disturb lands adjacent to the project site. Existing access roads and trails within the project area that are damaged by the Contractor shall be restored at the Contractor’s expense to the same condition they were in at the commencement of work. Stream channels, springs and other wet areas will be avoided by vehicles and heavy equipment.
Vehicles and other equipment used for implementation of the project shall be washed to remove any vegetation and potential noxious weed and invasive species parts prior to beginning the work and following completion of the work.
Due to timing restrictions for sensitive resources, treatments will not occur between February 28th and July 31st.
These timing restrictions shall be built into the proposal. No extensions to the performance period will be granted due to these timing restrictions.
D. Work Camp
Camping will be allowed during project implementation only at sites approved by BLM in advance. All fire regulations and permits shall be followed. All garbage and refuse shall be removed from the camp site by the contractor within fifteen days of camp abandonment. Final payment will be reserved subject to inspection of these sites by BLM and approval of site cleanup.
E. Pre-Work Conference
A pre-work conference will be held prior to the start of work, and within seven days of Contract award. The Contractor will be notified in advance of the meeting location, date and time. The purpose of the meeting will be to review the required work, the project location, project specifications, the work schedule, payroll and payments and administrative provisions of the Contract. The Contractor and the persons responsible for coordination of the work shall be present at the meeting. The Contractor shall be prepared to summarize and explain procedures planned for the project.
F. Progress Meetings
Meetings may be called by either the Contracting Officer or the Contractor. Meetings shall be held at the
Cut and Pile Performance Work Statement Page 4 of 4 project site, or as determined by the Contracting Officer.
G. Final Inspection
Final inspection for the project area shall be held at the project site or as otherwise mutually agreed by the Government and the Contractor. The Contractor shall notify the Government representative at least two (2) working days before the completion date, so the Government can schedule a final inspection. Final payment of the contract will be held pending the completion of a satisfactory final inspection of all associated areas.
H. Measurement of Payment
Work will be measured and paid for by the number of acres within each treatment unit as that unit is completed.
The total will be rounded up to the nearest whole acre. Once a treatment unit is complete the acreage completed may be billed for. Area measurements required under this Contract will be measured on a horizontal plane.
Prices and payment will be full compensation for the work described in this section. Payment will be made under the following:
Pay Item Pay Unit Hand Pile Acre
Cut and Pile Acre
The Contracting Officer or representative will make periodic inspections as a basis for progress payments and recommendations for adjustments in work quality. The Contractor or representative is encouraged to observe inspections at the time they are being made. Work performed according to the specifications will be considered acceptable for payment purposes.
I. Performance Schedule
Period of performance for this work shall begin as soon as possible following the award of the contract, not to exceed 30 days. The end of the performance period would be 1 calendar year from the award of the contract.
The Contractor shall be required to start and complete the treatment area within the performance time identified above or as otherwise negotiated during the pre-work conference, provided weather conditions permit. If inclement weather conditions should occur prior to the Contractor completing the project, the Contractor shall be issued a stop work order and the project shall be completed as soon as weather conditions permit.
Due to wildlife restrictions, work may only in the timeframes as described in the environmental considerations.
| A. Project Area Description and Location |
| b. Cut and Pile |
| C. Environmental Considerations |
| D. Work Camp |
| E. Pre-Work Conference |
| F. Progress Meetings |
| G. Final Inspection |
| H. Measurement of Payment |
| I. Performance Schedule |