A04_RTU_Replacement_SPECIFICATIONS_Redacted.pdf
PDF 325 KB Posted
- Attached to
- Rooftop HVAC replacement Federal contract opportunity
- Solicitation number
- 140L1726Q0025
About this file
This is a specifications document for a Rooftop Air Conditioning Unit (RTU) replacement project at the Montrose Public Lands Center in Montrose, Colorado, under the Bureau of Land Management, U.S. Department of the Interior.
The project requires replacement of an existing 5-ton Lennox RTU (Model TGA060S2DH1P, Serial 5607H17549) with a new packaged rooftop gas/electric unit meeting specific performance criteria. The replacement RTU must be a nominal 5-ton unit with dual-stage cooling operation, minimum 150,000 Btu/hr and 105,000 Btu/hr 2-stage natural gas heating input, and utilize R-454B (A2L compliant) refrigerant. Acceptable manufacturers include TRANE, Carrier, Lennox, or government-approved equivalents. The unit must be factory-packaged and UL-listed with integrated gas furnace, direct expansion cooling, supply fan, and controls providing a minimum of 2,000 cfm supply air, factory economizer with barometric relief, outdoor air intake hood, and filter section. The contractor bears responsibility for determining compatibility with the existing approximately 42-inch by 79-inch roof curb and existing electrical and gas service, with authority to provide adapter curbs or new curbs as necessary. Work is scheduled Monday through Friday, excluding federal holidays, with the facility remaining open to public and employees during construction. Required submittals include an initial project schedule, quality control manager identification, rooftop unit product data, and certification of qualifications for hazardous material removal. The contractor must handle refrigerant disposal per 40 CFR 82, protect existing roofing, provide weatherproofing and duct connections, and ensure integration with the existing Metasys Johnson Controls building automation system, including all necessary programming updates and graphic interface modifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L1726Q0025_Amd_0001.pdf | ||
| CLAUSE_AND_PROVISIONS_0001.pdf | ||
| Sol_140L1726Q0025.pdf | ||
| B03_2015-5435_REV_30.pdf | ||
| A04_RTU_Replacement_BID_SCHEDULE.pdf | ||
| A06_RTU_Replacement_-_Supplemental_Site_Pictures.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior Bureau of Land Management
Uncompahgre Field Office Colorado
Montrose Public Lands Center
Rooftop Air Conditioning Unit (RTU) Replacement
SPECIFICATIONS
Rooftop Air Conditioning Unit Replacement
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 46 00 QUALITY CONTROL
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 84 50 HAZARDOUS MATERIAL REMOVAL
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 81 10 ROOFTOP AIR CONDITIONING UNIT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
Replace an existing rooftop air conditioning unit (RTU).
1.2 LOCATION
The project is located at the Montrose public lands center.
Montrose Public Lands Center 2465 South Townsend Ave Montrose, CO 81401
1.3 WORK SCHEDULE
Work shall occur Monday - Friday. Work shall not occur on Federal
1.4 PUBLIC SAFETY
The Montrose Public Lands Center will remain open to the public and employees during the work. Contractor shall take precautions, as necessary, to protect the public and employees from construction hazards.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule ; G
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones, work listed in the bid schedule, and to allow for satisfactory project planning and execution.
3.2.2 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of submittals.
b. Long procurement activities.
c. Contractor's pre-final inspection.
d. Government's pre-final inspection.
e. Final inspection.
SECTION 01 32 01 Page 5
3.2.3 Government Activities
Include Government activities that could impact progress. These activities include, but are not limited to: Government inspections of work, Government approval of submittals.
3.3 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.
3.4 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
3.4.1 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.
3.4.2 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
SECTION 01 32 01 Page 6
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
1.2 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer's Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government.
1.3 GOVERNMENT APPROVING AUTHORITY
The Contracting Officer's Representative will:
a. Note the date on which the submittal was received.
b. Review submittals for approval within 10 days of receipt.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer's Representative and one copy of the submittal will be returned to the Contractor.
1.3.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until
SECTION 01 33 00 Page 7 resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.4 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer's Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.5 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 8
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 1 PAGES
South Building RTU Replacement 2026
01 32 01 SD-01 Preconstruction Submittals
GInitial Project Schedule
01 46 00 SD-01 Preconstruction Submittals
1.2 GQuality Control (QC) Manager
02 84 50 SD-07 Certificates
3.1Certification Of Qualifications
23 81 10 SD-03 Product Data
2.1 GRooftop Air Conditioning Unit
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SECTION 01 46 00
QUALITY CONTROL
PART 1 GENERAL
1.1 QUALITY CONTROL
Contractor shall establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction.
Quality control (QC) is comprised of plans, procedures, and organization necessary to produce an end product that complies with the contract requirements.
1.2 QUALITY CONTROL MANAGER
Provide a quality control (QC) manager at the work site to implement and manage the QC program. The QC Manager may also be the project superintendent.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Quality Control (QC) Manager ; G
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 QUALITY CONTROL
Contractor shall ensure that the construction complies with the requirements of the contract. At a minimum, perform the following prior to beginning work on each definable feature of work:
Review each paragraph of the applicable specification sections.
Review the contract drawings.
Verify that appropriate submittals have been approved.
Verify that the required preliminary work has been completed and complies with the contract.
Do not build upon nor conceal non-conforming work.
SECTION 01 46 00 Page 9
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 SECTION SUMMARY
Demolish existing rooftop air conditioning unit (RTU).
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 GENERAL
Do not disturb existing construction beyond the extent necessary for installation of new construction.
Protect items to remain during demolition.
3.2 DISPOSAL OF MATERIALS
Demolished items and materials shall become the property of the Contractor and removed from Government property and properly disposed of lawfully in accordance with applicable federal, state, and local regulations.
SECTION 02 41 00 Page 10
SECTION 02 84 50
HAZARDOUS MATERIAL REMOVAL
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
All hazardous materials must be properly removed prior to demolition.
Hazardous materials include, but are not limited to: ozone depleting controlled substances (refrigerants).
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 82 Protection of Stratospheric Ozone
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-07 Certificates
Certification Of Qualifications
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 OZONE DEPLETING CONTROLLED SUBSTANCES (REFRIGERANTS, COOLANTS, AND
HEAT TRANSFER FLUIDS)
Class 1 and class 2 ozone depleting controlled substances must be removed, and disposed of, in accordance with 40 CFR 82 . The removal must be completed by someone certified to complete the removal in accordance with 40 CFR 82 and with the state of Colorado. Submit the certification of qualifications certification of the person performing the removal and disposal.
3.2 OTHER HAZARDOUS MATERIALS
The BLM is not aware of any other hazardous materials in the demolition and work locations. The Contractor shall notify the BLM if any other hazardous materials, requiring special disposal are encountered prior to demolition.
SECTION 02 84 50 Page 11
SECTION 23 81 10
ROOFTOP AIR CONDITIONING UNIT
PART 1 GENERAL
1.1 SECTION SUMMARY
Replace the existing rooftop air conditioning unit (RTU).
1.2 EXISTING ROOF PENETRATION (ROOF CURB)
The size of the existing roof penetration (roof curb) at the existing RTU is approximately 42 inches by 79 inches. Contractor shall verify exact size.
1.3 EXISTING ROOFTOP AIR CONDITIONING UNIT (RTU)
Existing rooftop air conditioning unit (RTU) has the following properties:
Lennox S/N: 5607H17549
M/N: TGA060S2DH1P
Model Number Specifications Breakdown:
T: T-Class Product Line G: Packaged Gas Heat with Electric Cooling A: 1st Generation 060: 5 Tons Nominal Cooling Capacity S: Standard Efficiency 2: R-22 Refrigerant Type D: Direct Drive Blower Type H: High Gas Heat, 2-Stage 1: 1st Revision Minor Design Sequence P: 208/230V, 1-Phase, 60Hz Electrical Configuration
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Rooftop Air Conditioning Unit ; G
PART 2 PRODUCTS
2.1 ROOFTOP AIR CONDITIONING UNIT (RTU)
Contractor shall propose a replacement rooftop air conditioning unit (RTU). Government review is only on the contractor proposed RTU characteristics. Contractor is responsible for determining compatibility with the existing roof curb, electric, and gas service.
2.1.1 ROOFTOP AIR CONDITIONING UNIT (RTU) CHARACTERISTICS
Provide a packaged rooftop gas/electric unit, with a nominal 5-ton
SECTION 23 81 10 Page 12 electric cooling capacity with dual-stage (two-stage) cooling operation, and minimum 150,000 Btu / hr and 105,000 Btu/hr 2-stage natural gas heating input.
Refrigerant shall be R-454B (A2L compliant). Unit shall be factory-packaged, UL-listed, with fully integrated gas furnace, direct expansion cooling section, supply fan, and controls. Unit shall provide a minimum of 2,000 cfm of nominal supply air. Unit shall include factory economizer with barometric relief, outdoor air intake hood, and filter section.
Contractor shall provide a TRANE, Carrier, Lennox, or Government-approved equivalent.
2.1.2 ROOF CURB
Contractor shall be responsible for finding a RTU that is compatible with the existing roof curb. Or shall provide a roof curb adaptor, or new roof curb that is compatible with the contractor proposed RTU.
2.1.3 ELECTRIC AND GAS SERVICE
Contractor shall investigate the existing electric and gas service to determine an appropriate replacement RTU.
PART 3 EXECUTION
3.1 ROOF PROTECTION
Contractor shall take measures, as necessary, to protect the existing roof from damage during RTU installation. Contractor shall repair any damage caused by replacement of the RTU.
3.2 REMOVAL OF EXISTING ROOFTOP AIR CONDITIONING UNIT (RTU)
Dispose of refrigerant in accordance with section 02 84 50 HAZARDOUS MATERIAL REMOVAL. Existing RTU shall become property of the contractor and disposed of in accordance with section 02 41 00 DEMOLITION.
3.3 INSTALLATION
Install RTU level. Secure RTU to the building's structural supports.
Install in accordance with manufacturer's recommendations.
3.4 AIR DUCT CONNECTIONS
Connect the replacement RTU to the existing supply and return air ducts.
3.5 WEATHERPROOFING
Provide weather tight connection between roof and RTU. Provide single-ply roofing material to match existing, flashing, caulk, and other materials as necessary.
3.6 METASYS - JOHNSON CONTROLS
Existing thermostat and RTU is connected to Metasys monitoring. Metasys is the building automation environmental software that controls the HVAC to provide the environment within the building. The Metasys system is a
SECTION 23 81 10 Page 13 proprietary system that is managed by Johnson Control Building Solutions.
All programming and graphic interfaces, including setpoints, shall be updated as required to be monitored and controlled by Metasys, and is the responsibility of the contractor with the installation of the RTU.
3.7 TESTING
After installation of RTU, test and verify that the RTU is operating in accordance with the manufacturer's recommendations. Verify that the RTU is properly monitored and controlled by Metasys.
SECTION 23 81 10 Page 14
File details come from the government source that posted it. Updated .