This Performance Work Statement (PWS) outlines the characterization and cleanup requirements for the Former Sheep Island Boat Maintenance Facility located on Sheep Island in Uganik Bay, Kodiak, Alaska, under the U.S. Fish and Wildlife Service (USFWS). The project involves delineating and characterizing petroleum-contaminated soils and groundwater at the site, and removing lead-contaminated soil from marine batteries found on the beach. The contractor must be a qualified environmental professional meeting requirements under 18 AAC 75.33 and comply with Alaska Department of Environmental Conservation (ADEC) regulations and applicable federal requirements from USEPA, IEPA, OSFM, and OSHA.
The scope of work requires the contractor to prepare a detailed cost proposal categorized by 26 specific tasks, including pre-work meetings, work plan development with ADEC review, mobilization and demobilization, soil and groundwater sampling with analysis for GRO, DRO, BTEX, PAHs, and VOCs per ADEC protocols, lead contamination delineation and removal of up to 5 cubic yards of contaminated soil, completion of ADEC Contaminated Media Transport and Treatment or Disposal Approval Forms, and preparation of a Site Characterization Report and Corrective Action Completion Report (CACR) addressing remediation alternatives. The contractor must follow ADEC's 2024 Field Sampling Guidance and Site Characterization Work Plan standards, utilize ADEC-approved laboratories, maintain detailed field notes and daily reports, and coordinate all activities with the Contracting Officer, COTR, and Refuge representatives. The project schedule requires submission of a draft work plan within ten workdays of Notice to Proceed, with ADEC/government review taking 45 workdays, followed by field work and final reports due within 90 days of receiving laboratory analyses. Project completion is required by December 31, 2026. All work products, field notes, and documentation become the property of the government, with strict confidentiality requirements regarding survey data and cost estimates.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC126Q0023_Amd_0002.pdf | ||
| B09_AMENDMENT_P0002_0002.pdf | ||
| Sol_140FC126Q0023_Amd_0001.pdf | ||
| B09_AMENDMENT_P0001_0001.pdf | ||
| Sol_140FC126Q0023.pdf | ||
| B03_WAGE_DETER_05-18-2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Sheep Island Characterization Contaminated Soils Removal and Groundwater Investigation Kodiak NWR
KODIAK NATIONAL WILDLIFE REFUGE (NWR)
CHARACTERIZATION & CLEANUP FOR SHEEP ISLAND BOAT
MAINTENANCE FACILITY
PERFORMANCE WORK STATEMENT
Revised February 13, 2026
U.S. FISH AND WILDLIFE SERVICE
LEGACY REGION 7 ALASKA
GENERAL
BACKGROUND:
The Sheep Island Boat Maintenance Facility site is located on the northeast beach of Sheep Island, in Uganik Bay, in Kodiak. A cannery, along with a boat maintenance facility, were constructed during the late 1950’s or early 1960’s. The cannery went bankrupt in 1991 and abandoned the boat maintenance facility. An inspection of the abandoned facility revealed heavily stained soil over an area roughly 500 square feet in size. Samples collected from the stained areas in August of 1996 revealed DRO up to 41,000 mg/kg and RRO up to 120,000 mg/kg. It was determined that in-situ remediation was the best option for the stained area. In 1999, after tilling the soil and adding fertilizer, two composite soil samples were collected from 0 to 6 inches below ground surface (bgs) and 6 to 12 inches bgs, respectively. The composite sample collected from 0 to 6 inches bgs exhibited levels of DRO up to 20,000 mg/kg and RRO up to 52,000 mg/kg. The composite sample collected from 6 to 12 inches bgs exhibited levels of DRO up to 11,000 mg/kg and RRO up to 28,000 mg/kg. A follow-up evaluation of the site was conducted on June 20, 2019 by BGES. The soil boring samples were taken a 1 bgs and 2 bgs at nine (9) locations of the land farm site. All samples were below the DEC level for DRO of 230 mg/kg except for two (2) samples that were at 248 mg/kg and 302 mg/kg.
BGES site visit on June 20, 2019, also documented several broken lead marine batteries on the north and south beach. Only one site was sampled for lead. The total lead concentration was 6,800 kg, which exceeded the ADEC criteria of 400 mg/kg, The sample was analyzed for TCLP to determine the leachability of lead from the soil sample. TCLP for lead was 301mg/l, which exceeds the federal hazardous waste criterion of 5 mg/l.
Previous reports for the USFWS Sheep Island Boat Maintenance Facility shall be reviewed and used. They can be viewed on the Alaska Department of Environmental Conservation’s (ADEC) website: https://dec.alaska.gov/Applications/SPAR/PublicMVC/CSP/SiteReport/2105.
SPECIAL CONDITIONS:
Sheep Island is a remote island facility with absolutely no known amenities. All supplies and equipment necessary to perform this site survey/soil sampling must be transported to the site. The transportation plan to get to the island shall be coordinated through the Contracting Officer. The Contractor is responsible for all permits, Alaska Department of Environmental Conservation (ADEC) coordination, work plans, coordination with the Refuge, and contingencies.
Current property and adjoining property conditions will be documented that involve the use, treatment, storage, disposal or generation of petroleum products. Should these conditions be identified, the appropriate information will be collected, including storage tanks, odors, stained soil or pavement, stressed vegetation, pools of liquids, drums, unidentified containers, electric or hydraulic equipment, wastewater, solid waste, wells or septic systems. In addition, any indication of similar conditions from past use of the property will be recorded. Visual and physical geologic, hydro geologic, hydrologic and topographic characteristics of the property and adjoining properties will be noted for the potential of migration of contaminants. As appropriate, additional site visit information shall include as applicable, a general description of the structures, roads, potable water supply, and sewage disposal system.
Interviews with government officials shall be conducted in person, by telephone, or in writing. The contractor shall identify the key site manager who has a good knowledge of the uses and physical characteristics of the property. These interviews shall be conducted during the site visit. Appropriate local government officials may also be interviewed to obtain the necessary information. The contractor shall keep detailed notes of all interviews. These notes shall become the sole property of the USFWS. No one shall receive copies of notes, documentations, and reports without the permission of the government.
CONTRACTOR QUALIFICATIONS: Contractor experience must be approved by the Contracting Officer and will be based upon submission of the following information by the Contractor: Experience:
Name and location of a similar project completed by the Contractor, including the name and telephone number of the purchaser of the services. Comply with ADEC regulations and applicable requirements of USEPA, IEPA, OSFM, and OSHA regulation. Contractor shall be a “qualified environmental professional who meets the regulatory requirements described in 18 AAC 75.33. Contractor shall have project experience with work of this nature and his work crew shall have all necessary training and certifications.
CONFIDENTIALITY STATEMENT: Contractor shall protect the confidentiality of all work accomplished under this scope of work. Quantity surveys and cost estimates shall remain the sole property of the USFWS and shall not be made available to others for any purpose. Do not publicly disclose any data generated for review under this contract. Attachments provided are sole property of the USFWS. Submittals and data generated under this contract shall become the property of the USFWS and distribution to any other source, unless authorized by the USFWS, is prohibited. Direct any public inquiries to the Contracting Officer (CO), Contracting Officer Technical Representative (COTR) or the Refuge Representative. Do not divulge, explain, or share project information with anyone other than the government representatives above unless it is necessary to obtain permits, or clearances, etc. Any information that could have potential impact on the government shall be directed to the CO or COTR.
PROPOSAL:
Review this scope of work and the attached documents. Prepare a detailed proposal to complete the project in accordance with ADEC CSP Site Characterization Work Plan and Reporting Guidance for Investigation of Contaminated Sites and workplan. Categorize the proposal by task and subtask such as:
1. Pre-work meeting,
2. Development of workplan with ADEC review/comment resolution prior to starting work
3. mobilization,
4. demobilization,
5. airfare,
6. hotel,
7. per diem,
8. car rental,
9. licensing,
10. permits,
11. utilities locate
12. soil sampling costs,
13. ground water well installation cost
14. ground water sampling cost
15. lead contaminated soil disposal per cubic yard (up to 5 cubic yards),
16. lead contaminated soil additional soil removal per each additional 0.5 cubic yards,
17. clean soil (fill) cost,
18. lead contaminated soil disposal cost,
19. additional contaminated soils removal costs,
20. ADEC approval for transportation and disposal
21. additional clean soil (fill) costs
22. provide survey of site where samples were collected and results
23. Site Characterization Report with ADEC review/comment resolution
24. Corrective Action Completion Report with Corrective Action Plan that provides alternative methods to remediate site that results in final cleanup and/or no further action with/without institutional controls with ADEC review/comment resolution.
25. administrative costs, and
26. overhead and profit.
These are the minimum number of tasks; other tasks shall be added as approved and necessary.
WORK DESCRIPTION:
The purpose of this project is to provide all labor, resources, equipment, materials, permits, and services to delineate and characterize all the petroleum the contaminated soils and check for groundwater contamination on Sheep Island Boat Maintenance Facility and remove marine lead battery parts and lead contaminated soil from the beach.
1) The Contractor shall delineate soil contamination vertical and lateral, sample, and characterize the soil and ground water in the land farm area. The land farm samples analyzed in 2017 still show DRO contamination above the Table B2 Method Two Over 40 Inch Zone cleanup level of 230 mg/kg. Note: Groundwater sampling was not conducted in the land farm area and is required by ADEC for closure.
2) Soil and groundwater analysis shall include all the analytes listed in Appendix F of ADEC’s Field Sampling Guidance (2019): GRO, DRO, BTEX, PAHs, and VOCs. These data are required to evaluate the site for closure in the future.
3) Lead contamination removal and disposal from marine batteries that were found in two separate locations but have not been fully characterized or delineated. One soil sample was taken in 2017 and analyzed for lead, the result was 6,860 mg/kg. This is well above the Table B1 Method Two cleanup level of 400 mg/kg. The Contractor shall delineate and characterize this lead contamination and remove up to 5 Cubic yards of containment soil. If additional soil is identified, the contractor shall provide a cost per cubic yard for additional soil in bid. Any additional work shall be approved by contracting office prior to work being conducted.
4) Complete the ADEC Contaminated Media Transport and Treatment or Disposal Approval Form.
The form shall be submitted, prior to transport, to ADEC for approval in accordance with 18 AAC 75.325(i) and 18 AAC 75.360.
5) The Contractor shall provide a Site Characterization Report incorporating previous reports and current data collected during this contract. Previous reports and information can be viewed on the Alaska Department of Environmental Conservation’s (ADEC) website:
dec.alaska.gov/Applications/SPAR/PublicMVC/CSP/SiteReport/2105.
6) Develop a Corrective Action Completion Report (CACR) that discusses the cost and pros/cons of mitigating the site using active remediation, engineered barriers, institutional controls (Land Use Control Plan), or a combination of these methods if contamination remains on-site after completion of this work. The contractor shall provide a final recommendation based on this evaluation.
Please refer to DEC’s Field Sampling Guidance October 2024 for a list of analyte testing required for soil and water samples. This document is available at https://dec.alaska.gov/spar/csp/guidance-forms/. The groundwater shall not exceed the 18 AAC 75 Table C groundwater cleanup levels These data are required to evaluate the site for closure in the future.
Use Appendix F of ADEC’s Field Sampling Guidance, the following analysis and methods should be conducted for soil and groundwater: GRO (AK101); DRO (AK102); BTEX (EPA Method 8021B or 8260D); PAHs (EPA Method 8260D, 8270E, 8310); VOCs (EPA Method 8021B, 8260D).
Use Section 12 - Quality Control (QC) Measures of the Field Sampling Guidance Quality Control (QC) Measures to meet the Minimum Quality Assurance (QA) Requirements for Sample Handling, Reports, and Laboratory Data. The QA guidelines described in this memorandum are necessary to meet the requirements of 18 AAC 75.335; 75.360(2); and 18 AAC 78.007.
A Laboratory Data Review Checklist available at https://dec.alaska.gov/spar/csp/lab-approval/documents/ shall be provided for each analytical data package.
Use ADEC’s 2024 Site Closure Memorandum to ensure that future work at the site will move the site forward towards closure and is available at https://dec.alaska.gov/spar/csp/guidance-forms/.
Use ADEC’s Site Characterization Work Plan and Reporting guidance for Investigation of Contaminated Sites dated March 7, 2017. This document is available at https://dec.alaska.gov/spar/csp/guidance-forms/.
SCOPE of WORK:
Prepare the Cost Proposal (Note: Include projected cost for any coordination with ADEC or other agencies that may be necessary.
Conduct a kick-off/conference call meeting to review the proposed project work statement objectives and the project schedule. Contractor shall provide own meeting minutes and a list of action items, as needed.
Prepare a Draft and Final Work Plan (WP), which includes as a minimum Site Assessment, Sampling and Analysis, Ecological Risk, Health and Safety. After the Work Plan is approved the Contractor shall provide the services outlined in the plan task by task. Providing a cost task by task is critical for funding accuracy. Work Plan shall include: notes, documents, reports, expert recommendations, and task cost breakdowns. Review of the listed reports is critical to formulating a Work Plan that will achieve the government’s desired result.
Previous reports and information can be viewed on the Alaska Department of Environmental Conservation’s (ADEC) website:
dec.alaska.gov/Applications/SPAR/PublicMVC/CSP/SiteReport/2105.
Mobilize at the site following receipt of an approved Work Plan. The contractor will secure all tools and materials before leaving the work area.
Provide analysis of the suspected extent and distribution (horizontal and vertical) of petroleum contamination in soil
Provide analysis of the suspected extent and distribution (horizontal and vertical) of lead contamination in soil using XRF to identify soil to be removed and confirmation soil sampling of site where contaminated soil has been removed.
Conduct groundwater investigation to determine whether groundwater at the site has been impacted
Conduct remediation work to reduce and/or eliminate hazardous materials and properly dispose of materials.
Update Site Characterization Report for site based on historical data and data collected from this site.
Develop a Corrective Action Completion Report (CACR) that discusses the cost and pros/cons of mitigating the site using active remediation, engineered barriers, institutional controls (Land Use Control Plan), or a combination of these methods if contaminate above ADEC levels still are present. The contractor shall provide a final recommendation based on this evaluation.
Requirements:
Work Plan
The Work Plan shall be prepared, submitted, and approved prior to conducting any work. The Work Plan shall describe the approach to waste stream identification and segregation, sample location selection, workplan deviations, Conceptual Site Model, field screening method, collection of samples, field documentation, field quality control measures, tracking of samples, Investigation- Derived Waste (IDW), Quality Assurance Project Plan (QAPP), safety and health precautions, repair of damage caused by sample collection (where necessary), the experience and qualifications of the personnel conducting the survey, and identity of the ADEC certified laboratories that will be used. The Work Plan will be delineated by Task such that each task can be priced separately and clearly defined.
Quality Assurance/Quality Control:
The Contractor shall perform QC/calibration checks on all instruments (i.e. PID) in accordance with the instrument manufacturer’s PCS. At a minimum, calibration checks for each instrument shall be completed in accordance with the operator manual and the manufacturer’s PCS and documented if the final report. The calibration checks performed according to this paragraph that fall within the specification for the instrument shall demonstrate reading validity.
The Contractor shall follow Section 12 - Quality Control (QC) Measures of the Field Sampling Guidance Quality Control (QC) Measures to meet the Minimum Quality Assurance (QA) Requirements for Sample Handling, Reports, and Laboratory Data for all samples collected on-site.
The Contractor shall use a laboratory approved by ADEC for analyzing all samples.
Contaminated Soils and Groundwater Survey and Sampling:
Contractor shall provide the services of a qualified environmental professional to perform a soils investigation to complete sampling at the site. Major elements of the effort shall consist of the following:
Review all previous site reports and information and sample according to ADEC protocols.
Also develop a hypothesis about where contaminants might migrate to if they have spread out of the immediate government owned area. This hypothesis will be part of the Contractors proposal. The number, location and depth will be recommended by the contractor, as long as this is consistent with ADEC protocols and also gives the government the best most accurate information about soil contamination amounts and contamination migration. Any other soil samples necessary will be pre-priced by the Contractor on a per sample basis. The pre-price will be part of the proposal.
The Contractor shall conduct as many (a minimum of two (2)) groundwater samples as approved as necessary as long as this is consistent with ADEC protocols and also gives the government the best most accurate information about groundwater conditions. Additional samples necessary will be pre-priced by the Contractor on a per sample basis. The pre-price will be part of the proposal.
Samples shall be submitted to an ADEC approved laboratory for analysis of Diesel Range Organics (DRO) by Alaska Method AK102, Gasoline Range Organics (GRO) and Benzene, Toluene, Ethylbenzene, and Xylene (BTEX), by Alaska Method AK101. Environmental samples shall be delivered to the laboratory using chain-of-custody procedures.
Field headspace screening shall be performed on all soil samples taken from soil borings.
Samples shall be screened using a Photo Ionization Detector (PID). Readings shall be logged.
Mobilize at the site following receipt of an approved Work Plan. The contractor will secure all tools and materials before leaving the work area.
Prepare the site (locates, interviews, meetings, etc.). Implement spill control and erosion control measures as needed.
Provide analysis of the suspected extent and distribution (horizontal and vertical) of petroleum contamination in soil
Conduct groundwater investigation to determine where groundwater at the site has been impacted and if it is feasible to recover free product and/or treat the groundwater.
Perform all operations in a manner which will minimize dust, noise, and other nuisance.
Maintain haul routes for disposal of material, clean and free of debris.
Protect existing facilities from damage by falling debris, dust, and construction operations.
Perform operations in a manner that in no way endangers personnel, public, existing structures, utilities, road Contractor shall be responsible for damage to personnel, public, roadways, streets, structures, utilities, facilities, and equipment caused by operations and shall repair any damage at its own expense or replace items damaged beyond repair.
Materials to be removed will be permitted to accumulate on site. All materials shall be stored in a secured location at the end of the workday and in a manner to prevent contamination of the site.
Do not operate vehicles or equipment on existing construction or roadways which could be damaged.
Contractor shall relocate, as necessary, existing active miscellaneous piping, conduit, and electrical circuits and devices (if needed). Contractor is responsible for repairing any damaged assets or utilities.
The Contractor shall maintain field notes, daily logs, and photographs to document all field activities to include: site maps, excavation size, visibly contaminated soil, samples locations, depth to groundwater, and other important observations and events. Submit Field Notes to the Contracting Officer. All field notes shall become the property of the Government.
Provide the Contracting Officer with recommendations on further actions if necessary.
The Site Characterization Report shall follow ADEC CSP Site Characterization Work Plan and
Reporting Guidance for Investigation of Contaminated Sites provide (As a minimum):
1) A description of the work effort with analytical results that describes the significance of detected concentrations relative to appropriate regulations.
a. Note any discrepancies between the project work plan and the actual project activities performed.
b. Note any discrepancies between the Sample Location Selection detailed in the Work
Plan and any changes made during sampling, along with explanation of differences.
2) Results of the current round of sampling shall be provided in a spreadsheet with previous data collected 2017 and 2020 report and displayed on a map showing results and location of sample.
a. Date(s) of the survey and sample collection
b. Identification of field-portable methods used during the survey and applicable calibration check results.
c. Laboratory report and chain-of-custody forms
1) The Contractor shall require the laboratory to provide the information necessary for the Contractor to comply with the data evaluation/validation procedures outlined in this SOW. This shall include a data package containing the following information:
2) Cover page information including methods, dates, instruments, digestions, and signature of the laboratory director.
3) Sample information including identification and the results for samples, blanks, QC samples, dilution factors, and batch identification.
a. Comparison of the sample results to the cleanup levels for petroleum established by the Alaska Department of Environmental Conservation (ADEC).
3) In the conclusions and recommendations section, make a determination, using specific documentation and appropriate references, of whether chemical contamination is in the soil or groundwater, and if found, if the contamination may have been caused by the tank and/or piping.
4) The summary of all findings and recommendations shall be included in the Site Characterization Report and shall meet the requirements of the ADEC. The report shall be signed by a registered or licensed professional individual (s) in the employ of the Contractor as required by the State.
5) Respond to all comments received for U.S. Fish and Wildlife Service and ADEC.
Develop a Corrective Action Completion Report and Submit to ADEC that addresses:
1. For the purposes of the CACR, the specific pathways in which exceedances are present must be addressed. The pathways in question are:
a. Soil ingestion and inhalation pathways,
b. Soil component to the groundwater ingestion exposure pathway.
c. Groundwater ingestion pathway
d. Groundwater to Surface water exposure pathway.
e. Indoor inhalation pathway (Vapor Intrusion) (if a building is built in this location in the future),
f. Construction worker inhalation pathway.
2. The CACR shall develop a Corrective Action Plan that discusses the cost and pros/cons of mitigating the site using active remediation, engineered barriers, institutional controls (Land Use Control Plan), or a combination of these methods. The contractor shall provide a final recommendation based on this evaluation.
3. If Institutional Controls (Land Use Control Plan) is selected, work with U.S. Fish and Wildlife to develop and submit Land Use Control Plan to ADEC that will be recorded in the Kodiak NWR Comprehensive Conservation Plan (CCP) as a possibility.
4. Respond to all comments received from U.S. Fish and Wildlife and ADEC.
5. The report shall be signed by a registered or licensed professional individual (s) in the employ of the Contractor as required by the State.
DELIVERABLES:
● Pre-Work Meeting: Organize a pre-work meeting within 2 weeks of receiving the notice to proceed
(NTP). Within 10 workdays of pre-work meeting, contractor shall submit a Draft Work Plan for approval. The Service and ADEC requires 45 workdays to review and comment on the Draft Work Plan. After Draft Work Plan is approved, provide a copy of Final Work Plan within 10 workdays. With Final Work Plan ready, proceed to work site to complete all sampling activities. The Work Plan shall follow the ADEC 20217 Site Characterization Work Plan and Reporting guidance.
● Work Plans shall include a General Description Section followed by a Task Section
● Each task shall be broken down into sub-tasks. Sub-task shall include pictures and figures describing items and locations for sampling and remediation. The Task Section of the work plan shall be followed by a Regulation Section with all applicable federal, state and/or local regulations that regulate the handling, transporting, and disposing of all contaminated material from the site. The Regulation Section shall also identify the closest disposal locations for each waste stream.
● A Dailey Field Report
● Complete the ADEC Contaminated Media Transport and Treatment or Disposal Approval Form. The form shall be submitted, prior to transport, to ADEC for approval in accordance with 18 AAC 75.325(i) and 18 AAC 75.360.
● Prepare and submit copies of DRAFT Site Characterization Report and a Corrective Action Remediation Report within 90 days of receipt of regulatory sample analyses. Provide copies of report to CO, COR, Station, and ADEC.
● The government and ADEC shall have 45 days to comment on the Draft Reports. The Contractor shall then have 45 days to produce a Final Report. Provide copies of report to CO, COR, Station, and
ADEC.
● The final deliverable shall be the Site Characterization Report and a Corrective Action Remediation Report in editable electronic Microsoft Word. The report shall include information needed to verify work completed conclusions, and recommendations. The final report shall include photographs and field notes.
SITE VISITS, CONDITIONS, AND INSPECTIONS
Contractor should become familiar with the site to examine conditions under which this work is to be performed. Coordinate all site visits and work activities in advance with the Refuge On-Site Representative (OSR) and Contracting Officer Representative (COR), providing a minimum of five (5) business days of advance notice.
NOTIFICATIONS:
Contact the COTR, CO, and Refuge Representative before departing to the site. Review concerns about time lines, transportation, equipment, personnel, permits, licensing, and contingencies. Keep the CO and COTR informed of progress. Daily reports, photographs, notes, and all documentation shall become the sole property of the government.
ON-SITE WASTE MANAGEMENT
All waste generated from this contract shall be disposed of off-site according to local, state, and federal requirements. An ADEC Soil Transport Approval Form is required before removing any contaminated media from the site
ANALYSIS AND INVENTORY:
Provide documents that delineate a clear concise paper trail of how, when, and where contaminants were disposed of. This Statement of Work is not all-inclusive and shall not relieve the contractor of responsibilities as outlined in federal, state, and local regulations.
PROJECT SCHEDULE and REPORTING:
Within ten (10) work days after Notice to Proceed (NTP) shall provide a project work schedule. Verify and clarify travel, permits, payment schedules, report format, schedule of values, work plan actions, availability of equipment, etc. Coordinate existing and new data to evaluate and recommend proper course of action.
Daily reports, photographs, notes, and documentation shall become the sole property of the government.
The project shall be completed by December 31, 2026.
Contractor shall notify the Government no less than ten (10) days prior to commencement of any work activities.
AVAILABILITY: Normal duty hours, Monday thru Friday 7:30 a.m.-4:00 p.m. Non-duty hours include week nights, weekends, and federal holidays. Contractor shall request approval for any work outside normal duty hours.
PERMITS:
The Contractor shall be responsible for obtaining the necessary permits including preparing paperwork for permanent closure on behalf of the Government. Collect all data, maps, chemical analyses, etc., necessary to prepare complete and accurate report that meets the requirements of the ADEC.
Comply with inspection requirements of the State and local agencies. Inspect and ensure that no electrical, gas, water, structures, or other conditions are in the area that may affect work. Contact the local fire marshal and the public utilities office before beginning the work.
UNDERGROUND OBSTRUCTIONS:
There are no known underground piping, foundations, and other underground obstructions in the vicinity of work.
REMOVAL PROCEDURES:
Provide shoring and bracing where necessary to support existing construction and protect personnel during demolition in accordance with Occupational Safety and Health Agency’s construction standard 1926.650-652. Additional standard or codes shall apply if more stringent.
Excavated soil shall be stockpiled, stored and sampled according to 18 AAC 75.370 and the methods in the Alaska Department of Environmental Conservation’s Field Sampling Guidance. Contaminated soil disposal shall be in accordance with 18 AAC 75.325(i) and 18 AAC 75.360. A Contaminated Media Transport and Treatment or Disposal Approval Form shall be submitted prior to transporting any contaminated soils.
At completion of operations, the Contractor shall gently slope the berm using only existing clean material.
Place clean soil in 8" maximum lifts and compact to 95% maximum density as determined by ASTM D1557.
Any excavated material shall be placed in a separate stockpile pending disposal. The stockpile shall be located on an impermeable surface and shall be kept covered with plastic sheeting. Salvageable materials shall become property of Contractor and shall be removed from site as work progresses.materials or trash on site shall not be permitted. This project includes removal of up to 5 CY of contaminated soil.
DISPOSAL OF MATERIALS:
An ADEC “Contaminated Media Transport and Treatment or Disposal Approval Form “is required before removing any contaminated media from the site. Contractor shall be responsible for proper disposal of all project derived waste material. This includes, but is not limited to, recovered free product, excess excavated material, non-salvageable equipment and materials. Waste material shall be transported and disposed of using transporters and disposal facilities, which possess all required federal, state, or local licenses or permits. Submit manifests certifying destination, receipt, and disposal of demolition materials. Burning of waste lumber and other materials or trash on site shall not be permitted.
CLEANUP:
Maintain public streets, alleys, or other thoroughfares used in carrying out disposal free of litter or soil attributable to this operation. Equip and load trucks or other vehicles to prevent leakage, blowing off, or other escape of any portion of whatsoever is being hauled. Cost incurred by the Government in cleaning up such litter will be charged to Contractor and deducted from monies due or to become due it under this contract. Upon completion of work, thoroughly clean area of materials not to remain. Cleanup activities shall be in accordance with Federal, State, and Local regulations.
KEY PERSONNEL
The project team includes a Contracting Officer, Contracting Officer Representative, Program Manager, Project Manager/Lead Environmental Manager whom the Site Project Manager and Contractors reports to.
The following is an overview of personnel directly responsible for supporting the efforts of this contract.
Contracting Officer: Tiffannie Pannell, Phone: 703-468-8281, Email: tiffannie_pannell@ios.doi.gov
Contracting Officer Representative: Robert McGinn, Regional Environmental Compliance Coordinator Address: 5600 American Blvd W, Suite 990, Bloomington, MN 56001 Contact info, phone and email: (612) 518-1237, Robert_McGinn@fws.gov
Program Manager: Danielle, Fujii-Doe, Deputy Refuge Manager Address: 1390 Buskin River Road, Kodiak, Alaska 99615 Contact info, phone and email: (907) 308-6346, danielle_fujii-doe@fws.gov
Department of Environmental
Conservation
SPILL PREVENTION & RESPONSE
Contaminated Sites Program
43335 Kalifornsky Beach Road, Suite 11
Soldotna, Alaska 99669
Main: 907.262.5210
Fax: 907.262.2294 www.dec.alaska.gov
File No.: 2600.38.002
Hazard ID: 2105
December 31, 2025
Electronic Delivery Only
Robert McGinn
Regional Environmental Compliance Coordinator for Region 3 & 7
5600 American Blvd West, Suite 990
Bloomington, MN55437
Subject: Former Sheep Island Boat Maintenance Facility, Sheep Island, Uganik Bay, Kodiak
Island, Alaska – Revised Site Characterization Activities Report (December 2025)
Dear Mr. McGinn, The Alaska Department of Environmental Conservation (ADEC) Contaminated Sites Program (CSP) received and reviewed the above-referenced draft report for site assessment activities and evaluation of site conditions for the United States Fish and Wildlife (USFWS) property located on Sheep Island, Uganik Bay, Kodiak Island, Alaska. During site assessment activities and evaluation, the existing landfarm was identified and investigated, including soil sampling. Site reconnaissance was also conducted in accessible areas of the island to identify any previously unidentified environmental concerns arising from former property use, aside from the beach, where marine batteries were observed.
Diesel range organic (DRO) concentrations at the landfarm were found to exceed the ADEC cleanup criterion, with the highest concentrations of 302 mg/Kg, and the soil sample collected from where several marine batteries were found on the beach exceeded the ADEC cleanup criterion, with a concentration of 6,860 mg/Kg. Site reconnaissance efforts did not identify any additional environmental concerns beyond the marine batteries on the beach. The report further outlines recommendations for further site characterization work.
The ADEC provided initial comments on a draft of this submission on January 4, 2019. A final report addressing all the ADEC’s comments was submitted on December 18, 2025, and it has been approved.
http://www.dec.alaska.gov/
Mr. Robert McGinn 2 November 3, 2025
If you have any questions or need further assistance, please contact me at (907) 262-8203 or via email at jenny.gates@alaska.gov.
Sincerely, Jenny Gates
Environmental Program Specialist cc, via email: Jamie McKellar, ADEC mailto:jenny.gates@alaska.gov
ALASKA DEPARTMENT OF ENVIRONMENTAL CONSERVATION CONTAMINATED SITES PROGRAM
Report: Former Sheep Island Boat Maintenance Facility, Sheep Island, Uganik Bay
Site Characterization Activities Report
Bratslavsky Consulting Engineers, Inc. prepared by BGES, Inc. (August, 2017 and December 2025)
Primary Reviewer: Jamie McKellar
Response to Comments Reviewer: Jenny Gates
Comment
No.
Page/Section ADEC Comment/Recommendation: January 4, 2019
USFWS Response:
December 19, 2025
ADEC Response:
December 31, 2025
1. General
Please clarify how many marine batteries were found on the beach. BGES personnel identified at least two large marine batteries on the beaches (north and south) in the vicinity of the former boat maintenance facility that were damaged and deteriorated. Several whole and partial lead plates from within the batteries were encountered scattered along the beaches. The specific number of batteries and parts of batteries across these areas is not known.
ADEC, 12/31/2025: ADEC
acknowledges that recommendations by USFWS (Section 7.0) include further site reconnaissance and soil sampling activities to define the extent of lead contamination in all areas, determining the volume of lead-contaminated soils for remediation activities, and other associated tasks related to site characterization/investigation and remediation. Comment accepted.
Comment
No.
Page/Section ADEC Comment/Recommendation: January 4, 2019
USFWS Response:
December 19, 2025
ADEC Response:
December 31, 2025
2. General
The approved work plan states that a detailed discussion of the recommended remediation activities will be presented in the report.
However, the report only includes one sentence of site recommendations.
A discussion of recommended remediation activities has been added to Section 7 of the report.
ADEC, 12/31/2025: Comment accepted.
3. General
The approved work plan states that prior to site reconnaissance, BGES will interview the owners, the former employees of the former cannery and any other people who may have knowledge of the uses and physical characteristics of the property. The work plan also states that detailed information will be documented for all interviews and the information will be included in the field activities report.
This information was not included in the report.
Between December 4 and 10, 2025, numerous attempts were made to speak with Mike Shupe of
Polar Equipment / Polar Seafoods.
Mr. Shupe is the registered agent for a former cannery owned by
Cook Inlet Processing - Uganik, which is identified as an ADEC-listed contaminated site located in Port
O‘Brien. The former cannery in
Port O’Brien is located approximately 0.9 mile north of
Sheep Island, across the eastern arm of Uganik Bay. We received a return call from someone at Polar
Seafoods and they indicated they will request that the caretaker that stays at the former cannery, which is owned by Cook Inlet Processing, and Bill Reith (former ADEC employee), to contact us to discuss the former Sheep Island Boat
Page/Section ADEC Comment/Recommendation: January 4, 2019
USFWS Response:
December 19, 2025
ADEC Response:
December 31, 2025
Maintenance facility because they may have information about this facility. However, we have not received a return call from either
Mr. Shupe, the caretaker, or Mr.
Rieth (former ADEC employee).
We have not been able to identify any other individuals that may have information about the former Sheep
Island Boat Maintenance facility located in Uganak Bay.
We added this information to
Section 3 of the report.
ADEC, 12/31/2025: Accepted with comment. ADEC encourages USFWS to attempt to contact the relevant parties who may have information about the facility and area prior to deployment activities, and to identify interview activities in the associated work plan.
Page/Section ADEC Comment/Recommendation: January 4, 2019
USFWS Response:
December 19, 2025
ADEC Response:
December 31, 2025
4. General
The report does not include discussion of how investigation derived waste
(IDW) was handled.
All soil cuttings removed during advancement of the shallow soil borings were returned to the locations from which they originated. A dry decontamination method was utilized to remove as much soil as possible from the sampling equipment. Then a minimal amount of decontamination water was generated to complete decontamination of the hand tools.
The decontamination water was spread out over the top of the area of contaminated soil so it could infiltrate. All miscellaneous solid waste was transported to
Anchorage for disposal as general solid waste.
Page/Section ADEC Comment/Recommendation: January 4, 2019
USFWS Response:
December 19, 2025
ADEC Response:
December 31, 2025
5.
Sec. 4.1
p. 5
Soil samples were compared to the ADEC Method 2 Cleanup Criteria listed in 18 AAC 75.341 – Tables B1 and B2, Migration to Groundwater values, effective July 1, 2017…
Please note that DEC promulgated new cleanup levels on September 29, 2018.
The current ADEC cleanup levels were promulgated on October 18, 2023. The tables and text (Section
4.1 of the report) have been updated to reflect the new date in the report.
6. p. 6
…however, the arsenic concentrations were within typical background levels for Alaskan soils
Recommend adding a citation to support this statement.
A statement and reference were added to Section 4.1 (page 7) of the report.
ADEC, 12/31/2025: Arsenic in the referenced samples ranged from 4.36 –
15.0 mg/Kg and is considered background for this area. Comment
Page/Section ADEC Comment/Recommendation: January 4, 2019
USFWS Response:
December 19, 2025
ADEC Response:
December 31, 2025
7.
Laboratory Data
Review
Checklists
Page 163 of PDF, #1 – Did an ADEC CS approved laboratory receive and perform all of the submitted sample analysis? The question was answered
“No,” but no explanation is provided in the checklist or report text.
This was an error on the checklist.
The question in the checklist should have been marked as “yes”. A revised checklist was attached to the revised copy of the report.
SGS was the laboratory utilized for this project and they are an
ADECCS
approved laboratory. A copy of their accreditation was attached to the approved work plan for this project.